UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE COMMISSION In the Matter of
)
)
ENTERGY NUCLEAR VERMONT YANKEE,
)
Docket No. 50-271-LR LLC, and ENTERGY NUCLEAR
)
OPERATIONS, INC.
)
ASLBP No. 06-849-03-LR
)
(Vermont Yankee Nuclear Power Station)
)
In the Matter of
)
)
ENTERGY NUCLEAR GENERATION
)
Docket No. 50-293-LR COMPANY, and ENTERGY NUCLEAR
)
OPERATIONS, INC.
)
ASLBP No. 06-848-02-LR
)
(Pilgrim Nuclear Power Station)
)
NRC STAFF MOTION FOR CONSOLIDATION OF FILING DEADLINES INTRODUCTION Pursuant to 10 C.F.R. § 2.323, the NRC Staff (Staff) hereby moves for consolidation of deadlines for answering the Massachusetts Attorney Generals Motion for Reconsideration and Clarification of CLI-07-03 and Motion for Leave to File Motion for Reconsideration and Clarification of CLI-07-03 (collectively the Motion) filed in the above captioned proceedings.
DISCUSSION The Staffs lead counsel in the Pilgrim proceeding did not receive the Motion via electronic mail on the date it was sent, February 1, 2007. However, a Staff attorney in that proceeding did receive the Motion via electronic mail on February 1, 2007. Therefore, pursuant to 10 C.F.R. § 2.323, the Staffs answer in the Pilgrim proceeding is due on Monday, February 12, 2007. Although the service list indicates electronic mail service, Staff counsel in the Vermont Yankee proceeding did not receive the Motion via electronic mail, but have now 1 Staff counsel has been informed that the Office of the Secretary also did not receive the Motion by electronic mail.
2 Staff counsel has also contacted counsel for the New England Coalition, the Vermont Department of Public Service, the State of New Hampshire, Pilgrim Watch, and the Town of Plymouth, as well as the representative for the Town of Duxbury, none of whom oppose the motion.
received it through first class mail.1 Counsel for the Staff and for the Massachusetts Attorney General have agreed to treat the Vermont Yankee filing as if it were served by first class mail.
Therefore, pursuant to 10 C.F.R. § 2.306, the Staffs answer in the Vermont Yankee proceeding would be due on Friday, February 16, 2007.
To promote administrative efficiency, the Staff would prefer to file a single, consolidated answer in both proceedings. Counsel for the Massachusetts Attorney General has agreed to the Staff filing a consolidated answer to the Motion on February 16, the current deadline in the Vermont Yankee proceeding.2 Counsel for Entergy does not oppose extending the Staffs deadline in the Pilgrim proceeding, and seeks consent to move its deadline to February 16, as well. Counsel for the Massachusetts Attorney General and the Staff do not oppose allowing Entergy to file a consolidated answer on February 16. Therefore, the Staff requests the Commission consolidate the filing deadlines, allowing the Staff and Entergy to file answers to the Motion on Friday, February 16, 2007.
CONCLUSION For the reasons discussed above, the Staff requests the Commission grant its motion, allowing both the Staff and Entergy to file consolidated answers to the Massachusetts Attorney Generals Motion on February 16, 2007.
Respectfully submitted,
/RA/
Susan L. Uttal Counsel for NRC Staff
/RA/
Steven C. Hamrick Counsel for NRC Staff Dated at Rockville, Maryland this 7th day of February, 2007
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE COMMISSION In the Matter of
)
)
ENTERGY NUCLEAR OPERATIONS, INC. )
Docket No. 50-293-LR
)
(Pilgrim Nuclear Power Station)
)
ASLBP No. 06-848-02-LR
)
CERTIFICATE OF SERVICE I hereby certify that copies of the NRC STAFF MOTION FOR CONSOLIDATION OF FILING DEADLINES in the above-captioned proceeding have been served on the following by electronic mail and deposit in the U.S. Mail Service or by deposit in the U.S. Nuclear Regulatory Commissions internal mail system as indicated by a single asterisk(*), or by deposit in the U.S.
mail system, as indicated by a double asterisk (**) this 7th day of February, 2007.
Administrative Judge*
Richard F. Cole Atomic Safety and Licensing Board Panel Mail Stop: T-3F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 E-mail: rfc1@nrc.gov Administrative Judge*
Ann Marshall Young, Chair Atomic Safety and Licensing Board Panel Mail Stop: T-3F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 E-mail: amy@nrc.gov Sheila Slocum Hollis**
Duane Morris LLP 1667 K Street, NW, Suite 700 Washington, DC 20006 E-mail: sshollis@duanemorris.com Administrative Judge*
Paul B. Abramson Atomic Safety and Licensing Board Panel Mail Stop: T-3F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 E-mail: pba@nrc.gov Office of Commission Appellate
- Adjudication Mail Stop: O-16C1 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 E-mail: OCAAMail@nrc.gov Office of the Secretary*
Attn: Rulemaking and Adjudications Staff Mail Stop: O-16C1 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 E-mail: hearingdocket@nrc.gov Atomic Safety and Licensing Board*
Mail Stop: T-3 F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Molly H. Bartlett, Esq.**
52 Crooked Lane Duxbury, MA 02332 E-mail: mollyhbartlett@hotmail.com Chief Kevin M. Nord**
Fire Chief & Director Duxbury Emergency Management Agency 668 Tremont Street Duxbury, MA 02332 E-mail: nord@town.duxbury.ma.us Fax: 781-934-6530 Diane Curran, Esq.**
Harmon, Curran, Spielberg
& Eisenberg, L.L.P.
