November 9, 2006

Tennessee Valley Authority

ATTN: Mr. Karl W. Singer

Chief Nuclear Officer and

Executive Vice President

6A Lookout Place

1101 Market Street

Chattanooga, TN 37402-2801

SUBJECT:

REACTOR AND SENIOR REACTOR OPERATOR INITIAL EXAMINATIONS -

SEQUOYAH NUCLEAR PLANT 05000327/2007301 AND 05000328/2007301

Dear Mr. Singer:

In a telephone conversation on November 7, 2006, between Mr. James Reisenbuechler,

Operations Training Manager and Mr. Mark A. Bates, Sr. Operations Engineer, arrangements

were made for the administration of licensing examinations at the Sequoyah Nuclear Plant

during the week of April 9, 2007. The on-site preparatory week is scheduled for the week of

March 19, 2007.

As agreed during the telephone conversation, your staff will prepare the examination based on

the guidelines in Revision 9 of NUREG-1021, "Operator Licensing Examination Standards for

Power Reactors." The NRC regional office will discuss with your staff any changes that might

be necessary before the examination is administered. Your staff will also provide copying

services for administering the exam.

To meet the above schedule, it will be necessary for your staff to furnish the examination

outlines by January 23, 2007. The written examinations, operating tests, and the supporting

reference materials identified in NUREG 1021, ES-201, Attachment 2, Reference Material

Guidelines For Initial Licensing Examinations, will be due by February 23, 2007. Pursuant to

10 CFR 55.40(b)(3), an authorized representative of the facility licensee shall approve the

outlines, examinations, and tests before they are submitted to the NRC for review and approval.

All materials shall be complete and ready-to-use. We request that any personal, proprietary,

sensitive unclassified, or safeguards information in your response be contained in a separate

enclosure and appropriately marked. Any delay in receiving the required examination and

reference materials, or the submittal of inadequate or incomplete materials, may cause the

examinations to be rescheduled.

In order to conduct the requested written examinations and operating tests, it will be necessary

for your staff to provide adequate space and accommodations in accordance with NUREG 1021, ES-402, Administering Initial Written Examinations, and to make the simulation facility

available on the dates noted above. In accordance with NUREG 1021, ES-302, Administering

Operating Tests To Initial License Applicants, your staff should retain the original simulator

performance data (e.g., system pressures, temperatures, and levels) generated during the

dynamic operating tests until the examination results are final.

TVA

2

Appendix E of NUREG 1021, Policies and Guidelines For Taking NRC Examinations,

contains a number of NRC policies and guidelines that will be in effect while the written

examinations and operating tests are being administered.

To permit timely NRC review and evaluation, your staff should submit preliminary reactor

operator and senior reactor operator license applications (Office of Management and Budget

(OMB) approval number 3150-0090), medical certifications (OMB approval number 3150-0024),

and waiver requests (if any)(OMB approval number 3150-0090) at least 30 days before the first

examination date. If the applications are not received at least 30 days before the examination

date, a postponement may be necessary. Signed applications certifying that all training has

been completed should be submitted at least 14 days before the first examination date.

This letter contains information collections that are subject to the Paperwork Reduction Act of

1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of

Management and Budget, approval number Part 55 (3150-0018), which expires on June 30,

2009. The public reporting burden for this collection of information is estimated to average 500

hours per response, including the time for writing the examinations, and reviewing instructions,

gathering and maintaining the data needed, and completing and reviewing the collection of

information. Send comments on any aspect of this collection of information, including

suggestions for reducing the burden, to the Information and Records Management Branch (T-6

F33), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by internet

electronic mail at BJS1@NRC.GOV; and to the Desk Officer, Office of Information and

Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget,

Washington, DC 20503.

The NRC may not conduct or sponsor, and a person is not required to respond to, a collection

of information unless it displays a currently valid OMB control number.

In accordance with 10 CFR 2.390 of the NRC's Rules of Practice, a copy of this letter will be

available electronically for public inspection in the NRC Public Document Room or from the

Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS

is accessible from the NRC Web site at http://www/nrc.gov/readingrm/adams.html (the Public

Electronic Reading Room).

Thank you for your cooperation in this matter. Mr. Reisenbuechler has been advised of the

policies and guidelines referenced in this letter. If you have any questions regarding the NRC's

examination procedures and guidelines, please contact Mr. Mark A. Bates at (404) 562-4612,

(Internet E-mail: mab7@nrc.gov), or me at (404) 562-4607, (Internet E-mail: rch@nrc.gov).

Sincerely,

/RA By R. Baldwin for/

Robert C. Haag, Chief

Operations Branch

Division of Reactor Safety

Docket Nos.: 50-327, 50-328

License Nos.: DPR-77, DPR-79

cc: (See Page 3)

_________________________

OFFICE

RII:DRS

RII:DRS

RII:DRP

SIGNATURE

/RA/

/RA By R. Baldwin for/

/RA By L. Garner for/

NAME

MBates

RHaag

MWidmann

DATE

11/8/06

11/8/06

11/08/06

E-MAIL COPY?

YES

NO YES

NO YES

NO YES

NO YES

NO YES

NO

TVA

3

cc cont'd

Ashok S. Bhatnagar

Senior Vice President

Nuclear Operations

Tennessee Valley Authority

Electronic Mail Distribution

Preston D. Swafford

Senior Vice President

Nuclear Support

Tennessee Valley Authority

Electronic Mail Distribution

Larry S. Bryant, Vice President

Nuclear Engineering &

Technical Services

Tennessee Valley Authority

Electronic Mail Distribution

Randy Douet

Site Vice President

Sequoyah Nuclear Plant

Electronic Mail Distribution

General Counsel

Tennessee Valley Authority

Electronic Mail Distribution

John C. Fornicola, General Manager

Nuclear Assurance

Tennessee Valley Authority

Electronic Mail Distribution

Glenn W. Morris, Manager

Licensing and Industry Affairs

Sequoyah Nuclear Plant

Tennessee Valley Authority

Electronic Mail Distribution

Russell R. Thompson, Acting Manager

Corporate Nuclear Licensing and

Industry Affairs

Tennessee Valley Authority

4X Blue Ridge

1101 Market Street

Chattanooga, TN 37402-2801

Robert H. Bryan, Jr., General Manager

Licensing and Industry Affairs

Sequoyah Nuclear Plant

Tennessee Valley Authority

4X Blue Ridge

1101 Market Street

Chattanooga, TN 37402-2801

David A. Kulisek, Plant Manager

Sequoyah Nuclear Plant

Tennessee Valley Authority

Electronic Mail Distribution

Lawrence E. Nanney, Director

TN Dept. of Environment & Conservation

Division of Radiological Health

Electronic Mail Distribution

County Mayor

Hamilton County Courthouse

Chattanooga, TN 37402-2801

Ann Harris

341 Swing Loop

Rockwood, TN 37854

James H. Bassham, Director

Tennessee Emergency Management

Agency

Electronic Mail Distribution

Mr. Ronald J. Bruno

Training Manager

Sequoyah Nuclear Plant

P. O. Box 2000

Soddy-Daisy, TN 37384-2000

TVA

4

Distribution:

Bob Pascarelli, NRR

D. Pickett, NRR

C. Evans (Part 72 Only)

L. Slack, RII EICS

OE Mail (email address if applicable)

RIDSNRRDIRS

PUBLIC