MONTHYEARML23165A2342023-03-0303 March 2023 News Release-23-019: NRC Issues Annual Assessments for Nations Nuclear Power Plants ML22153A1312022-05-24024 May 2022 News Release-III-22-014: NRC to Hold Webinar to Discuss 2021 Performance of Dresden and Quad Cities Nuclear Power Plants Press Release-III-21-014, NRC Names New Resident Inspector at Quad Cities Nuclear Power Plant2021-06-23023 June 2021 Press Release-III-21-014: NRC Names New Resident Inspector at Quad Cities Nuclear Power Plant Press Release-III-21-012, NRC to Hold Virtual Meeting to Discuss 2020 Performance of Dresden and Quad Cities Nuclear Power Plants2021-06-22022 June 2021 Press Release-III-21-012: NRC to Hold Virtual Meeting to Discuss 2020 Performance of Dresden and Quad Cities Nuclear Power Plants Press Release-III-21-001, NRC Names New Senior Resident Inspector at Quad Cities Nuclear Power Plant2021-01-0505 January 2021 Press Release-III-21-001: NRC Names New Senior Resident Inspector at Quad Cities Nuclear Power Plant Press Release-III-20-009, NRC to Hold Virtual Meeting to Discuss 2019 Performance of Dresden and Quad Cities Nuclear Power Plants2020-07-23023 July 2020 Press Release-III-20-009: NRC to Hold Virtual Meeting to Discuss 2019 Performance of Dresden and Quad Cities Nuclear Power Plants Press Release-III-19-008, NRC to Hold Open House to Discuss 2018 Performance of Quad Cities Nuclear Power Station2019-04-24024 April 2019 Press Release-III-19-008: NRC to Hold Open House to Discuss 2018 Performance of Quad Cities Nuclear Power Station Press Release-III-18-018, NRC to Hold Open House to Discuss 2017 Performance of Quad Cities Nuclear Power Plant2018-05-24024 May 2018 Press Release-III-18-018: NRC to Hold Open House to Discuss 2017 Performance of Quad Cities Nuclear Power Plant Press Release-III-17-011, NRC to Conduct Open House to Discuss 2016 Performance of Quad Cities Nuclear Power Plant2017-05-17017 May 2017 Press Release-III-17-011: NRC to Conduct Open House to Discuss 2016 Performance of Quad Cities Nuclear Power Plant Press Release-III-16-006, NRC to Hold Open House to Discuss Agency'S Assessment of Quad Cities Nuclear Power Plant2016-05-0303 May 2016 Press Release-III-16-006: NRC to Hold Open House to Discuss Agency'S Assessment of Quad Cities Nuclear Power Plant Press Release-III-14-021, NRC Schedules Open House June 17 to Discuss Performance of Quad Cities Nuclear Power Station2014-06-11011 June 2014 Press Release-III-14-021: NRC Schedules Open House June 17 to Discuss Performance of Quad Cities Nuclear Power Station Press Release-III-14-015, NRC Names New Senior Resident Inspector at Quad Cities Nuclear Station2014-05-0505 May 2014 Press Release-III-14-015: NRC Names New Senior Resident Inspector at Quad Cities Nuclear Station Press Release-III-14-013, NRC Monitoring Alert at Quad Cities Nuclear Power Plant2014-04-0202 April 2014 Press Release-III-14-013: NRC Monitoring Alert at Quad Cities Nuclear Power Plant Press Release-III-13-022, NRC Will Hold a June 11 Open House on Quad Cities Nuclear Power Plant 2012 Performance2013-06-0303 June 2013 Press Release-III-13-022: NRC Will Hold a June 11 Open House on Quad Cities Nuclear Power Plant 2012 Performance Press Release-III-12-020, NRC Schedules June 12 Open House to Discuss Quad Cities Nuclear Power Station Performance and NRC Oversight2012-06-0404 June 2012 Press Release-III-12-020: NRC Schedules June 12 Open House to Discuss Quad Cities Nuclear Power Station Performance and NRC Oversight Press Release-III-11-003, NRC Schedules Open House for April 5 to Discuss Quad Cities Nuclear Power Plant Performance and NRC Oversight2011-03-28028 March 2011 Press Release-III-11-003: NRC Schedules Open House for April 5 to Discuss Quad Cities Nuclear Power Plant Performance and NRC Oversight Press Release-III-10-025, NRC Schedules Open House to Discuss Quad Cities Nuclear Power Plant Performance and Related Issues June 152010-06-11011 June 2010 Press Release-III-10-025: NRC Schedules Open House to Discuss Quad Cities Nuclear Power Plant Performance and Related Issues June 15 Press Release-III-09-008, NRC to Discuss 2008 