Action Request - Corrective Action Program (CAP) (CAP064648)
ML062650395
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 05/18/2005
From:
- No Known Affiliation
To:
Office of Nuclear Reactor Regulation
References
CAP064648, FOIA/PA-2006-0113
Download: ML062650395 (1)


Text

TeamTrack Reports Page 10 of 47 NMC > Sites > Point Beach - Action Request > Corrective Actn Program (CAP) AR 4! C Section 1 Activity Request Id:

qCAP06464484 Activity Type:

CAP Submit Date:

5/18/2005 10:59:43 AM I One Line

Description:

24-Hour FFD ENS Report Issued by NRC Operations Center Contained Error Detailed

Description:

5/18/2005 10:59:43 AM - FLENTJE, FRITZIE:

A 24-hour FFD ENS report (EN 41705) was submitted by PBNP on 05/17105. The report was submitted on the Unit I docket, as is the practice for reporting of events that are non-physical plant and not unit-specific, such as security events. The NRC daily report of the event indicated that Unit 2 was at full power. Unit 2 is shut down for its refueling outage. (Copies of the as -submitted ENS worksheet and daily event report are attached.)

Initiator:

FLENTJE, FRITZIE C Initiator Department:

SRL Licensing 1 Date/Time of Discovery: 5/18/2005 10:41:35 AM Datemme of Occurrence:

5/18/2005 10:41:35 AM Identified By:

Site-identified System:

(None)

Equipment # (1st):

(None)

Equipment Name (1st):

(None)

Equipment # (2nd):

(None)

Equipment Name (2nd):

(None)

Equipment # (3rd):

(None)

Equipment Name (3rd):

(None)

SitelUnit:

Point Beach - None Why did this occur?:

5/18/2005 10:59:43 AM - FLENTJE, FRITZIE:

Data provided appears to have been modified following receipt at NRC Operations Center.

Immediate Action Taken: 5/18/2005 10:59:43 AM - FLENTJE, FRITZIE:

Discussed with PBNP NRC Senior Resident Inspector. Item was also noted by NRC during daily phone call.

NRC will follow up with Operations Center.

Recommendations:

5/18/2005 10:59:43 AM - FLENTJE, FRITZIE:

None. Per NRC Senior Resident Inspector, no further action is required on the part of NMC.

0 SRO Review Required?: N Section 2 Operability Status:

Basis for Operability:

0 Unplanned TSAC Entry:

NA 0 Compensatory Actions:

5/18/2005 10:59:43 AM - FLENTJE, FRITZIE:

Not an operability issue.

N 5/18/2005 12:30:26 PM - JESSESSKY, TOM:

No system, structure or component important to nuclear safety is identified as being degraded.

N

@ External Notification: