ML063340179

From kanterella
Jump to navigation Jump to search

Generic Letter 2003-01
ML063340179
Person / Time
Site: Duane Arnold NextEra Energy icon.png
Issue date: 12/11/2006
From: Richard Ennis
NRC/NRR/ADRO/DORL/LPLIII-1
To: Vanmiddlesworth G
Duane Arnold
K. Feintuch, LPL3-1
References
GL-03-001, TAC MB9801
Download: ML063340179 (4)


Text

December 11, 2006 Mr. Gary Van Middlesworth Site Vice President Duane Arnold Energy Center 3277 DAEC Road Palo, Iowa 52324-9785

SUBJECT:

NRC RECEIPT OF DUANE ARNOLD ENERGY CENTER RESPONSE TO GENERIC LETTER 2003-01 CONTROL ROOM HABITABILITY (TAC NO. MB9801)

Dear Mr. Van Middlesworth:

The Nuclear Regulatory Commission (NRC) acknowledges the receipt of the responses to Generic Letter (GL) 2003-01 Control Room Habitability for the Duane Arnold Energy Center (DAEC) from Nuclear Management Company, LLC (NMC) dated August 11, 2003, November 25, 2003, and January 28, 2005 (Agencywide Documents Access and Management System (ADAMS) Accession Nos. ML032310414, ML033300162, ML050390308, respectively).

Amendment No. 260, issued on January 27, 2006, transferred the DAEC license from NMC to FPL Energy Duane Arnold, LLC (FPL Energy). As noted in your letter dated February 6, 2006, FPL Energy adopted and endorsed all docketed requests for NRC review previously submitted by NMC. This letter provides a status of your response for DAEC and describes any actions that may be necessary to consider the response to GL 2003-01 to be complete.

The GL requested that licensees confirm that the control room meets its design bases (e.g.,

General Design Criteria (GDC) 1, 3, 4, 5, and 19, draft GDC, or principal design criteria), with special attention to: (1) Determination of the most limiting unfiltered and/or filtered inleakage into the control room and comparison to values used in the design bases for meeting control room operator dose limits from accidents (GL 2003-01 Item 1a); (2) Determination that the most limiting unfiltered inleakage is incorporated into the hazardous chemical assessments (GL 2003-01 Item 1b); and, (3) Determination that reactor control capability is maintained in the control room or at the alternate shutdown location in the event of smoke (GL 2003-01 Item 1b).

The GL further requested information on any compensatory measures in use to demonstrate control room habitability (CRH) and plans to retire them (GL 2003-01 Item 2).

You reported the results of American Society for Testing and Materials E741 tracer gas tests for the DAEC control room, which is pressurized for accident mitigation. You determined that the most limiting unfiltered inleakage into the control room envelope (CRE), was 85 standard cubic feet per minute (scfm), which is less than the value of 1000 scfm assumed in the design basis radiological analyses for CRH.

You also reported that DAECs toxic chemical analysis assumes a normal ventilation mode of 3150 scfm inflow plus 1000 scfm inleakage, for a total of 4150 scfm, all unfiltered. Tracer gas testing in the 'Normal" mode of operation (recirculation mode) was performed and total flow was 2848 +/- 81 scfm. Therefore, normal ventilation mode total intake and inleakage is within

G. Van Middlesworth analyzed limits for toxic chemical analysis. Additionally, you indicated that reactor control capability is maintained in the event of smoke from either the control room, or the alternate shutdown panel.

The GL further requested that licensees assess the Technical Specifications (TSs) to determine if the TSs verify the integrity of the CRE, including ongoing verification of the inleakage assumed in the design basis analysis for CRH, in light of the demonstrated inadequacy of a delta () P measurement to, alone, provide such verification (GL 2003-01 Item 1c). As permitted by the GL, you provided a schedule for revising the surveillance requirements in the TSs to reference an acceptable surveillance methodology. In your response dated January 28, 2005, you committed to submit proposed changes to the TSs, based upon the final approved version of Technical Specification Task Force (TSTF) Traveler No. TSTF-448, within 180 days following NRC approval of TSTF-448.

The information you provided supports that there are no compensatory measures currently in place to demonstrate CRH. The information you provided also supports your conclusion that the facility design, as documented in the DAEC Updated Final Safety Analysis Report, is consistent with the GDC regarding CRH.

Your commitment to submit a License Amendment Request (LAR) based on TSTF-448, following our formal review and approval, is acceptable for purposes of closing out the response to GL 2003-01 for DAEC. The NRC staff will monitor submission of the LAR and interact with you as necessary during the amendment review process.