Performance Assessment for Quad Cities Nuclear Power Plant Unit 1 and 22009-03-31031 March 2009 Press Release-III-09-008: NRC to Discuss 2008 Performance Assessment for Quad Cities Nuclear Power Plant Unit 1 and 2 Press Release-III-08-037, NRC Names New Resident Inspector at Quad Cities Nuclear Power Plant2008-09-22022 September 2008 Press Release-III-08-037: NRC Names New Resident Inspector at Quad Cities Nuclear Power Plant Press Release-III-08-022, NRC to Discuss 2007 Performance Assessment for Quad Cities Unit 1 and 2 Nuclear Power Plant2008-05-19019 May 2008 Press Release-III-08-022: NRC to Discuss 2007 Performance Assessment for Quad Cities Unit 1 and 2 Nuclear Power Plant Press Release-III-07-016, NRC to Discuss 2006 Performance Assessment for Quad Cities Nuclear Power Plant2007-04-12012 April 2007 Press Release-III-07-016: NRC to Discuss 2006 Performance Assessment for Quad Cities Nuclear Power Plant Press Release-III-06-027, NRC Finds Inadequate Valve Analysis Prior to Power Uprate to Be of Low to Moderate Safety Significance2006-06-30030 June 2006 Press Release-III-06-027: NRC Finds Inadequate Valve Analysis Prior to Power Uprate to Be of Low to Moderate Safety Significance Press Release-III-06-025, NRC to Discuss 2005 Performance Assessment for Quad Cities Nuclear Power Plant2006-06-12012 June 2006 Press Release-III-06-025: NRC to Discuss 2005 Performance Assessment for Quad Cities Nuclear Power Plant ML0613504212006-05-11011 May 2006 NRC News - NRC Region III Tritium Inspection Activities ML0613201402006-05-11011 May 2006 NRC News Dated 5/11/2006 NRC Region III Tritium Inspection Activities Press Release-III-06-002, NRC Begins Special Inspection at Quad Cities Nuclear Plant2006-01-10010 January 2006 Press Release-III-06-002: NRC Begins Special Inspection at Quad Cities Nuclear Plant Press Release-III-05-026, NRC to Discuss 2004 Performance Assessment for Quad Cities Nuclear Power Plant2005-05-19019 May 2005 Press Release-III-05-026: NRC to Discuss 2004 Performance Assessment for Quad Cities Nuclear Power Plant Press Release-04-138, NRC Renews Licenses for Dresden and Quad Cities Nuclear Power Plants for an Additional 20 Years2004-10-28028 October 2004 Press Release-04-138: NRC Renews Licenses for Dresden and Quad Cities Nuclear Power Plants for an Additional 20 Years Press Release-04-083, NRC Finds No Significant Environmental Impacts from Extended Operation of Dresden and Quad Cities Nuclear Plants2004-07-0808 July 2004 Press Release-04-083: NRC Finds No Significant Environmental Impacts from Extended Operation of Dresden and Quad Cities Nuclear Plants Press Release-III-04-025, NRC to Meet with Exelon Generation Company to Discuss Performance of Quad Cities Nuclear Plant2004-04-22022 April 2004 Press Release-III-04-025: NRC to Meet with Exelon Generation Company to Discuss Performance of Quad Cities Nuclear Plant Press Release-I-03-045, NRC to Meet with Exelon to Discuss Status of Company'S Reactors2003-07-28028 July 2003 Press Release-I-03-045: NRC to Meet with Exelon to Discuss Status of Company'S Reactors Press Release-03-093, NRC to Hold Public Meeting July 25 on Quad Cities Nuclear Plant Steam Dryer Cracks and Future Uprates2003-07-16016 July 2003 Press Release-03-093: NRC to Hold Public Meeting July 25 on Quad Cities Nuclear Plant Steam Dryer Cracks and Future Uprates Press Release-III-03-044, NRC Special Inspection of Reactor Component Damage at Quad Cities2003-06-23023 June 2003 Press Release-III-03-044: NRC Special Inspection of Reactor Component Damage at Quad Cities Press Release-III-03-034, Special Inspection Team to Review Valve Failure at Quad Cities Plant2003-04-17017 April 2003 Press Release-III-03-034: Special Inspection Team to Review Valve Failure at Quad Cities Plant Press Release-III-03-013, NRC to Meet with Exelon Nuclear Officials to Discuss Safety Performance at Quad Cities Nuclear Power Plant2003-03-26026 March 2003 Press Release-III-03-013: NRC to Meet with Exelon Nuclear Officials to Discuss Safety Performance at Quad Cities Nuclear Power Plant Press Release-III-02-008, NRC to Meet with Exelon Generation Co. April 2 to Discuss Quad Cities Nuclear Power Station Performance2002-03-27027 March 2002 Press Release-III-02-008: NRC to Meet with Exelon Generation Co. April 2 to Discuss Quad Cities Nuclear Power Station Performance Press Release-III-02-001, NRC Begins Special Inspection of Pump Problem at Quad Cities Plant2002-01-16016 January 2002 Press Release-III-02-001: NRC Begins Special Inspection of Pump Problem at Quad Cities Plant 2023-03-03
