December 13, 2006 MEMORANDUM TO: David C. Lew, Director Division of Reactor Projects, RI FROM:
Raymond J. Powell, Chief /RA/
Projects Branch 5 Division of Reactor Projects, RI
SUBJECT:
DROP-IN VISIT FROM ENTERGY (PILGRIM)
On December 6, 2006, Samuel Collins, Marc Dapas, David Lew, A. Randall Blough, Tracy Walker, Nicole Sieller, and Garrett Newman met with Constellation's Mike Balduzzi (Site Vice President), Kevin Bronson (General Manager), Steve Bethay (Director of Nuclear Safety Assessments), and Bryan Ford (Licensing Manager). The purpose of this visit was to discuss Pilgrim Nuclear Power Station performance and initiatives.
During the meeting, the following topics were discussed:
1.
Plant performance overview 2.
Results of recent INPO evaluation 3.
Equipment reliability 4.
Maintenance backlogs 5.
Radiation exposure 6.
Human performance 7.
Staffing issues (security transition, SRO/RO retention and pipeline) 8.
Refueling outage major projects The visit began at 10:00 a.m. and ended at 1:00 p.m. No regulatory decisions were requested or made. A meeting handout was provided by Entergy and is enclosed with this memorandum.
Enclosure:
As stated
2 D. Lew MEMORANDUM TO:
David C. Lew, Director Division of Reactor Projects, RI FROM:
Raymond J. Powell, Chief Projects Branch 5 Division of Reactor Projects, RI
SUBJECT:
DROP-IN VISIT FROM ENTERGY (PILGRIM)
On December 6, 2006, Samuel Collins, Marc Dapas, David Lew, A. Randall Blough, Tracy Walker, Nicole Sieller, and Garrett Newman met with Constellation's Mike Balduzzi (Site Vice President), Kevin Bronson (General Manager), Steve Bethay (Director of Nuclear Safety Assessments), and Bryan Ford (Licensing Manager). The purpose of this visit was to discuss Pilgrim Nuclear Power Station performance and initiatives.
During the meeting, the following topics were discussed:
1.
Plant performance overview 2.
Results of recent INPO evaluation 3.
Equipment reliability 4.
Maintenance backlogs 5.
Radiation exposure 6.
Human performance 7.
Staffing issues (security transition, SRO/RO retention and pipeline) 8.
Refueling outage major projects The visit began at 10:00 a.m. and ended at 1:00 p.m. No regulatory decisions were requested or made.
A meeting handout was provided by Entergy and is enclosed with this memorandum.
Enclosure:
As stated Distribution: Via Email S. Collins, RA M. Dapas, DRA D. Lew, DRP J. Clifford, DRP A. Blough, DRS K. Farrar, ORA R. Powell, DRP N. Sieller, DRP SUNSI Review Complete: TEW (Reviewers Initials)
DOCUMENT NAME: C:\\FileNet\\ML063480024.wpd After declaring this document An Official Agency Record it will be released to the Public.