Category:Meeting Summary
MONTHYEARML24268A0722024-09-24024 September 2024 Summary of August 28, 2024, Public Meeting to Discuss Cyber Security Regulatory Issues Regarding Wolf Creeks Implementation of Advanced Remote Monitoring Using Wireless ML24212A0372024-08-0707 August 2024 Summary of July 23, 2024, Teleconference with Wolf Creek Nuclear Operating Corporation Regarding Wolf Creek Generating Station, Unit 1, Amendment No. 237, Allowing the Use of Portable Lighting ML24088A3122024-04-0101 April 2024 Summary of March 25, 2024, Teleconference with Wolf Creek Nuclear Operating Corporation Regarding Revised Safety Evaluation for Wolf Creek Generating Station Unit 1, Amendment No. 237, Allowing the Use of Portable Lighting ML23303A2182023-11-0606 November 2023 Summary of October 16, 2023, Pre-Submittal Teleconference with Wolf Creek Nuclear Operating Corporation Regarding a License Amendment Request to Adopt TSTF-505 for Wolf Creek Generating Station, Unit 1 ML22147A0932022-06-0606 June 2022 2021 Annual Assessment Public Meeting Summary ML22011A0862022-01-11011 January 2022 Summary of January 10, 2022, Pre-Submittal Teleconference with Wolf Creek Nuclear Operating Corporation Regarding a License Amendment Request to Use Portable Lighting for Wolf Creek Generating Station, Unit 1 ML21333A1312021-12-0707 December 2021 Summary of Meeting with Wolf Creek Nuclear Operating Corporation Diesel Generator Completion Time License Amendment Request for Wolf Creek Generating Station ML21200A1102021-07-21021 July 2021 Summary of July 13, 2021, Pre-Submittal Teleconference with Wolf Creek Nuclear Operating Corporation Regarding a Temporary Emergency Preparedness Exercise Exemption Request ML21140A3892021-05-24024 May 2021 Riv Column 1 EOC 2020 Public Meeting Summary ML21127A1322021-05-11011 May 2021 Summary of April 16, 2021, Conference Call with Representatives of Wolf Creek Generating Station Regarding the Spring 2021 Steam Generator Tube Inspections ML20332A0422020-12-0101 December 2020 Summary of November 19, 2020, Pre-Submittal Teleconference with Wolf Creek Nuclear Operating Corporation an Emergency Response Organization Staffing License Amendment Request ML20332A0462020-11-30030 November 2020 Summary of November 18, 2020, Pre-Submittal Teleconference with Wolf Creek Nuclear Operating Corporation a Risk-Informed Generic Safety Issue (GSI)-191 License Amendment Request ML20189A2832020-07-0707 July 2020 Summary of Region IV Annual Assessment Public Meeting ML19143A4182019-05-21021 May 2019 Summary of Public Meeting with Wolf Creek Nuclear Operation Corporation ML19140A4742019-05-20020 May 2019 Closed Meeting with Wolf Creek Nuclear Operating Corporation to Conduct a Mediation Session Regarding Falsification of Documentation Associated with Licensee Maintenance Activities ML18313A2542018-11-16016 November 2018 Summary of Public Meeting with Wolf Creek Nuclear Operating Corporation Regarding License Amendment Request for Transition to Westinghouse Core Design and Safety Analyses for Wolf Creek Generating Station ML17276B4892017-10-23023 October 2017 9/25/17 Summary of Public Meeting with Wolf Creek Nuclear Operating Corporation Regarding the Proposed LAR for Change in Emergency Plan Staff Augmentation Response Times for Wolf Creek Generating Station (CAC No. MG0174; EPID L-2017-LRM-001 ML16271A4822016-09-27027 September 2016 Summary of Regulatory Conference to Discuss Safety Significance of Wolf Creek Generating Station Emergency Generator Excitation Diode Apparent Violation ML16250A1652016-09-0909 September 2016 8/25/16 Summary of Preapplication Meeting with Wolf Creek Nuclear Operating Corporation to Discuss Amendment Request to Transition to Westinghouse Analyses Methodologies and Alternate Source Term at Wolf Creek Generating Station ML16243A5132016-09-0101 September 2016 Summary of August 25, 2016, Public Meeting with Wolf Creek Nuclear Operating Corporation and Amerenue Regarding a Proposed Application for a New Technical Specification for the Class 1E Electrical Equipment Air Conditioning System (MF8118 a ML16106A1742016-04-22022 April 2016 Summary of Meeting with Wolf Creek Nuclear Operating Company to Discuss the Generic Safety Issue (GSI)-191 Testing Plan/Fiber Penetration and Head Loss Testing Approach for Wolf Creek Generating Station ML15182A0952015-06-30030 June 2015 Summary of Annual Assessment Meeting with Wolf Creek Nuclear Operating Corporation (WCNOC) Regarding Wolf Creek Generating Station 2014 Performance ML14188C4812014-07-0707 July 2014 Summary of Annual Assessment Meeting with Wolf Creek Generating Station ML14134A1842014-05-14014 May 2014 Summary of Public Meeting to Discuss an Apparent Violation Identified at Wolf Creek Generating Station ML14038A3852014-02-0606 February 2014 1/22/2014 - Summary of Public Meeting to Discuss Corrective Actions Implemented