1 PSEG Nuclear LLC Annual Assessment Meeting Bridgeport Holiday Inn April 23, 2007 PSEG Nuclear LLC Annual Assessment Meeting Bridgeport Holiday Inn April 23, 2007
2 Introduction and Overview William Levis President and CNO PSEG Nuclear LLC Introduction and Overview William Levis President and CNO PSEG Nuclear LLC
3 CNO Introduction and Overview CNO Introduction and Overview Salem and Hope Creek are being operated safely Plant performance has improved Improved the work environment
Operationally focused organization
Clear roles and responsibilities
Consistent direction
Accountability
4 How we execute day to day will not change.
How we manage the corporate support functions will be determined.
Establish Independent Operation Establish Independent Operation Stage 1 Identify Requirements (Jan-Mar)
Determine organization required Complete leadership staffing Review Management Model Controls Identify Critical Skill Gaps Identify industry participation and support Stage 2 Create Plan (Mar-Jun)
Develop plan to resume functions from Exelon
- Transition into station organization
- Transition into Corporate Function
- Transition into Operations Support Organization
- Outsource
- Eliminate Complete organization staffing Stage 3 Execute Plan (Jul-Dec)
Implement Plan Check and adjust accordingly Resume Corporate Support Resume Corporate Support Resume Corporate Support Continue Day to Day Management Model Execution Continue Day to Day Management Model Execution Continue Day to Day Management Model Execution
5 Salem Performance Tom Joyce Vice President, Salem Generating Station PSEG Nuclear LLC Salem Performance Tom Joyce Vice President, Salem Generating Station PSEG Nuclear LLC
6 Salem Accomplishments Salem Accomplishments Work Force Alignment Equipment Reliability Station / Outage Performance
7 Salem Focus Areas Salem Focus Areas Human Performance Equipment Reliability Station / Outage Performance Transition / Stay the Course
8 Hope Creek Performance George Barnes Vice President, Hope Creek Generating Station PSEG Nuclear LLC Hope Creek Performance George Barnes Vice President, Hope Creek Generating Station PSEG Nuclear LLC
9 Hope Creek Accomplishments Hope Creek Accomplishments Work Force Alignment Equipment Reliability Station / Outage Performance
10 Hope Creek Focus Areas Hope Creek Focus Areas Human Performance Equipment Reliability Station / Outage Performance Transition / Stay the Course
11 Closing Remarks William Levis President and CNO PSEG Nuclear LLC Closing Remarks William Levis President and CNO PSEG Nuclear LLC
12 Common Site Objectives Common Site Objectives Act as One
Outage Support
Oversight Support
Shared Goals - Director and above Life Extension
13 Closing Remarks Closing Remarks Improvement efforts have yielded the expected results Our performance has continued to improve We have a healthy work environment Continue to strive for industry best performance Results through Focus, Accountability, and Engagement