April 9, 2007 Mr. Terry J. Garrett Vice President Engineering Wolf Creek Nuclear Operating Corporation P.O. Box 411 Burlington, KS 66839
SUBJECT:
REVISION OF SCHEDULE FOR THE CONDUCT OF REVIEW OF THE WOLF CREEK GENERATING STATION, UNIT 1, LICENSE RENEWAL APPLICATION
Dear Mr. Garrett:
Enclosed is a revised schedule for review of the Wolf Creek Generating Station, Unit 1, license renewal application. The original schedule was affected because the NRC operated for several months under a Continuing Resolution. Therefore, the schedule has been revised to add four months that will allow us to recover from this delay. If you have any questions on the revised schedule, please contact me by telephone at 301-415-3703 or via e-mail at VMR1@nrc.gov.
Sincerely,
/RA/
Verónica M. Rodríguez, Project Manager License Renewal Branch B Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-482
Enclosure:
Revised Schedule cc w/encl: See next page
ML070930175 OFFICE LA:DLR PM:RLRB:DLR PM:REBB:DLR BC:REBB:DLR BC:RLRB:DLR NAME IKing VRodríguez CJacobs RFranovich RAuluck DATE 04/04/07 04/09/07 04/05/07 04/05/07 04/09/07
Enclosure WOLF CREEK GENERATING STATION, UNIT 1 LICENSE RENEWAL APPLICATION REVISION OF SCHEDULE Milestone Schedule Actual Receive License Renewal Application (LRA) 09/27/06 10/04/06 Publish Federal Register Notice (FRN) - LRA receipt and availability 10/14/06 10/12/06 Publish FRN - LRA acceptability, environmental scoping period, and opportunity for hearing 11/30/06 11/30/06 Public Meeting - license renewal process and environmental scoping 12/19/06 12/19/06 Audit - scoping and screening methodology 01/08-12/07 01/08-12/07 Environmental scoping periods ends 01/29/07 1/29/07 Audit - environmental 03/12-16/07 03/12-16/07 Audit - aging management programs (AMPs) 03/26-30/07 03/26-30/07 Issue environmental requests for additional information (RAIs) 04/20/07 Audit - aging management reviews (AMRs) 05/07-11/07 Receive responses for environmental RAIs 05/20/07 Audit - Time Limited Aging Analysis (TLAAs) (Optional) 06/18-22/07 Issue safety RAIs 06/22/07 Receive responses for safety RAIs 07/23/07 Inspection - scoping, screening, and AMPs 09/10-14/07 Issue draft supplemental environmental impact statement (SEIS) 09/25/07 Publish FRN - availability and comments on draft SEIS 10/09/07 Inspection - scoping, screening, and AMPs 10/22-26/07 Public Exit Meeting - scoping, screening, and AMPs inspections TBD Public Meeting - draft SEIS 11/08/07 End of comment period for the draft SEIS 12/26/07 Issue safety evaluation report (SER) with open item(s) 02/01/08 Advisory Committee on Reactor Safeguards (ACRS) subcommittee meeting on SER with open item(s) 03/ /08 Receive responses related to the SER with open item(s) 04/01/08 Issue Regional Administrator's letter TBD Issue final SEIS 05/08/08 Publish FRN - availability of final SEIS 05/26/08 Issue SER 06/30/08 ACRS full committee meeting on SER 09/ /08 Issue ACRS letter 09/17/08 Issue staff recommendation to NRRs Director 11/14/08 NRR decision (license issued, if approved and no hearing is granted) 11/21/08 Commission decision (if hearing is granted)
N/A
Letter to T. Garrett from V. Rodriguez dated April 9, 2007
SUBJECT:
REVISION OF SCHEDULE FOR THE CONDUCT OF REVIEW OF THE WOLF CREEK GENERATING STATION, UNIT 1, LICENSE RENEWAL APPLICATION DISTRIBUTION:
HARD COPY DLR RF E-MAIL:
PUBLIC RWeisman GGalletti SSmith (srs3)
SDuraiswamy RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDlrRlrc RidsNrrDlrReba RidsNrrDlrRebb RidsNrrDci RidsNrrDra RidsNrrDe RidsNrrDeEemb RidsNrrDeEeeb RidsNrrDeEqvb RidsNrrDss RidsOgcMailCenter RidsNrrAdes VRodriguez CJacobs JDonohew CLong, RIV GPick, RIV SCochrum, RIV TCombs, OCA VGaddy, RIV LSmith, RIV CLong, RIV DMcIntyre, OPA SBurnell, OPA
Wolf Creek Generating Station cc:
Jay Silberg, Esq.
Pillsbury Winthrop Shaw Pittman, LLP 2300 N Street, NW Washington, DC 20037 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-7005 Senior Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 311 Burlington, KS 66839 Chief Engineer, Utilities Division Kansas Corporation Commission 1500 SW Arrowhead Road Topeka, KS 66604-4027 Office of the Governor State of Kansas Topeka, KS 66612 Attorney General 120 S.W. 10th Avenue, 2nd Floor Topeka, KS 66612-1597 County Clerk Coffey County Courthouse 110 South 6th Street Burlington, KS 66839 Thomas A. Conley, Section Chief Radiation and Asbestos Control Kansas Department of Health and Environment Bureau of Air and Radiation 1000 SW Jackson, Suite 310 Topeka, KS 66612-1366 Vice President Operations/Plant Manager Wolf Creek Nuclear Operating Corporation P.O. Box 411 Burlington, KS 66839 Supervisor Licensing Wolf Creek Nuclear Operating Corporation P.O. Box 411 Burlington, KS 66839 U.S. Nuclear Regulatory Commission Resident Inspectors Office/Callaway Plant 8201 NRC Road Steedman, MO 65077-1032 Kevin J. Moles, Manager Regulatory Affairs Wolf Creek Nuclear Operating Corporation P.O. Box 411 Burlington, KS 66839 Lorrie I. Bell, Project Manager Wolf Creek Nuclear Operating Corporation P.O. Box 411 Burlington, KS 66839 Mr. James Ross Nuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, DC 20006-3708