Summary of Category 1 Pre-submittal Meeting with Fenco to Discuss Davis-Besses Proposed Conversion to Improved Technical Specifications
ML063200123
Person / Time
Site: Davis Besse 
Issue date: 12/11/2006
From: Thomas Wengert
NRC/NRR/ADRO/DORL/LPLIII-2
To:
Wengert, Thomas
Shared Package
ML063200134 List:
References
TAC MD3229
Download: ML063200123 (6)


Text

December 11, 2006 LICENSEE:

FirstEnergy Nuclear Operating Company FACILITY:

Davis-Besse Nuclear Power Station, Unit 1

SUBJECT:

SUMMARY

OF NOVEMBER 7, 2006, PRE-SUBMITTAL MEETING WITH FENOC TO DISCUSS DAVIS-BESSES PROPOSED CONVERSION TO IMPROVED TECHNICAL SPECIFICATIONS (TAC NO. MD3229)

On November 7, 2006, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC), and representatives of FirstEnergy Nuclear Operating Company (FENOC), the licensee for Davis-Besse Nuclear Power Station (Davis-Besse), Unit 1, and its contractor, EXCEL Services Corporation (EXCEL) at the NRC headquarters located at One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to discuss Davis-Besses proposed conversion to Improved Technical Specifications (ITS).

A list of attendees is provided as Enclosure 1. FENOCs presentation slides are provided as.

The presentation to the NRC staff included an overview of the planned scope, schedule, and implementation approach of the conversion effort. FENOC advised that the scope of the ITS project would include preparation of a license amendment request to convert the Davis-Besse current technical specifications to the ITS as described in NUREG-1430, ?Standard Technical Specifications - Babcock and Wilcox Plants, Revision 3.1. FENOC presented details of the four major phases planned for the conversion project: (1) Initial Planning; (2) License Amendment Request Development; (3) NRC Review and Approval; and (4) Implementation.

Following their presentation, FENOC and the NRC staff discussed roles and responsibilities, lessons learned from the Beaver Valley Nuclear Plant ITS conversion, review time for requests for additional information, treatment of beyond scope items, resources/schedule support, and FENOC/NRC communications.

No members of the public were in attendance.

CONTACT: Thomas Wengert, NRR 301-415-4037 tjw2@nrc.gov

FENOC Please direct any inquiries to me at 301-415-4037, or tjw2@nrc.gov.

/RA/

Thomas J. Wengert, Project Manager Plant Licensing Branch III-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-346

Enclosure:

1. List of Attendees
2. Licensee Handouts cc w/encl: See next page

FENOC Please direct any inquiries to me at 301-415-4037, or tjw2@nrc.gov.

/RA/

Thomas J. Wengert, Project Manager Plant Licensing Branch III-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-346

Enclosure:

1. List of Attendees
2. Licensee Handouts cc w/encl: See next page Distribution PUBLIC LPL3-2 R/F RidsNrrDorlDpl3-2 RidsNrrDorl RidsNrrItsb RidsNrrPMTWengert RidsNrrLAEWhitt RidsOgcRp RidsAcrsAcnwMailCenter RJasinski, NRR RTelson, NRR PHearn, NRR CSchultin, NRR RGrover, NRR DCollins, NRR TKobetz, NRR Tammy Bloomer (TEB), EDO Region III RidsRgn3MailCenter Package Accession number ML063200134 Meeting Summary Accession number ML063200123 Slides Accession number ml063200367 OFFICE LPL3-2/PM LPL3-2/LA ITSB/BC LPL3-2/BC NAME TWengert:mw EWhitt TKobetz (CSchulten for)

MMarshall DATE 12/7/2006 12/7/2006 12/8/2006 12/11/2006 OFFICIAL RECORD COPY

LIST OF ATTENDEES PRE-SUBMITTAL MEETING FOR IMPROVED TECHNICAL SPECIFICATION CONVERSION FOR DAVIS-BESSE NUCLEAR POWER STATION NOVEMBER 7, 2006 1:00 PM - 3:00 PM NAME ORGANIZATION

1. T. Wengert NRC
2. T. Kobetz NRC
3. R. Telson NRC
4. P. Hearn NRC
5. D. Collins NRC
6. C. Schulten NRC
7. R. Grover NRC
8. R. Schrauder FENOC - Director, Performance Improvement
9. B. Bentley FENOC - Project Manager, Davis-Besse ISTS
10. G. Dunn FENOC - Manager, Fleet Licensing
11. R. Schiele EXCEL Services - Project Manager, ITS Conversion

Davis-Besse Nuclear Power Station, Unit 1 cc:

Manager, Site Regulatory Compliance FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station Mail Stop A-DB-3065 5501 North State Route 2 Oak Harbor, OH 43449-9760 Director, Ohio Department of Commerce Division of Industrial Compliance Bureau of Operations & Maintenance 6606 Tussing Road P.O. Box 4009 Reynoldsburg, OH 43068-9009 Regional Administrator U.S. Nuclear Regulatory Commission 801 Warrenville Road Lisle, IL 60523-4351 Resident Inspector U.S. Nuclear Regulatory Commission 5503 North State Route 2 Oak Harbor, OH 43449-9760 Dennis Clum Radiological Assistance Section Supervisor Bureau of Radiation Protection Ohio Department of Health P.O. Box 118 Columbus, OH 43266-0118 Carol OClaire, Chief, Radiological Branch Ohio Emergency Management Agency 2855 West Dublin Granville Road Columbus, OH 43235-2206 Zack A. Clayton DERR Ohio Environmental Protection Agency P.O. Box 1049 Columbus, OH 43266-0149 State of Ohio Public Utilities Commission 180 East Broad Street Columbus, OH 43266-0573 Attorney General Office of Attorney General 30 East Broad Street Columbus, OH 43216 President, Board of County Commissioners of Ottawa County Port Clinton, OH 43252 President, Board of County Commissioners of Lucas County One Government Center, Suite 800 Toledo, OH 43604-6506 The Honorable Dennis J. Kucinich United States House of Representatives Washington, D.C. 20515 The Honorable Dennis J. Kucinich United States House of Representatives 14400 Detroit Avenue Lakewood, OH 44107 Gary R. Leidich President and Chief Nuclear Officer FirstEnergy Nuclear Operating Company Mail Stop A-GO-19 76 South Main Street Akron, OH 44308 Joseph J. Hagan Senior Vice President of Operations and Chief Operating Officer FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 David W. Jenkins, Attorney FirstEnergy Corporation Mail Stop A-GO-18 76 South Main Street Akron, OH 44308

Davis-Besse Nuclear Power Station, Unit 1 cc:

Danny L. Pace Senior Vice President, Fleet Engineering FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 Manager, Fleet Licensing FirstEnergy Nuclear Operating Company Mail Stop A-GHE-115 395 Ghent Road Akron, OH 44333 Director, Fleet Regulatory Affairs FirstEnergy Nuclear Operating Company Mail Stop A-GHE-315 395 Ghent Road Akron, OH 44333 Jeannie M. Rinckel Vice President, Fleet Oversight FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 Richard Anderson Vice President, Nuclear Support FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308