Summary of a Telephone Conference Call Held on October 10, 2006, Between the NRC and Entergy Nuclear Operations, Inc., Concerning Information Pertaining to the Vermont Yankee Nuclear Power Station License Renewal Application
ML063050619
Person / Time
Site: Vermont Yankee File:NorthStar Vermont Yankee icon.png
Issue date: 11/06/2006
From: Rowley J
NRC/NRR/ADRO/DLR/RLRB
To:
Entergy Nuclear Operations
Rowley J, NRR/DLR/RLRB, 415-4053
References
%dam200612
Download: ML063050619 (8)


Text

November 6, 2006 LICENSEE:

Entergy Nuclear Operations, Inc.

FACILITY:

Vermont Yankee Nuclear Power Station

SUBJECT:

SUMMARY

OF A TELEPHONE CONFERENCE CALL HELD ON OCTOBER 10, 2006, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY NUCLEAR OPERATIONS, INC., CONCERNING INFORMATION PERTAINING TO THE VERMONT YANKEE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION The U.S. Nuclear Regulatory Commission staff (the staff) and representatives of Entergy Nuclear Operations, Inc., held a telephone conference call on October 10, 2006, to discuss and clarify the staffs requests for additional information concerning the Vermont Yankee Nuclear Station license renewal application. The conference call was useful in clarifying the staffs questions. provides a listing of the conference call participants. Enclosure 2 contains a listing of the issues discussed with the applicant, including a brief discussion of the items status.

The applicant had an opportunity to comment on this summary.

/RA/

Jonathan Rowley, Project Manager License Renewal Branch B Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-271

Enclosures:

As stated cc w/encls: See next page

ML063050619 OFFICE PM:RLRB LA:RLRB BC:RLRB NAME JRowley S. Figueroa RAuluck DATE 11/2/06 11/2/06 11/6/06

Vermont Yankee Nuclear Power Station cc:

Regional Administrator, Region I U. S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406-1415 Mr. David R. Lewis Pillsbury, Winthrop, Shaw, Pittman, LLP 2300 N Street, N.W.

Washington, DC 20037-1128 Mr. David OBrien, Commissioner Vermont Department of Public Service 112 State Street Montpelier, VT 05620-2601 Mr. James Volz, Chairman Public Service Board State of Vermont 112 State Street Montpelier, VT 05620-2701 Chairman, Board of Selectmen Town of Vernon P.O. Box 116 Vernon, VT 05354-0116 Operating Experience Coordinator Vermont Yankee Nuclear Power Station 320 Governor Hunt Road Vernon, VT 05354 G. Dana Bisbee, Esq.

Deputy Attorney General 33 Capitol Street Concord, NH 03301-6937 Chief, Safety Unit Office of the Attorney General One Ashburton Place, 19th Floor Boston, MA 02108 Ms. Carla A. White, RRPT, CHP Radiological Health Vermont Department of Health P.O. Box 70, Drawer #43 108 Cherry Street Burlington, VT 05402-0070 Mr. James M. DeVincentis Manager, Licensing Vermont Yankee Nuclear Power Station P.O. Box 0500 185 Old Ferry Road Brattleboro, VT 05302-0500 Resident Inspector Vermont Yankee Nuclear Power Station U. S. Nuclear Regulatory Commission P.O. Box 176 Vernon, VT 05354 Director, Massachusetts Emergency Management Agency ATTN: James Muckerheide 400 Worcester Rd.

Framingham, MA 01702-5399 Jonathan M. Block, Esq.

Main Street P.O. Box 566 Putney, VT 05346-0566 Mr. John F. McCann Director, Licensing Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601 Mr. Gary J. Taylor Chief Executive Officer Entergy Operations 1340 Echelon Parkway Jackson, MS 39213

Vermont Yankee Nuclear Power Station cc:

Mr. John T. Herron Sr. VP and Chief Operating Officer Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601 Mr. Oscar Limpias Vice President, Engineering Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601 Mr. Christopher Schwartz Vice President, Operations Support Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601 Mr. Michael J. Colomb Director of Oversight Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601 Mr. Travis C. McCullough Assistant General Counsel Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601 Mr. Theodore Sullivan Site Vice President Entergy Nuclear Operations, Inc.

Vermont Yankee Nuclear Power Station P.O. Box 0500 185 Old Ferry Road Brattleboro, VT 05302-0500 Mr. James H. Sniezek 5486 Nithsdale Drive Salisbury, MD 21801 Mr. Garrett D. Edwards 814 Waverly Road Kennett Square, PA 19348 Ms. Stacey M. Lousteau Treasury Department Entergy Services, Inc.

