2005 Regulatory Commitment Change Summary Report
ML062710353
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 09/15/2006
From: Enright D
Exelon Generation Co, Exelon Nuclear
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
RA-06-64
Download: ML062710353 (2)


Text

Exel fl,.

Exelon Generation Company, LLC www.exeloncorp.com Nuclear LaSalle County Station 2601 North 21'tRoad Marseilles, I L 61341-9757 RA-06-64 September 15, 2006 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555-0001 LaSalle County Station, Units 1 and 2 Facility Operating License Nos. NPF-1 1 and NPF-18 NRC Docket Nos. 50-373 and 50-374

SUBJECT:

2005 Regulatory Commitment Change Summary Report Enclosed is the Exelon Generation Company, LLC, (EGC), 2005 commitment change summary for LaSalle County Station. Revisions to docketed correspondence were processed using the Nuclear Energy Institute's (NEI) 99-04, Revision 0, "Guidelines for Managing NRC Commitment Changes," dated July 1999.

Should you have any questions concerning this letter, please contact Mr. Terrence Simpkin at (815)-415-2800.

Respectfully, Daniel Enright Plant Manager LaSalle County Station Attachment cc:

Regional Administrator, NRC Region III NRC Senior Resident Inspector - LaSalle County Station

ATTACHMENT 2005 LaSalle County Station Commitment Change Summary Commitment Date of Original Original Commitment Changed Commitment Basis for Change Change Commitment Document Tracking No. Change 05-001 6/24/2005 GL 89-13 The portion of the Lake Screen The portion of the Lake Screen The Lake Screen House Intake House Intake Structure from the House Intake Structure from the Structure has shown significant area downstream of the bar grill area downstream of the bar grill decrease in the amount of silt to the circulating water system to the circulating water system and debris over the last three pump inlets is inspected for pump inlets is inspected for years. In addition, changing the accumulation of silt, corbicula or accumulation of silt, corbicula or inspection frequency to once zebra mussel infestation, zebra mussel infestation, every two years will meet the biological debris and concrete biological debris and concrete minimum requirements of GL 89-degradation once each year.

degradation once every two 13 to visually inspect once per years.

refueling cycle.05-002 Number Not Used 05-003 8/5/2005 Notice of Violation Conduct detailed technical Deleted the commitment.

Improvements made in the Response dated review meetings with the fuel current Exelon reload process 2/14/1989, vendors on each reload design.

made the commitment for Inspection Report additional review meetings Nos. 50-redundant.

373/88022 and 374-88021