Revision of Schedule for the Conduct of Review of the Monticello Nuclear Generating Plant License Renewal Application
ML062790037
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 10/10/2006
From: Daniel Merzke
NRC/NRR/ADRO/DLR/RLRB
To: Conway J
Nuclear Management Co
Merzke, D., NRR/ADRO/DLR/RLRB, 415-3777
References
Download: ML062790037 (4)


Text

October 10, 2006 Mr. John T. Conway Site Vice President Nuclear Management Company, LLC 2807 West County Road 75 Monticello, MN 55362-9637

SUBJECT:

REVISION OF SCHEDULE FOR THE CONDUCT OF REVIEW OF THE MONTICELLO NUCLEAR GENERATING PLANT LICENSE RENEWAL APPLICATION

Dear Mr. Conway:

Enclosed is a revised schedule for review of the Monticello Nuclear Generating Plant (MNGP) license renewal application (LRA). This schedule has been revised to reflect the new date for the decision to be made on the approval of the MNGP LRA by the Director of the Office of Nuclear Reactor Regulation. If you have any questions on the revised schedule, please contact me by telephone at 301-415-3777 or via e-mail at DXM2@nrc.gov.

Sincerely,

/RA/

Daniel J. Merzke, Project Manager License Renewal Branch B Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-263

Enclosure:

As stated cc w/encl: See next page

ML062790037 Document Name: E:\\Filenet\\ML062790037.wpd OFFICE PM:RLRM LA:RLRB BC:RLRB NAME DMerzke IKing JZimmerman LTran for DATE 10/10/06 10/05/06 10/10/06

Enclosure Monticello Nuclear Generating Plant LICENSE RENEWAL APPLICATION REVIEW MILESTONES Milestone Schedule Actual Receive License Renewal (LR) Application 03/24/05 03/24/05 Federal Register Notice (FRN) published - Receipt & Availability review 04/06/05 04/06/05 Public Information Meeting - LR Process & Safety Review Overview 04/20/05 04/20/05 FRN published - Acceptability/Opportunity for Hearing 05/10/05 05/12/05 FRN published - Intent/Environmental Scoping Meeting 06/03/05 06/02/05 Public Exit Meeting - Scoping & Screening Methodology Audit 06/24/05 06/24/05 Public Meeting - Environmental Scoping 06/30/05 06/30/05 Deadline for filing hearing requests and petitions for intervention 07/11/05 07/11/05 Environmental Scoping Periods Ends 08/02/05 08/02/05 Public Exit Meeting - AMP/AMR Audit 08/18/05 08/18/05 Environmental Requests for Additional Information (RAIs) - issued 08/26/05 08/26/05 Environmental RAIs - responses received 10/07/05 10/07/05 Safety RAIs - issued 11/01/05 11/07/05 Safety RAI - responses received 12/01/05 12/07/05 Draft Supplemental Environmental Impact Statement (SEIS) Issued 02/10/06 01/23/06 FRN Published - Availability/Comment on draft SEIS 02/17/06 02/02/06 Public Exit Meeting - Scoping & Screening/AMP Inspections 02/22/06 02/22/06 Public Meeting - draft SEIS 03/22/06 03/22/06 Safety Evaluation Report (SER) with Open Item(s) - Issued 04/28/06 04/26/06 End of draft SEIS comment period 05/04/06 05/04/06 ACRS Subcommittee Meeting on SER with Open Item(s) 06/06 05/30/06 SER Open Item(s) - Response(s) Received 06/23/06 06/15/06 Final SEIS - issued 09/22/06 09/19/06 FRN published - Availability of Final SEIS 09/29/06 09/27/06 SER - issued 10/04/06 07/28/06 ACRS Full Committee Meeting on SER 11/06 09/07/06 Decision - Director, NRR (license issued, if approved) 11/07/06

Letter to Mr. J. T. Conway from D. Merzke dated October 10, 2006

SUBJECT:

REVISION OF SCHEDULE FOR THE CONDUCT OF REVIEW OF THE MONTICELLO NUCLEAR GENERATING PLANT LICENSE RENEWAL APPLICATION DISTRIBUTION:

HARD COPY DLR R/F E-MAIL:

JFair RWeisman AMurphy RPettis GGalletti DShum GBagchi SSmith (srs3)

SDuraiswamy YL (Renee) Li RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDlrRlrc RidsNrrDlrReba RidsNrrDlrRebb RidsNrrDe RidsNrrDci RidsNrreEemb RidsNrrDeEeeb RidsNrrDeEqva RidsNrrDss RidsNrrDnrl RidsOgcMailCenter RidsNrrAdes LRaghavan PTam AStone, RIII BBurgess, RIII PLougheed, RIII SRay, RIII AHodgdon RidsOpaMail