Response to Generic Letter 2006-02, Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power
ML071060279
Person / Time
Site: Cooper Entergy icon.png
Issue date: 04/19/2007
From: Lyon C
NRC/NRR/ADRO/DORL/LPLIV
To: Minahan S
Nebraska Public Power District (NPPD)
Lyon C Fred, NRR/DORL/LPL4, 301-415-2296
References
TAC MD0969
Download: ML071060279 (5)


Text

April 19, 2007 Mr. Stewart B. Minahan Vice President-Nuclear and CNO Nebraska Public Power District 72676 648A Avenue Brownville, NE 68321

SUBJECT:

COOPER NUCLEAR STATION - RESPONSE TO GENERIC LETTER 2006-02, GRID RELIABILITY AND THE IMPACT ON PLANT RISK AND THE OPERABILITY OF OFFSITE POWER (TAC NO. MD0969)

Dear Mr. Minahan:

On February 1, 2006, the U.S. Nuclear Regulatory Commission (NRC) issued Generic Letter (GL) 2006-02, Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power (Agencywide Document Access and Management System (ADAMS) Accession No. ML060180352), to all holders of operating licenses for nuclear power reactors, except those who have permanently ceased operation and have certified that fuel has been removed from the reactor vessel. GL 2006-02 notified licensees of the NRC staffs need for information in the following four areas:

(1) use of protocols between the nuclear power plant (NPP) and the transmission system operator (TSO), independent system operator (ISO), or reliability coordinator/authority (RC/RA) and the use of transmission load flow analysis tools (analysis tools) by TSOs to assist NPPs in monitoring grid conditions to determine the operability of offsite power systems under plant technical specifications (TSs). (The TSO, ISO, or RA/RC is responsible for preserving the reliability of the local transmission system. In this GL, the term TSO is used to denote these entities.);

(2) use of NPP/TSO protocols and analysis tools by TSOs to assist NPPs in monitoring grid conditions for consideration in maintenance risk assessments; (3) offsite power restoration procedures in accordance with Section 2 of NRC Regulatory Guide (RG) 1.155, Station Blackout; and (4) losses of offsite power caused by grid failures at a frequency equal to or greater than once in 20 site-years in accordance with RG 1.155.

Subsequent to the GL, the NRC issued a Request for Additional Information (RAI) (ADAMS Accession No. ML063380308), regarding the resolution of GL 2006-02 to 63 of 65 holders of operating licenses for nuclear power reactors. The RAI requested that licensees respond to questions in the following areas:

(1) Switchyard Minimum Voltage;

S. B. Minahan (2) Loss of Real-Time Contingency Analysis (RTCA) Capability; (3) Verification of RTCA Predicted Post-Trip Voltage; (4) Identification of Applicable Single Contingencies; (5) Seasonal Variation in Grid Stress (Reliability and Loss-of-offsite Power (LOOP)

Probability; and (6) Interface With Transmission System Operator During Extended Plant Maintenance.

By letters dated March 30, 2006 (ADAMS Accession No. ML060940419), and January 31, 2007 (ADAMS Accession No. ML070360038), you responded to the information request of GL 2006-02 and the subsequent RAI. Based on the information you provided, the staff has concluded that compliance is being maintained with NRC regulatory requirements governing electric power sources and associated personnel training and considers your response to GL 2006-02 complete.

If you have any questions regarding this matter, please contact me 301-415-2296.

Sincerely,

/RA/

Carl F. Lyon, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-298 cc: See next page

ML060940419), and January 31, 2007 (ADAMS Accession No. ML070360038), you responded to the information request of GL 2006-02 and the subsequent RAI. Based on the information you provided, the staff has concluded that compliance is being maintained with NRC regulatory requirements governing electric power sources and associated personnel training and considers your response to GL 2006-02 complete.

If you have any questions regarding this matter, please contact me 301-415-2296.

Sincerely,

/RA/

Carl F. Lyon, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-298 cc: See next page DISTRIBUTION:

PUBLIC LPLIV Reading RidsAcrsAcnwMailCenter RidsNrrDeEeeb RidsNrrDprPgcb RidsNrrDorlLpl4 RidsNrrLAJBurkhardt RidsNrrPMFLyon RidsOgcRp RidsRgn4MailCenter JRobinson, NRR ADAMS Accession No.: ML071060279 OFFICE LPL4/PM LPL4/LA EEEB/BC LPL4/BC NAME FLyon JBurkhardt GWilson THiltz DATE 4/18/07 4/18/07 4/18/07 4/19/07 Cooper Nuclear Station cc:

Mr. Ronald D. Asche Mr. H. Floyd Gilzow President and Chief Executive Officer Deputy Director for Policy Nebraska Public Power District Missouri Department of Natural Resources 1414 15th Street P.O. Box 176 Columbus, NE 68601 Jefferson City, MO 65102-0176 Mr. Gene Mace Senior Resident Inspector Nuclear Asset Manager U.S. Nuclear Regulatory Commission Nebraska Public Power District P.O. Box 218 P.O. Box 98 Brownville, NE 68321 Brownville, NE 68321 Regional Administrator, Region IV Mr. John C. McClure U.S. Nuclear Regulatory Commission Vice President and General Counsel 611 Ryan Plaza Drive, Suite 400 Nebraska Public Power District Arlington, TX 76011 P.O. Box 499 Columbus, NE 68602-0499 Director, Missouri State Emergency Management Agency Mr. Paul V. Fleming P.O. Box 116 Licensing Manager Jefferson City, MO 65102-0116 Nebraska Public Power District P.O. Box 98 Chief, Radiation and Asbestos Brownville, NE 68321 Control Section Kansas Department of Health Mr. Michael J. Linder, Director and Environment Nebraska Department of Environmental Bureau of Air and Radiation Quality 1000 SW Jackson P.O. Box 98922 Suite 310 Lincoln, NE 68509-8922 Topeka, KS 66612-1366 Chairman Mr. Donald A. Flater Nemaha County Board of Commissioners Radiation Control Program Director Nemaha County Courthouse Bureau of Radiological Health 1824 N Street Iowa Department of Public Health Auburn, NE 68305 Lucas State Office Building, 5th Floor 321 East 12th Street Ms. Julia Schmitt, Manager Des Moines, IA 50319 Radiation Control Program Nebraska Health & Human Services R & L Mr. Daniel K. McGhee Public Health Assurance Bureau of Radiological Health 301 Centennial Mall, South Iowa Department of Public Health P.O. Box 95007 Lucas State Office Building, 5th Floor Lincoln, NE 68509-5007 321 East 12th Street Des Moines, IA 50319 February 2007

Cooper Nuclear Station cc:

Mr. Keith G. Henke, Planner Mr. John F. McCann, Director Division of Community and Public Health Licensing, Entergy Nuclear Northeast Office of Emergency Coordination Entergy Nuclear Operations, Inc.

930 Wildwood P.O. Box 570 440 Hamilton Avenue Jefferson City, MO 65102 White Plains, NY 10601-1813 Mr. Kevin V. Chambliss, Director of Nuclear Safety Assurance Nebraska Public Power District P.O. Box 98 Brownville, NE 68321 February 2007