[Table view] |
Text
NRC NEWS U.S. NUCLEAR REGULATORY COMMISSION 2443 Warrenville Road Lisle IL 60532 Web Site: http://www.nrc.gov E-mail: opa3@nrc.gov No. III-07-016 April 12, 2007 CONTACT: Viktoria Mitlyng (630) 829-9662 NRC TO DISCUSS 2006 PERFORMANCE ASSESSMENT FOR QUAD CITIES NUCLEAR POWER PLANT The Nuclear Regulatory Commission staff will meet with representatives of Exelon Generation Co. on Wednesday, Apr. 18, to discuss the agencys assessment of safety performance for last year at the Quad Cities Nuclear Power Plant. The plant is located near Cordova, Ill..
The meeting, which will be open to the public, is scheduled to begin at 6 p.m. at the Best Western Steeplegate Inn, 100 West 76th Street, in Davenport, Iowa. The NRC staff will present the results of the assessment and be available to respond to questions or comments from the public before the close of the meeting.
The NRC continually reviews the performance of the Quad Cities plant and the nations other commercial nuclear power facilities, NRC Region III Administrator James Caldwell said. This meeting will provide an opportunity for a discussion of our annual assessment of safety performance with the company and with local officials and residents who live near the plant. Our goal is to explain the NRC oversight process and make as much information as possible available to the public regarding our regulation of these facilities.
A letter sent from the NRC Region III Office to plant officials addresses the performance of the plant during the period and will serve as the basis for the meeting discussion. It is available on the NRC web site at: http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/LETTERS/quad_2006q4.pdf.
The NRCs assessment concluded that the Quad Cities plant operated safely during the period.
The NRC uses color-coded inspection findings and performance indicators to assess nuclear plant performance. The colors start with green and then increase to white, yellow or red, commensurate with the safety significance of the issues involved.
During 2006, there was one white inspection finding of low-to-moderate safety significance at Quad Cities, Unit 1. This finding was associated with the failure to verify that the design of the electromatic relief valve actuators would not be damaged by increased vibrations produced by operation at extended power uprate power levels.
As a result, in addition to regular, baseline inspections during calendar year 2007, the NRC conducted a supplemental inspection on Unit 1 to review the plants corrective actions on this issue.
All of the inspection findings and performance indicators for Quad Cities, Unit 2, during 2006 were determined to be green.
As a result of this performance, the NRC will conduct the normal, baseline level of inspections on Unit 2 during calendar year 2007.
Routine inspections are performed by two NRC Resident Inspectors assigned to the plant and by inspection specialists from the Region III Office in Lisle, Ill., and the agencys headquarters in Rockville, Md. Among the areas of plant operations to be inspected this year by NRC specialists are modifications, maintenance effectiveness, radioactive material processing and transportation; radiological environmental monitoring program and radioactive material control; performance indicator verification; and operation of an independent spent fuel storage facility.
Current performance information for Quad Cities is available on the NRCs web site at:
http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/QUAD1/quad1_chart.html for Unit 1 and http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/QUAD2/quad2_chart.html for Unit 2.