If you have any questions, please contact Karl Feintuch at 301-415-3079 or myself at 301-415-1420.

Sincerely,

/RA/

Richard B. Ennis, Senior Project Manager Plant Licensing Branch III-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-331 cc: See next page

G. Van Middlesworth analyzed limits for toxic chemical analysis. Additionally, you indicated that reactor control capability is maintained in the event of smoke from either the control room, or the alternate shutdown panel.

The GL further requested that licensees assess the Technical Specifications (TSs) to determine if the TSs verify the integrity of the CRE, including ongoing verification of the inleakage assumed in the design basis analysis for CRH, in light of the demonstrated inadequacy of a delta () P measurement to, alone, provide such verification (GL 2003-01 Item 1c). As permitted by the GL, you provided a schedule for revising the surveillance requirements in the TSs to reference an acceptable surveillance methodology. In your response dated January 28, 2005, you committed to submit proposed changes to the TSs, based upon the final approved version of Technical Specification Task Force (TSTF) Traveler No. TSTF-448, within 180 days following NRC approval of TSTF-448.

The information you provided supports that there are no compensatory measures currently in place to demonstrate CRH. The information you provided also supports your conclusion that the facility design, as documented in the DAEC Updated Final Safety Analysis Report, is consistent with the GDC regarding CRH.

Your commitment to submit a License Amendment Request (LAR) based on TSTF-448, following our formal review and approval, is acceptable for purposes of closing out the response to GL 2003-01 for DAEC. The NRC staff will monitor submission of the LAR and interact with you as necessary during the amendment review process.

If you have any questions, please contact Karl Feintuch at 301-415-3079 or myself at 301-415-1420.

Sincerely,

/RA/

Richard B. Ennis, Senior Project Manager Plant Licensing Branch III-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-331 cc: See next page DISTRIBUTION PUBLIC LPL3-1 R/F RidsNrrPMKFeintuch RidsNrrPMREnnis RidsNrrLATHarris RidsNrrDorlLpl3-1 RidsRgn3MailCenter RidsOgcRp JRobinson RidsNrrDprPgcb RidsAcrsAcnwMailCenter RidsNrrDssScvb ADAMS ACCESSION NO. ML063340179 OFFICE LPL3-1/PM LPL3-1/PM LPL3-1/LA SCVB/BC PGCB/BC LPL3-1/BC NAME KFeintuch REnnis THarris RDennig CJackson LRaghavan DATE 11/30/06 12/6/06 11/29/06 12/6/06 12/6/06 12/11/06 OFFICIAL RECORD COPY

G. Van Middlesworth Duane Arnold Energy Center cc:

Mr. J. A. Stall Regional Administrator, Region III Senior Vice President, Nuclear and Chief U.S. Nuclear Regulatory Commission Nuclear Officer Suite 210 Florida Power & Light Company 2443 Warrenville Road P. O. Box 14000 Lisle, IL 60532-4351 Juno Beach, FL 33408-0420 Mr. M. Warner Mr. M. S. Ross Vice President, Nuclear Operations Managing Attorney Support Florida Power & Light Company Florida Power & Light Company P. O. Box 14000 P. O. Box 14000 Juno Beach, FL 33408-0420 Juno Beach, FL 33408-0420 Mr. R. E. Helfrich Mr. D. A. Curtland Senior Attorney Plant Manager Florida Power & Light Company Duane Arnold Energy Center P. O. Box 14000 3277 DAEC Rd.

Juno Beach, FL 33408-0420 Palo, IA 52324-9785 Mr. W. E. Webster Mr. R. S. Kundalkar Vice President, Nuclear Operations Vice President, Nuclear Engineering Florida Power & Light Company Florida Power & Light Company P. O. Box 14000 P. O. Box 14000 Juno Beach, FL 33408-0420 Juno Beach, FL 33408-0420 John Bjorseth Daniel K. McGhee Site Director Iowa Department of Public Health Duane Arnold Energy Center Bureau of Radiological Health 3277 DAEC Road 321 East 12th Street Palo, IA 52324 Lucas State Office Building, 5th Floor Des Moines, IA 50319-0075 Steven R. Catron Manager, Regulatory Affairs Chairman, Linn County Duane Arnold Energy Center Board of Supervisors 3277 DAEC Road 930 1st Street SW Palo, IA 52324 Cedar Rapids, IA 52404 U. S. Nuclear Regulatory Commission Resident Inspectors Office Rural Route #1 Palo, IA 52324 October 12, 2006