to Address the Chilling Effect Letter ML13221A2132013-08-12012 August 2013 8/7/2013 - Summary of Preapplication Meeting with Wolf Creek Nuclear Operating Corporation to Discuss Long-Term Corrective Actions for Water Hammer Events in the Essential Service Water System at Wolf Creek ML13221A2152013-08-12012 August 2013 7/30/2013 - Summary of Preapplication Meeting with Wolf Creek Nuclear Operating Company to Discuss Proposed Transition to Westinghouse Methodologies for Core Design and Non-LOCA Safety Analyses at Wolf Creek Generating Station ML13121A4892013-05-0101 May 2013 End of Cycle Meeting Summary 4-18-13 ML13077A0732013-04-0101 April 2013 Summary of 2/28/13 and 3/11/13 Conference Calls with Licensee and Its Contractors Ongoing Steam Generator Tube Inspection Activities During Refueling Outage 19 ML12355A6922012-12-20020 December 2012 Summary of Public Meeting with Wolf Creek Nuclear Operating Corp Re Improved Station Performance ML12276A2652012-11-0101 November 2012 Meeting Summary with Wolf Creek Nuclear Operating Corporation to Discuss Transition from Current to NRC-Approved Westinghouse Methodologies for Performing the Core Design and Non-LOCA Safety Analysis at Wolf Creek ML12191A1742012-07-0909 July 2012 6/25/2012 Summary of Public Meeting with Wolf Creek Nuclear Operating Corporation ML12191A1462012-07-0606 July 2012 6/26/2012 - Summary of Public Meeting to Discuss Performance of Wolf Creek Nuclear Operating Corporation ML13246A3802012-05-0808 May 2012 Email from M. King, NRR on Ioeb Clearinghouse Screening Summary for Tuesday, May 8, 2012 ML1207601012012-03-16016 March 2012 Summary of Public Meeting with Wolf Creek Nuclear Operating Corporation ML13246A3782012-02-16016 February 2012 Email from M. King, NRR on Ioeb Clearinghouse Screening Summary for Thursday, February 16, 2012 ML13246A3772012-01-31031 January 2012 Email from M. King, NRR on Ioeb Clearinghouse Screening Summary for Tuesday, January 31, 2012 ML13246A3762012-01-23023 January 2012 Email from M. King, NRR on Ioeb Clearinghouse Screening Summary for Monday, January 23, 2012 ML12011A1012012-01-19019 January 2012 Summary of Meeting with NEI and to Address Di&C Issues ML13246A3742012-01-17017 January 2012 Email from M. King, NRR on Ioeb Clearinghouse Screening Summary for Tuesday, January 17, 2012 ML1110104292011-04-11011 April 2011 Summary of Annual Performance Assessment Meeting with Wolf Creek Nuclear Operating Corporation to Discuss Wolf Creek Generating Station Performance for the NRC Inspection Period Ending December 31, 2010 ML1024506282010-09-0202 September 2010 Summary of Public Meeting with Wolf Creek Nuclear Operating Corporation ML1013404892010-05-14014 May 2010 Summary of Annual Performance Assessment Meeting with Wolf Creek Nuclear Operating Corporation to Discuss the Wolf Creek Generating Station Performance for the NRC Inspection Period from January 1 Through December 31, 2009 ML0933805662009-12-17017 December 2009 Summary of Meeting with Union Electric Company and Wolf Creek Nuclear Operating Company to Discuss NRC Requests for Additional Information on Generic Letter 2004-02 Sent 7/31/2009 and 8/27/2009, Respectively ML0933702032009-12-0303 December 2009 Summary of Public Meeting for Wolf Creek Generating Station ML0924607142009-09-28028 September 2009 Summary of Meeting with Union Electric Co., and Wolf Creek, to Discuss Draft Requests for Additional Information on GL 2004-02 for Callaway, Unit 1, and Wolf Creek ML0911205282009-04-21021 April 2009 Summary of Annual Performance Assessment Meeting for Wolf Creek Generating Station ML0902102062009-01-23023 January 2009 Summary of Meeting with Wolf Creek Nuclear Operating Corporation to Discuss Changes to Post Fire Shutdown Unresolved Items Analysis Methods Pre-Application for Wolf Creek Generating Station ML0829607972008-10-22022 October 2008 Summary of Meeting with Wolf Creek, Discussing Several Initiatives Being Implemented to Improve Plant Performance ML0817706682008-06-25025 June 2008 Summary of Meeting with Wolf Creek Nuclear Operating Corporation to Discuss Several Initiatives That Were Being Implemented to Improve Plant Performance at Wolf Creek 2024-09-24
[Table view] |
Text
May 22, 2007 LICENSEE: Wolf Creek Nuclear Operating Corporation FACILITY: Wolf Creek Generating Station, Unit 1
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON MARCH 7, 2007, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND WOLF CREEK NUCLEAR OPERATING CORPORATION, CONCERNING THE UPCOMING SAFETY AUDIT The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Wolf Creek Nuclear Operating Corporation held a telephone conference call on March 7, 2007, regarding the upcoming aging management programs (AMPs) and time-limited aging analyses (TLAAs) audit to be conducted at Wolf Creek Generating Station during the week of March 26, 2007.
