April 12, 2007 Mr. Biff Bradley, Manager Risk Assessment Nuclear Energy Institute Suite 400 1776 I Street, NW Washington, DC 20006-3708
SUBJECT:
DRAFT SAFETY EVALUATION FOR NUCLEAR ENERGY INSTITUTE (NEI)
TOPICAL REPORT (TR) NEI 06-09, RISK-INFORMED TECHNICAL SPECIFICATIONS INITIATIVE 4B, RISK-MANAGED TECHNICAL SPECIFICATIONS (RMTS) GUIDELINES (TAC NO. MD4995)
Dear Mr. Bradley:
During a December 16, 2003, public meeting, the NEI representatives provided Interim Report 1002965, Risk-Managed Technical Specifications (RMTS) Guidelines, dated October 2003 to the U.S. Nuclear Regulatory Commission (NRC) staff. By letter dated November 13, 2006, it was supplemented by a final version, TR NEI 06-09 entitled Risk-Informed Technical Specifications Initiative 4B, Risk-Managed Technical Specifications (RMTS) Guidelines, to the NRC staff for review. Enclosed for NEI's review and comment is a copy of the NRC staff's draft safety evaluation (SE) for TR NEI 06-09.
Twenty working days are provided to you to comment on any factual errors or clarity concerns contained in the SE. The final SE will be issued after making any necessary changes and will be made publicly available. The NRC staff's disposition of your comments on the draft SE will be discussed in the final SE.
To facilitate the NRC staff's review of your comments, please provide a marked-up copy of the draft SE showing proposed changes and provide a summary table of the proposed changes.
If you have any questions, please contact Tanya Mensah at 301-415-3610.
Sincerely,
/RA/
Stacey L. Rosenberg, Chief Special Projects Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Project No. 689
Enclosure:
Draft SE cc w/encl: See next page
Nuclear Energy Institute Project No. 689 cc:
Mr. Anthony Pietrangelo, Vice President Mr. Alexander Marion, Executive Director Regulatory Affairs Nuclear Operations & Engineering Nuclear Energy Institute Nuclear Energy Institute 1776 I Street, NW, Suite 400 1776 I Street, NW, Suite 400 Washington, DC 20006-3708 Washington, DC 20006-3708 arp@nei.org am@nei.org Mr. Jack Roe, Director Mr. Jay Thayer, Vice President Operations Support Nuclear Operations Nuclear Energy Institute Nuclear Energy Institute 1776 I Street, NW, Suite 400 1776 I Street, NW, Suite 400 Washington, DC 20006-3708 Washington, DC 20006-3708 jwr@nei.org jkt@nei.org Mr. Charles B. Brinkman Mr. John Butler, Director Washington Operations Safety-Focused Regulation ABB-Combustion Engineering, Inc. Nuclear Energy Institute 12300 Twinbrook Parkway, Suite 330 1776 I Street, NW, Suite 400 Rockville, MD 20852 Washington, DC 20006-3708 brinkmcb@westinghouse.com jcb@nei.org Mr. Gary L. Vine, Executive Director Mike Melton, Senior Project Manager Federal and Industry Activities, Nuclear 1776 I Street, NW, Suite 400 Sector Washington, DC 20006-3708 EPRI man@nei.org 2000 L Street, NW, Suite 805 Washington, DC 20036 Mr. James H. Riley, Director gvine@epri.com Engineering Nuclear Energy Institute Mr. James Gresham, Manager 1776 I Street, NW Regulatory Compliance and Plant Licensing Washington, DC 20006-3708 Westinghouse Electric Company jhr@nei.org P.O. Box 355 Pittsburgh, PA 15230-0355 greshaja@westinghouse.com Ms. Barbara Lewis Assistant Editor Platts, Principal Editorial Office 1200 G St., N.W., Suite 1100 Washington, DC 20005 Barbara_lewis@platts.com 3/8/07
Mr. Biff Bradley, Manager April 12, 2007 Risk Assessment Nuclear Energy Institute Suite 400 1776 I Street, NW Washington, DC 20006-3708
SUBJECT:
DRAFT SAFETY EVALUATION FOR NUCLEAR ENERGY INSTITUTE (NEI)
TOPICAL REPORT (TR) NEI 06-09, RISK-INFORMED TECHNICAL SPECIFICATIONS INITIATIVE 4B, RISK-MANAGED TECHNICAL SPECIFICATIONS (RMTS) GUIDELINES (TAC NO. MD4995)
Dear Mr. Bradley:
During a December 16, 2003, public meeting, the NEI representatives provided Interim Report 1002965, Risk-Managed Technical Specifications (RMTS) Guidelines, dated October 2003 to the U.S. Nuclear Regulatory Commission (NRC) staff. By letter dated November 13, 2006, it was supplemented by a final version, TR NEI 06-09 entitled Risk-Informed Technical Specifications Initiative 4B, Risk-Managed Technical Specifications (RMTS) Guidelines, to the NRC staff for review. Enclosed for NEI's review and comment is a copy of the NRC staff's draft safety evaluation (SE) for TR NEI 06-09.
Twenty working days are provided to you to comment on any factual errors or clarity concerns contained in the SE. The final SE will be issued after making any necessary changes and will be made publicly available. The NRC staff's disposition of your comments on the draft SE will be discussed in the final SE.
To facilitate the NRC staff's review of your comments, please provide a marked-up copy of the draft SE showing proposed changes and provide a summary table of the proposed changes.
If you have any questions, please contact Tanya Mensah at 301-415-3610.
Sincerely,
/RA/
Stacey L. Rosenberg, Chief Special Projects Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Project No. 689
Enclosure:
Draft SE cc w/encl: See next page DISTRIBUTION:
PUBLIC PSPB Reading File RidsNrrDpr RTjader RidsNrrDprPspb RidsNrrPMTMensah RidsNrrLADBaxley RidsOgcMailCenter RidsAcrsAcnwMailCenter SRosenberg (HardCopy)
ADAMS ACCESSION NOS.:Package: ML070930481 Letter: ML070930309 Draft SE: ML070930461 NRR-043 OFFICE PSPB/PM PSPB/LA PSPB/BC ITSB/BC APLA/BC NAME TMensah DBaxley SRosenberg TKobetz MRubin DATE 04/ 12 /07 04/ 12 /07 04/12 /07 03/29/07 2/22/07 OFFICE SPWB/BC EEEB/BC EICB/BC NAME JNakoski GWilson AHowe DATE 3/12/07 3/1/07 3/28/07 OFFICIAL RECORD COPY