Inspection Results Required Per First Revised NRC Order (EA-03-009)
ML070170465
Person / Time
Site: Mcguire
Issue date: 01/09/2007
From: Gordon Peterson
Duke Energy Carolinas, Duke Power Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
EA-03-009
Download: ML070170465 (4)


Text

P Duke 6Energy GARY R. PETERSON Vice President McGuire Nuclear Station Duke Energy Corporation MG01 VP / 12700 Hagers Ferry Rd.

Huntersville, NC 28078 704 875 5333 704 875 4809 fax grpeters@duke-energy. com January 9, 2007 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

SUBJECT:

Duke Power Company LLC d/b/a Duke Energy Carolinas, LLC (Duke)

McGuire Nuclear Station, Unit 2 Docket Number 50-370 Inspection Results Required Per First Revised NRC Order (EA-03-009)

By letter dated February 20, 2004, the NRC issued the First Revised NRC Order (EA 009) Establishing Interim Inspection Requirements for Reactor Pressure Vessel Heads at Pressurized Water Reactors. The Order imposed requirements for pressurized water reactor licensees to inspect reactor pressure vessel heads and related penetration nozzles pending the revision of 10 CFR 50.55a and to submit a report detailing the inspection results within sixty (60) days after returning the unit to operation.

Duke Energy performed the required inspections in accordance with the First Revised NRC Order on McGuire Unit 2 during the End-of-Cycle 17 refueling outage.

The inspections met the requirements of the Order with no deviations or evidence of leakage, cracking or wastage detected. provides the required inspection results.

Questions regarding the subject submittal should be directed to Kay Crane, McGuire Regulatory Complia t (704) 875-4306.

Gary R. Peterson Attachment Awl www. duke-energy. corn

U. S. Nuclear Regulatory Commission January 9, 2007 Page 2 W. D. Travers, Region II Administrator U.S. Nuclear Regulatory Commission Sam Nunn Atlanta Federal Center, 23 T85 61 Forsyth St., SW Atlanta, GA 30303-8931 J. F. Stang, Jr., Senior Project Manager (CNS & MNS)

U. S. Nuclear Regulatory Commission 11555 Rockville Pike Mail Stop 0-8 H 4A Rockville, MID 20852-2738 J. B. Brady NRC Senior Resident Inspector McGuire Nuclear Station

U. S. Nuclear Regulatory Commission January 9, 2007 Page 3 Gary R. Peterson, affirms that he is the person who subscribed his name to the foregoing statement, and that all the matters and facts set forth herein are true and correct to the best of his knowledge.

Gary R. feterson, Vice President Subscribed and sworn to me:

,-J L

&6 r Date 9/ q 'ý(

Notary Public X" dAzýýI,)-

My Commission Expires:

Date SE'A L

Attachment I McGuire Nuclear Station, Unit 2 End-of-Cycle 17 Reactor Vessel Head Inspection Results Report During the McGuire Unit 2 End-of-Cycle 17 refueling outage, Duke Energy performed inspections in accordance with the First Revised NRC Order EA-03-009 dated February 20, 2004. The inspections met the requirements of the Order with no deviations or evidence of leakage, cracking or wastage detected.

The susceptibility of the Reactor Pressure Vessel (RPV) head to PWSCC-related degradation, as represented by a value of effective degradation years (EDY), was calculated. The calculated value determined that the McGuire Unit 2 RPV head is in the Low Susceptibility Category.

The Bare Metal Visual (BMV) inspection examined 100 percent of the Reactor Pressure Vessel (RPV) upper head surface including 3600 around each RPV head penetration nozzle. The RPV head was determined to be free of boron deposits with no evidence of leakage, cracking, or wastage.

The volumetric Ultrasonic (UT) inspection examined each Control Rod Drive Mechanism (CRDM) penetration and the vent line penetration.

UT of the RPV head penetration nozzle volume from 2 inches above the highest point of the root of the J-groove weld to 1-inch below the lowest point at the toe of the J-groove weld and including all RPV head penetration nozzle surfaces below the J-groove weld that have an operating stress level of 20 ksi tension and greater was performed. No crack-like indications were detected in the CRDM penetrations or in the vent line penetration.

UT leak path detection was used to assess if leakage has occurred into the annulus between the RPV head penetration nozzle and the RPV head low-alloy steel for all CRDM penetrations. No UT leak path signals were detected in the CRDM penetrations.

Surface examination using dye penetrant supplemented the volumetric inspection of the vent line penetration.

Surface examination included the surface of the vent line penetration J-groove weld, the bottom of the vent line penetration, and the chamfer on the ID of the vent line penetration that was not covered by UT.

No indications were detected during the surface examination of the vent line.