October 4, 2006 South Carolina Electric & Gas Company ATTN: Mr. Jeffrey B. Archie Vice President, Nuclear Operations Virgil C. Summer Nuclear Station P. O. Box 88 Jenkinsville, SC 29065

SUBJECT:

PUBLIC MEETING

SUMMARY

- REFUELING OUTAGE 16 - VIRGIL C.

SUMMER NUCLEAR STATION, DOCKET NO. 50-395

Dear Mr. Archie:

This refers to the meeting conducted at your staffs request at the Region II Office in Atlanta, Georgia, on September 27, 2006, at 10:30 a.m. The meetings purpose was to discuss your planned activities during Refueling Outage 16 at the Virgil C. Summer Nuclear Station.

Enclosed is a list of attendees. The presentation material used for the discussion is available from the NRCs document system (ADAMS) as accession number ML062760245.

It is our opinion that this meeting was beneficial, in that, your staff presented an informative overview of activities to be performed during the Refueling Outage 16, including goals and major modifications and work activities, and a description of the planned recirculation sump design changes.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room (PDR) or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

SCE&G 2 Should you have any questions concerning this letter, please contact me at (404) 562-4662.

Sincerely,

/RA/

Eugene F. Guthrie, Chief Reactor Projects Branch 5 Division of Reactor Projects Docket No.: 50-395 License No.: NPP-12

Enclosure:

List of Attendees cc w/encl: (See page 3)

OFFICE RII:DRP SIGNATURE LXG1 NAME LGarner:aws DATE 10/03/2006 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO SCE&G 3 cc w/encl:

R. J. White Nuclear Coordinator Mail Code 802 S.C. Public Service Authority Virgil C. Summer Nuclear Station Electronic Mail Distribution Kathryn M. Sutton, Esq.

Morgan, Lewis & Bockius LLP Electronic Mail Distribution Henry J. Porter, Director Div. of Radioactive Waste Mgmt.

Dept. of Health and Environmental Control Electronic Mail Distribution R. Mike Gandy Division of Radioactive Waste Mgmt.

S. C. Department of Health and Environmental Control Electronic Mail Distribution Robert G. Sweet, Manager Nuclear Licensing (Mail Code 830)

South Carolina Electric & Gas Company Virgil C. Summer Nuclear Station Electronic Mail Distribution Robert M. Fowlkes, General Manager Engineering Services South Carolina Electric & Gas Company Virgil C. Summer Nuclear Station Electronic Mail Distribution Thomas D. Gatlin, General Manager Nuclear Plant Operations (Mail Code 303)

South Carolina Electric & Gas Company Virgil C. Summer Nuclear Station Electronic Mail Distribution David A. Lavigne, General Manager Organization Development South Carolina Electric & Gas Company Vigil C. Summer Nuclear Station Electronic Mail Distribution Distribution w/encl: (See page 4)

SCE&G 4 Meeting Summary letter to Jeffrey B. Archie from Eugene F. Guthrie dated October 4, 2006

SUBJECT:

PUBLIC MEETING

SUMMARY

- REFUELING OUTAGE 16 - VIRGIL C.

SUMMER NUCLEAR STATION, DOCKET NO. 50-395 Distribution w/encl.:

R. Martin, NRR L. Slack, RII RIDSNRRDIRS PUBLIC

LIST OF ATTENDEES Nuclear Regulatory Commission W. Travers, Regional Administrator, Region II (RII)

H. Christensen, Deputy Director, Division of Reactor Safety (DRS), RII E. Guthrie, Branch Chief, Branch 5, Division of Reactor Projects (DRP), RII L. Garner, Senior Project Engineer, Branches 5 & 6, DRP, RII C. Peabody, Reactor Inspector, DRS, RII South Carolina Electric and Gas Company (Virgil C. Summer Nuclear Station)

J. Archie, Site Vice President D. Gatlin, Plant Manager A. Torres, Manager, Planning and Scheduling B. Stokes, Manager, Design Engineering R. Sweet, Manager, Licensing K. Weir, Supervisor, Design Engineering Enclosure