The Enclosure shows a list of participants. During the telephone conference call the following logistical items were discussed:
- The applicant was informed that the staff will be auditing the AMPs and TLAAs. The first group of audit questions will be sent via e-mail by the end of the week. All questions and answers gathered during the audit will be collected in a database and incorporated in the docket as a publicly available document.
- The staff requested access to the TLAA basis documents. Systems descriptions, design specifications, metal fatigue analysis data, and any supporting information should be made available during the audit.
- The staff requested supporting documentation for the leak before break analysis and Fatigue Monitoring Program. Manual transients data and projections basis should be made available during the audit.
- The staff requested that dissimilar metals plant-specific operating experience should be available during the audit.
- The applicant was informed that the entrance meeting will be on Monday, March 26, 2007.
/RA/
Verónica M. Rodríguez, Project Manager License Renewal Branch B Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-482
Enclosure:
List of Participants cc w/encl: See next page
ML071240256 OFFICE PM:RLRB:DLR LA:DLR BC:RLRB:DLR NAME VRodríguez YEdmonds RAuluck DATE 05/22/07 05/22/07 05/22/07 TELEPHONE CONFERENCE CALL WOLF CREEK GENERATING STATION, UNIT 1 LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS MARCH 7, 2007 PARTICIPANTS AFFILIATIONS Verónica M. Rodríguez U.S. Nuclear Regulatory Commission (NRC)
Kenneth Chang NRC Peter Wen NRC Kaihwa Hsu NRC Surinder Arora NRC Lorrie Bell Wolf Creek Nuclear Operating Corporation (WCNOC)
Charlie Medenciy WCNOC Eric Blocher Strategic Teaming and Resource Sharing Alliance (STARS)
Arden Aldridge STARS Paul Crawley STARS Donald Stevens STARS Enclosure
Letter to Wolf Creek Nuclear Operating Corporation, from V. Rodriguez, date May 22, 2007
SUBJECT:
SUMMARY
OF CONFERENCE CALL HELD ON MARCH 7, 2007, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND WOLF CREEK NUCLEAR OPERATING CORPORATION, CONCERNING THE UPCOMING SAFETY AUDIT DISTRIBUTION:
HARD COPY:
DLR RF E-MAIL:
PUBLIC RWeisman SSmith (srs3)
SDuraiswamy RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDlrRlrc RidsNrrDlrReba RidsNrrDlrRebb RidsNrrDci RidsNrrDra RidsNrrDe RidsNrrDeEemb RidsNrrDeEeeb RidsNrrDss RidsOgcMailCenter RidsNrrAdes VRodriguez CJacobs JDonohew GPick, RIV SCochrum, RIV CLong, RIV PWen JDavis
Wolf Creek Generating Station cc:
Jay Silberg, Esq. Supervisor Licensing Pillsbury Winthrop Shaw Pittman, LLP Wolf Creek Nuclear Operating Corporation 2300 N Street, NW P.O. Box 411 Washington, DC 20037 Burlington, KS 66839 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Resident Inspectors Office/Callaway Plant 611 Ryan Plaza Drive, Suite 400 8201 NRC Road Arlington, TX 76011-7005 Steedman, MO 65077-1032 Senior Resident Inspector Kevin J. Moles, Manager U.S. Nuclear Regulatory Commission Regulatory Affairs P.O. Box 311 Wolf Creek Nuclear Operating Corporation Burlington, KS 66839 P.O. Box 411 Burlington, KS 66839 Chief Engineer, Utilities Division Kansas Corporation Commission Lorrie I. Bell, Project Manager 1500 SW Arrowhead Road Wolf Creek Nuclear Operating Corporation Topeka, KS 66604-4027 P.O. Box 411 Burlington, KS 66839 Office of the Governor State of Kansas Mr. James Ross Topeka, KS 66612 Nuclear Energy Institute 1776 I Street, NW, Suite 400 Attorney General Washington, DC 20006-3708 120 S.W. 10th Avenue, 2nd Floor Topeka, KS 66612-1597 County Clerk Coffey County Courthouse 110 South 6th Street Burlington, KS 66839 Thomas A. Conley, Section Chief Radiation and Asbestos Control Kansas Department of Health and Environment Bureau of Air and Radiation 1000 SW Jackson, Suite 310 Topeka, KS 66612-1366 Vice President Operations/Plant Manager Wolf Creek Nuclear Operating Corporation P.O. Box 411 Burlington, KS 66839