rames Nogge - NHU Uroundwater Uontamination Inspection Plan Page 111
_gL_
From:
To:
Date:
Subject:
James Noggle e Croulet, Donald; Don Mayer 11/06/2006 4:48:58 PM NRC Groundwater Contamination Inspection Plan
Dear Don Croulet,
We have drafted an inspection itinerary for next week's NRC inspection which is attached. Please coordinate these meetings with locations and staff presenters. Please let me know of any schedule conflicts and confirm the agenda. Thanks.
- Regards, Jim CC:
James Kottan; John White; Rice, Timothy; Rosenmann, Larry; Thomas Nicholson
IPEC November 13-17, 2006 NRC Inspection Agqenda
- 1. Review timeline of Unit 1 SFP leak associated activities (C. English) 11/13, 1:00 pm J. Kottan, J. Noggle
- 2. Review historical Unit 1 Sr-90 and Cs-137 analysis results (J. Peters, S. Sandike) 11/14, 8:00 am J. Kottan, J. Noggle
- 3. Collect groundwater seepage sample from North wall of Trap Rock Quarry and other onsite MW split samples (T. Burns), 11/14, 1:00 pm J. Noggle, J. Kottan
- 4. Review all MW results with licensee, NRC, and NYS (J. Adler, J. Kottan, T. Rice) 11/15, 8:00 am J. Noggle
- 5. Establish schedule and protocol for future 3-way splits (J. Adler, T. Burns), 11/15, 10:00 am J. White, J. Kottan, T. Rice, J. Noggle
- 6. Review long term monitoring plan and REMP/ODCM changes (J. Adler, S. Sandike)1 1/15, 10:30 am J. White, J. Kottan, J. Noggle, T. Rice
- 7. Review results of storm drain renovation project and impact on site (G. Hinrichs/ D.'
Winslow) 11/15, 1:00 pm J. White, J. Kottan, J. Noggle, T. Nicholson, T. Rice, L. Rosenmann
- 8. Presentation of Unit 2 SFP recovery well test results (M. Barvenik) 11/16, 8:00 am J. White, J. Kottan, J. Noggle, T. Nicholson, T. Rice, L. Rosenmann
- 9. Discuss Unit 2 SFP remediation plan strategies and options (M. Barvenik) 11/16, 10:00 am J. White, J. Kottan, J. Noggle, T. Nicholson, T. Rice, L. Rosenmann
- 10. Review project status to include: schedule of activities, Unit 2 SFP transfer canal indications, Unit 1 NCD historical discharge pipe investigation/remediation (G. Hinrichs) 11/16, 1:00 pm J. White, J. Kottan, J. Noggle, T. Nicholson, T. Rice, L. Rosenmann
- 11. NRC debrief with licensee (J.Noggle, J. White) 11/17, 9:30 am J. Kottan, T. Rice