ML071060269

From kanterella
Jump to navigation Jump to search

Response to Generic Letter 2006-02, Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power
ML071060269
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 04/19/2007
From: Lyon C
NRC/NRR/ADRO/DORL/LPLIV
To: Parrish J
Energy Northwest
Lyon C Fred, NRR/DORL/LPL4, 301-415-2296
References
TAC MD0966
Download: ML071060269 (4)


Text

April 19, 2007 Mr. J. V. Parrish Chief Executive Officer Energy Northwest P.O. Box 968 (Mail Drop 1023)

Richland, WA 99352-0968

SUBJECT:

COLUMBIA GENERATING STATION - RESPONSE TO GENERIC LETTER 2006-02, GRID RELIABILITY AND THE IMPACT ON PLANT RISK AND THE OPERABILITY OF OFFSITE POWER (TAC NO. MD0966)

Dear Mr. Parrish:

On February 1, 2006, the U.S. Nuclear Regulatory Commission (NRC) issued Generic Letter (GL) 2006-02, Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power (Agencywide Document Access and Management System (ADAMS) Accession No. ML060180352), to all holders of operating licenses for nuclear power reactors, except those who have permanently ceased operation and have certified that fuel has been removed from the reactor vessel. GL 2006-02 notified licensees of the NRC staffs need for information in the following four areas:

(1) use of protocols between the nuclear power plant (NPP) and the transmission system operator (TSO), independent system operator (ISO), or reliability coordinator/authority (RC/RA) and the use of transmission load flow analysis tools (analysis tools) by TSOs to assist NPPs in monitoring grid conditions to determine the operability of offsite power systems under plant technical specifications (TSs). (The TSO, ISO, or RA/RC is responsible for preserving the reliability of the local transmission system. In this GL, the term TSO is used to denote these entities.);

(2) use of NPP/TSO protocols and analysis tools by TSOs to assist NPPs in monitoring grid conditions for consideration in maintenance risk assessments; (3) offsite power restoration procedures in accordance with Section 2 of NRC Regulatory Guide (RG) 1.155, Station Blackout; and (4) losses of offsite power caused by grid failures at a frequency equal to or greater than once in 20 site-years in accordance with RG 1.155.

Subsequent to the GL, the NRC issued a Request for Additional Information (RAI) (ADAMS Accession No. ML063380308), regarding the resolution of GL 2006-02 to 63 of 65 holders of operating licenses for nuclear power reactors. The RAI requested that licensees respond to questions in the following areas:

(1)

Switchyard Minimum Voltage;

J. V. Parrish (2)

Loss of Real-Time Contingency Analysis (RTCA) Capability; (3)

Verification of RTCA Predicted Post-Trip Voltage; (4)

Identification of Applicable Single Contingencies; (5)

Seasonal Variation in Grid Stress (Reliability and Loss-of-offsite Power (LOOP)

Probability; and (6)

Interface With Transmission System Operator During Extended Plant Maintenance.

By letters dated April 3, 2006 (ADAMS Accession No. ML061010040, non-publicly available),

June 15, 2006 (ADAMS Accession No. ML061780425), and January 25, 2007 (ADAMS Accession No. ML070370406), you responded to the information request of GL 2006-02 and the subsequent RAI. Based on the information you provided, the staff has concluded that compliance is being maintained with NRC regulatory requirements governing electric power sources and associated personnel training and considers your response to GL 2006-02 complete.

If you have any questions regarding this matter, please contact me 301-415-2296.

Sincerely,

/RA/

Carl F. Lyon, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-397 cc: See next page

ML061010040, non-publicly available),

June 15, 2006 (ADAMS Accession No. ML061780425), and January 25, 2007 (ADAMS Accession No. ML070370406), you responded to the information request of GL 2006-02 and the subsequent RAI. Based on the information you provided, the staff has concluded that compliance is being maintained with NRC regulatory requirements governing electric power sources and associated personnel training and considers your response to GL 2006-02 complete.

If you have any questions regarding this matter, please contact me 301-415-2296.

Sincerely,

/RA/

Carl F. Lyon, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-397 cc: See next page DISTRIBUTION:

PUBLIC LPLIV Reading RidsAcrsAcnwMailCenter RidsNrrDeEeeb RidsNrrDprPgcb RidsNrrDorlLpl4 RidsNrrLAJBurkhardt RidsNrrPMFLyon RidsOgcRp RidsRgn4MailCenter JRobinson, NRR ADAMS Accession No.: ML071060269 OFFICE LPL4/PM LPL4/LA EEEB/BC LPL4/BC NAME FLyon JBurkhardt GWilson THiltz DATE 4/18/07 4/18/07 4/18/07 4/19/07

April 2007 Columbia Generating Station cc:

Chairman Energy Facility Site Evaluation Council P.O. Box 43172 Olympia, WA 98504-3172 Mr. Douglas W. Coleman (Mail Drop PE20)

Manager, Regulatory Programs Energy Northwest P.O. Box 968 Richland, WA 99352-0968 Chairman Benton County Board of Commissioners P.O. Box 190 Prosser, WA 99350-0190 Mr. William A. Horin, Esq.

Winston & Strawn 1700 K Street, N.W.

Washington, DC 20006-3817 Mr. Matt Steuerwalt Executive Policy Division Office of the Governor P.O. Box 43113 Olympia, WA 98504-3113 Ms. Lynn Albin Washington State Department of Health P.O. Box 7827 Olympia, WA 98504-7827 Technical Services Branch Chief FEMA Region X 130 228th Street, S.W.

Bothell, WA 98201-9796 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-4005 Senior Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 69 Richland, WA 99352-0069 Assistant Director Nuclear Safety and Energy Siting Division Oregon Department of Energy 625 Marion Street NE Salem, OR 97301-3742 Special Hazards Program Manager Washington Emergency Management Div.

127 W. Clark Street Pasco, WA 99301