Receipt of Response to Generic Letter 2006-03, Potentially Nonconforming Hemyc and MT Fire Barrier Configurations (TAC Nos. MD1578 and MD1579)
ML071280045
Person / Time
Site: Farley  Southern Nuclear icon.png
Issue date: 05/14/2007
From: Cotton K
NRC/NRR/ADRO/DORL/LPLII-1
To: Rachel Johnson
Southern Nuclear Operating Co
Cotton K R, NRR/DORL, 301-415-1438
References
GL-06-003, TAC MD1578, TAC MD1579
Download: ML071280045 (3)


Text

May 14, 2007 Mr. J. Randy Johnson Vice President - Farley Joseph M. Farley Nuclear Plant 7388 North State Highway 95 Columbia, AL 36319

SUBJECT:

NRC RECEIPT OF JOSEPH M. FARLEY NUCLEAR PLANT, UNITS 1 AND 2 RESPONSE TO GENERIC LETTER 2006-03, POTENTIALLY NONCONFORMING HEMYC AND MT FIRE BARRIER CONFIGURATIONS (TAC NOS. MD1578, MD1579)

Dear Mr. Johnson:

The U.S. Nuclear Regulatory Commission (NRC) acknowledges the receipt of your response to Generic Letter 2006-03, Potentially Nonconforming Hemyc and MT Fire Barrier Configurations. Under oath or affirmation, you have stated that your nuclear power plant does not rely on either the Hemyc or MT fire barrier system. You have submitted documentation under oath or affirmation that other 1 or 3-hour fire barrier that separates redundant safe shutdown trains located within the same fire area have been designed and installed in accordance with current NRC guidance. Based on your response, the basis for stating that this other fire barrier has been designed and installed in accordance with NRC guidance should be maintained on site, and will be subject to inspection during the normal NRC inspection process.

If you have any questions regarding this response, please contact me at 301-4151438.

Sincerely,

/RA/

Karen Cotton, Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-348 and 50-364 cc: See next page

May 14, 2007 Mr. J. Randy Johnson Vice President - Farley Joseph M. Farley Nuclear Plant 7388 North State Highway 95 Columbia, AL 36319

SUBJECT:

NRC RECEIPT OF JOSEPH M. FARLEY NUCLEAR PLANT, UNITS 1 AND 2 RESPONSE TO GENERIC LETTER 2006-03, POTENTIALLY NONCONFORMING HEMYC AND MT FIRE BARRIER CONFIGURATIONS (TAC NOS. MD1578, MD1579)

Dear Mr. Johnson:

The U.S. Nuclear Regulatory Commission (NRC) acknowledges the receipt of your response to Generic Letter 2006-03, Potentially Nonconforming Hemyc and MT Fire Barrier Configurations. Under oath or affirmation, you have stated that your nuclear power plant does not rely on either the Hemyc or MT fire barrier system. You have submitted documentation under oath or affirmation that other 1 or 3-hour fire barrier that separates redundant safe shutdown trains located within the same fire area have been designed and installed in accordance with current NRC guidance. Based on your response, the basis for stating that this other fire barrier has been designed and installed in accordance with NRC guidance should be maintained on site, and will be subject to inspection during the normal NRC inspection process.

If you have any questions regarding this response, please contact me at 301-4151438.

Sincerely,

/RA/

Karen Cotton, Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-348 and 50-364 cc: See next page DISTRIBUTION:

PUBLIC RidsAcrsAcnwMailCenter LPL2-1 R/F RidsNrrLACSola (hard copy)

RidsNrrDorlLpl2-1 (EMarinos) RidsNrrDorlDpr RidsNrrPMRMartin (hard copy) RidsOgcRp RidsRgn2MailCenter (SShaeffer)

Accession No. ML071280045 OFFICE NRR/LPL2-1/PM NRR/LPL2-1/LA NRR/LPL2-1/BC NAME KCotton:nc CSola EMarinos DATE 5/8/07 5/7/07 5/14/07 OFFICIAL RECORD COPY

Joseph M. Farley Nuclear Plant, Units 1 & 2 cc:

Mr. J. Randy Johnson Vice President - Farley Joseph M. Farley Nuclear Plant 7388 North State Highway 95 Columbia, AL 36319 Mr. B. D. McKinney, Licensing Manager Southern Nuclear Operating Company, Inc.

P.O. Box 1295 Birmingham, AL 35201-1295 Mr. M. Stanford Blanton Balch and Bingham Law Firm P.O. Box 306 1710 Sixth Avenue North Birmingham, AL 35201 Mr. J. Gasser Executive Vice President Southern Nuclear Operating Company, Inc.

P.O. Box 1295 Birmingham, AL 35201 State Health Officer Alabama Department of Public Health 434 Monroe St.

Montgomery, AL 36130-1701 Chairman Houston County Commission P.O. Box 6406 Dothan, AL 36302 Resident Inspector U.S. Nuclear Regulatory Commission 7388 N. State Highway 95 Columbia, AL 36319 William D. Oldfield SAER Supervisor Southern Nuclear Operating Company, Inc.

P.O. Box 470 Ashford, AL 36312