1726 M Street, NW., Suite 600 Washington, DC 20036 E-mail: dcurran@harmoncurran.com Terence A. Burke, Esq.**
Entergy Nuclear 1340 Echelon Parkway Mail Stop: M-ECH-62 Jackson, MS 39213 David R. Lewis, Esq.**
Paul A. Gaukler, Esq.
Pillsbury, Winthrop, Shaw, Pittman, LLP 2300 N Street, NW Washington, DC 20037-1137 E-mail: david.lewis@pillsburylaw.com paul.gaukler@pillsburylaw.com Town Manager**
Town of Plymouth 11 Lincoln St.
Plymouth, MA 02360 E-mail: msylvia@townhall.plymouth.ma.us Matthew Brock, Esq.**
Assistant Attorney General Office of the Massachusetts Attorney General Environmental Protection Division One Ashburton Place, Room 1813 Boston, MA 02108-1598 E-mail: matthew.brock@ago.state.ma.us
/RA/
Marian L. Zobler Counsel for the NRC Staff
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE COMMISSION In the Matter of
)
)
ENTERGY NUCLEAR VERMONT YANKEE,
)
Docket No. 50-271-LR LLC, and ENTERGY NUCLEAR
)
OPERATIONS, INC.
)
ASLBP No. 06-849-03-LR
)
(Vermont Yankee Nuclear Power Station)
)
CERTIFICATE OF SERVICE I hereby certify that copies of the NRC STAFF MOTION FOR CONSOLIDATION OF FILING DEADLINES in the above-captioned proceeding have been served on the following by electronic mail with copies by deposit in the NRCs internal mail system by electronic mail, with copies by U.S. mail, first class, as indicated by an asterisk, this 7th day of February, 2007.
Administrative Judge Alex S. Karlin, Chair Atomic Safety and Licensing Board Panel U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 E-mail: ask2@nrc.gov Administrative Judge Thomas S. Elleman*
Atomic Safety and Licensing Board Panel 5207 Creedmoor Road, #101 Raleigh, NC 27612 E-mail: elleman@eos.ncsu.edu Office of Commission Appellate Adjudication Mail Stop: O-16C1 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 E-mail: OCAAmail@nrc.gov Administrative Judge Richard E. Wardwell Atomic Safety and Licensing Board Panel U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 E-mail: rew@nrc.gov Office of the Secretary Attn: Rulemaking and Adjudications Staff Mail Stop: O-16C1 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 E-mail: hearingdocket@nrc.gov Sarah Hofmann, Esq.*
Special Counsel Department of Public Service 112 State Street - Drawer 20 Montpelier, VT 05620-2601 E-mail: sarah.hofmann@state.vt.us Diane Curran, Esq.*
Harmon, Curran, Spielberg
& Eisenberg, L.L.P.
1726 M Street, NW., Suite 600 Washington, DC 20036 E-mail: dcurran@harmoncurran.com Ronald A. Shems, Esq.*
Karen Tyler, Esq.*
Shems Dunkiel Kassel & Saunders, PLLC 91 College Street Burlington, VT 05401 E-mail: rshems@sdkslaw.com Ktyler@sdkslaw.com Marcia Carpentier, Esq.
Atomic Safety and Licensing Board Panel Mail Stop: T-3F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 E-mail: mxc7@nrc.gov Jennifer J. Patterson*
Senior Assistant Attorney General Environmental Protection Bureau Office of the Attorney General 33 Capitol Street Concord, New Hampshire 03301 E-mail: jennifer.patterson@doj.nh.gov Anthony Z Roisman, Esq.*
National Legal Scholars Law Firm 84 East Thetford Rd.
Lyme, NH 03768 E-mail: aroisman@nationallegalscholars.com Matthew Brock, Esq.*
Assistant Attorney General Office of the Massachusetts Attorney General Environmental Protection Division One Ashburton Place, Room 1813 Boston, MA 02108-1598 E-mail: matthew.brock@ago.state.ma.us David R. Lewis, Esq.*
Matias F. Travieso-Diaz*
Pillsbury Winthrop Shaw Pittman LLP 2300 N Street, NW Washington, DC 20037-1128 E-mail: david.lewis@pillsburylaw.com matias.travieso-diaz@pillsburylaw.com
/RA/
Steven C. Hamrick Counsel for NRC Staff