ML070860321

From kanterella
Jump to navigation Jump to search
Intro February 5-6, 2007, Program for the Inspection of Nickel Alloy Components (Pinc) 8th Meeting
ML070860321
Person / Time
Site: North Anna Dominion icon.png
Issue date: 02/05/2007
From: Carol Moyer
NRC/RES/DFERR
To:
Shared Package
ML070860236 List:
References
Download: ML070860321 (6)


Text

United States Nuclear Regulatory Commission Program for the Inspection of Nickel Alloy Components (PINC) 8th Meeting February 5-6, 2007 Rockville, Maryland, USA Carol E. Moyer, Materials Engineer US NRC Office of Nuclear Regulatory Research 01-415-6764 cem3@nrc.gov

Objectives for PINC Cooperative Research Project

  • Document the range of locations and crack morphologies associated with PWSCC and observed NDE responses
  • Fabricate / obtain representative NDE mock-ups with flaws to simulate tight PWSCC cracks
  • Identify and quantitatively assess NDE methods for accurately detecting, sizing and characterizing tight cracks such as PWSCC
  • Incorporate findings from other ongoing PWSCC research programs, as appropriate 5-6 February 2007 PINC-8 2

Project Organization

  • Task 1 - Morphology Atlas (TG-Atlas)

- Compile existing work on crack morphology of PWSCC

- Correlate with NDE data, when available

- Develop an electronic Atlas (database) of NDE and metallography information

- Perform new NDE, fractography, metallography

  • Task 2 - NDE Technology Assessment (TG-NDE)

- Round Robin of NDE techniques on PWSCC and simulated cracks

- Assess techniques to detect and size cracks

- Assess techniques to manufacture test blocks

- Consider relevant materials, geometries

- Integrate findings for regulatory application, process qualification 5-6 February 2007 PINC-8 3

Status of Agreements

  • Signed Members

- SKI

- JNES

- Tohoku University

- Kansai Electric Power Co. (Japanese PWR Industry)

- VTT / HUT (Finland)

- KINS / KAERI (Korea)

  • Committed Members (Agreements in Process)

- EPRI 5-6 February 2007 PINC-8 4

Meeting Agenda: February 5th Opening of meeting, introductions, logistics C. Moyer Welcome, opening comments J. Wiggins Review of minutes from PINC-7 meeting P. Merck Review of action items from PINC-7 meeting P. Merck/G. Schuster Lessons learned from Piping RRT in Japan I. Komura Break Proposed CRDM and BMI mockups G. Schuster Lunch Discussion - RRT schedule development S. Doctor/P. Merck Data analysis group (DAG) C. Moyer/S. Doctor Break Discussion - plans for subsequent RRTs Finland program update P. Kauppinen Adjourn for the day 5-6 February 2007 PINC-8 5

Meeting Agenda: February 6th Resume meeting, introductions, logistics C. Moyer TG-Atlas update G. Schuster Break TG-NDE summary S. Doctor Review of action items P. Merck/G. Schuster Lunch Steering Committee Meeting C. Moyer Discussion - program extension through 2008 Discussion - DAG Discussion - RRT schedule Schedule for future meetings Adjourn 5-6 February 2007 PINC-8 6