February 2, 2007 Southern Nuclear Operating Company, Inc.

ATTN: Mr. J. R. Johnson Vice President - Farley Joseph M. Farley Nuclear Plant 7388 North State Highway 95 Columbia, AL 363 19

SUBJECT:

ASSESSMENT FOLLOW-UP LETTER - JOSEPH M. FARLEY NUCLEAR PLANT

Dear Mr. Johnson:

In October 2006, the NRC staff completed, as part of our quarterly review, an update of our assessment of the Farley plant. The assessment evaluated performance indicators (PIs) and inspection results. The purpose of this letter is to inform you of your safety performance during this period and our plans for a future inspection at your facility. This letter supplements, but does not supercede, our mid-cycle assessment letter issued on August 31, 2006.

Our review identified that you crossed the threshold from Green to White for the Mitigating System Performance Index, Cooling Water Systems performance indicator. This resulted from several breaker demand failures for the Service Water pumps. As a result, we have assessed Farleys performance to be in the Regulatory Response column of the NRCs Action Matrix.

In December 2006, we were notified by your staff of your readiness for the NRC to conduct a supplemental inspection to review the actions taken to address the PI. Therefore, we plan to conduct supplemental inspection (Inspection P-rocedure 95001) beginning on February 12, 2007. This inspection procedure is conducted to provide assurance that the root causes and contributing causes of risk significant performance issues are understood, the extent of condition is identified, and the corrective actions are sufficient to prevent recurrence.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS).

ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact Mr. Scott Shaeffer at 404-562-4521 with any questions you may have regarding this letter.

Sincerely;

/RA/

Charles A. Casto, Director Division of Reactor Projects Docket Nos. 50-348 and 50-364 License Nos. NPF-2 and NPF-8 cc: (See next page)

OFFICE RII:DRP RII:DRP SIGNATURE

/RA/

/RA/

NAME CRapp SShaeffer DATE 2/1/07 2/1/07 E-MAIL COPY?

YES NO YES NO YES NO YES NO YES NO YES NO YES NO

SNC 2

cc:

B. D. McKinney, Licensing Services Manager, B-031 Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution J. T. Gasser Executive Vice President Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution Bentina C. Terry Southern Nuclear Operating Company, Inc.

Bin B-022 P. O. Box 1295 Birmingham, AL 35201-1295 State Health Officer Alabama Department of Public Health RSA Tower - Administration 201 Monroe St., Suite 700 P. O. Box 303017 Montgomery, AL 36130-3017 M. Stanford Blanton Balch and Bingham Law Firm P. O. Box 306 1710 Sixth Avenue North Birmingham, AL 35201 William D. Oldfield Quality Assurance Supervisor Southern Nuclear Operating Company Electronic Mail Distribution

SNC 3

Distribution:

K. Cotton, NRR L. Slack, RII EICS RIDSNRRDIRS Chief, NRR/DIPM/IIPB RidsNrrDirsIpab@nrc.gov OE Mail (email address if applicable)

PUBLIC