639 Loyola Avenue New Orleans, LA 70113 Mr. Norman L. Rademacher Director, NSA Vermont Yankee Nuclear Power Station P.O. Box 0500 185 Old Ferry Road Brattleboro, VT 05302-0500 Mr. Raymond Shadis New England Coalition Post Office Box 98 Edgecomb, ME 04556 Mr. James P. Matteau Executive Director Windham Regional Commission 139 Main Street, Suite 505 Brattleboro, VT 05301 Mr. William K. Sherman Vermont Department of Public Service 112 State Street Drawer 20 Montpelier, VT 05620-2601 Mr. Michael D. Lyster 5931 Barclay Lane Naples, FL 34110-7306 Ms. Charlene D. Faison Manager, Licensing 440 Hamilton Avenue White Plains, NY 10601 Mr. James Ross Nuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, DC 20006-3708

Vermont Yankee Nuclear Power Station cc:

Diane Curran, Esq.

Harmon, Curran, Spielberg &

Eisenberg, L.L.P 1726 M Street, NW, Suite 600 Washington, DC 20036

Note to Entergy Nuclear Operations, Inc., from Jonathan Rowley dated November 6, 2006

SUBJECT:

SUMMARY

OF A TELEPHONE CONFERENCE CALL HELD ON OCTOBER 10, 2006, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY NUCLEAR OPERATIONS, INC., CONCERNING INFORMATION PERTAINING TO THE VERMONT YANKEE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION HARD COPY DLR R/F JRowley E-MAIL:

JFair RWeisman AMurphy RPettis GGalletti DShum GBagchi SSmith (srs3)

SDuraiswamy YL (Renee) Li RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDlrRlrc RidsNrrDlrReba RidsNrrDlrRebb RidsNrrDe RidsNrrDci RidsNrreEemb RidsNrrDeEeeb RidsNrrDeEqva RidsNrrDss RidsNrrDnrl RidsOgcMailCenter RidsNrrAdes JRowley RLaufer JShea CAnderson, RI RPowell, RI DScrenci, RI MModes, RI DPelton, Sr. Resident MYoung RidsOpaMail LIST OF PARTICIPANTS FOR TELEPHONE CONFERENCE CALL TO DISCUSS THE VERMONT YANKEE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION October 10, 2006 PARTICIPANTS AFFILIATIONS Jonathan Rowley U.S. Nuclear Regulatory Commission (NRC)

Michael Morgan NRC Dan Hoang NRC Kenneth Chang NRC Kaihwa Hsu NRC Greg Galletti NRC John Dreyfuss Entergy Nuclear Operations, Inc. (ENO)

Lori Potts ENO Alan Cox ENO Dave Lach ENO Jim DeVincentis ENO Mike Hamer ENO Mike Metel ENO Ted Ivey ENO VERMONT YANKEE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION October 10, 2006 The U.S. Nuclear Regulatory Commission staff (the staff) and representatives of Entergy Nuclear Operations, Inc., held a telephone conference call on October 10, 2006, to discuss and clarify the staffs requests for additional information (RAIs) and other issues concerning the Vermont Yankee Nuclear Power Station (VYNPS) license renewal application (LRA). The following issues were discussed during the telephone conference call:

RAI 3.6.2.2-N-08-1 The applicant responded to the staffs Request for Additional Information (RAI) 3.6.2.2-N-08 in a letter dated July 14, 2006, License Renewal Application, Amendment 4. In the letter the applicant stated:

Entergy, consistent with the Peach Bottom precedent, credited the [Federal Energy Regulatory Commission] FERC dam inspection program to manage the effects of aging on civil and structural elements of the [Vernon Hydroelectric Station] VHS.

A FERC letter to the previous owner of the VHS, New England Power Company (currently owned by TransCanada Hydro Northeast Inc.), dated August 6, 1997 states: By letter dated June 26, 1997, you requested an exemption from filing an Independent Consultants Safety Inspection Report under Part 12, Subpart D, of the Commissions Regulations... and...I am granting your request for an exemption from the Part 12, Subpart D requirement for submittal of an Independent Consultants Safety Inspection Report.

As the exemption is only on the filing of an Independent Consultants Safety Inspection Report under Part 12, Subpart D, describe specific Vermont Yankee Nuclear Power Station aging management activities, provide inspection reports, and describe any corrective actions that have been taken as a result of the inspection reports - as they pertain to the VHS in accordance with 10 CFR 54.21(a)(3) - since the exemption was granted.

Discussion: Prior to submitting its response to this RAI, the applicant wanted to inform the staff of new and significant information pertaining to the VHS. The applicant directed the staff to the Federal Energy Regulation Commission (FERC), where some operation reports containing information to be used in the applicants response reside. Due to FERC non-disclosure considerations associated with critical energy infrastructure information, the applicant was unable to provide the inspection reports directly. The staff was informed of the appropriate report numbers and will obtain them from FERC. The applicant will reference these reports in the RAI response.