MONTHYEARML24036A2652024-02-0505 February 2024 Notice of Inspection and Request for Information for the NRC Age-Related Degradation Inspection: Inspection Report 05000266/2024010 and 05000301/2024010 ML24030A0352024-01-30030 January 2024 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection IR 05000266/20230052023-08-24024 August 2023 Updated Inspection Plan for Point Beach Nuclear Plant (Report 05000266/2023005 and 05000301/2023005) ML23163A2422023-06-13013 June 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000266/2023004 IR 05000266/20220062023-03-0101 March 2023 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2022006 and 05000301/2022006) ML23003A8022023-01-0303 January 2023 Notification of NRC Baseline Inspection and Request for Information ML22256A3182022-09-13013 September 2022 Request for Information for an NRC Quadrennial Comprehensive Engineering Team Inspection Report 05000266/2023010 05000301/2023010 IR 05000266/20220052022-08-26026 August 2022 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2022005 and 05000301/2022005) ML22175A2002022-06-27027 June 2022 Request for Information for an NRC Triennial Heat Exchanger/Sink Performance Inspection and Request for Information: Inspection Report 05000266/2022004: 05000301/2022004 ML22172A2132022-06-22022 June 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection ML22173A0172022-06-22022 June 2022 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Point Beach Nuclear Plant IR 05000266/20210062022-03-0202 March 2022 Annual Assessment Letter for Point Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2021006 and 05000301/2021006) ML22041B0752022-02-10010 February 2022 Notification of NRC Baseline Inspection and Request for Information Inspection Report 05000266/2022002 ML21253A1672021-09-10010 September 2021 Notification of NRC Design Bases Assurance Inspection (Programs) and Initial Request for Information Inspection Report 05000266/2022010 05000301/2022010 IR 05000266/20210052021-09-0101 September 2021 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2021005 and 05000301/2021005) ML21214A2812021-08-0202 August 2021 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML21180A2302021-06-29029 June 2021 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000266/2021004 and 05000301/2021004 ML21074A3962021-03-15015 March 2021 Information Request for NRC Triennial Evaluations of Changes, Tests, and Experiments (50.59) Baseline Inspection; Inspection Report 05000266/2021010; 05000301/2021010 IR 05000266/20200062021-03-0404 March 2021 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2020006 and 05000301/2020006) IR 05000266/20200052020-09-0101 September 2020 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2020005 and 05000301/2020005) ML20218A4322020-08-0505 August 2020 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000266/2020004 ML20168A8912020-06-15015 June 2020 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Point Beach Nuclear Plant, Units 1 and 2 IR 05000266/20190062020-03-0303 March 2020 Annual Assessment Letter for Point Beach Nuclear Plants, Units 1 and 2 (Report 05000266/2019006 and 05000301/2019006) IR 05000266/20190052019-08-28028 August 2019 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2019005 and 05000301/2019005) ML19190A1532019-07-0909 July 2019 Ltr. 07/09/19 Point Beach Nuclear Plant, Units 1 and 2 - Notification of NRC Triennial Fire Protection Baseline Inspection Request for Information; Inspection Report 05000266/2019012; 05000301/2019012 (DRS-G.Hausman) ML19136A1402019-05-15015 May 2019 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection (Garza) ML19094B1182019-04-0404 April 2019 Ltr. 04/04/19 Point Beach Nuclear Plant, Units 1 and 2 - Request for Information for an NRC Design Bases Assurance Inspection (Program): Implementation of the EQ Program; Inspection Report 05000266/2019013 and 05000301/2019013 (DRS-B.Jose) IR 05000266/20180062019-03-0404 March 2019 Annual Assessment Letter for Point Beach Nuclear Plant (Report 05000266/2018006 and 05000301/2018006) ML19037A3102019-02-0505 February 2019 Ltr. 02/05/19 Point Beach Nuclear Plant, Units 1 and 2 - Information Request for the Cyber-Security Full Implementation Inspection, Notification to Perform Inspection; Inspection Report 05000266/2019412; 05000301/2019412 (DRS-G.Hausman) ML19024A2772019-01-24024 January 2019 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000266/2019001 (DRS-M.Domke) IR 05000266/20180052018-08-28028 August 2018 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2018005 and 05000301/2018005) IR 05000266/20170062018-03-0202 March 2018 Annual Assessment Letter for Point Beach Plant, Units 1 and 2 (Report 05000266/2017006 and 05000301/2017006) IR 05000266/20170052017-08-28028 August 2017 Updated Inspection Plan (Report 05000266/2017005 and 05000301/2017005) ML17088A7242017-03-29029 March 2017 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team): Inspection Report 05000266/2017007; 05000301/2017007 IR 05000266/20160062017-03-0101 March 2017 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2016006 and 05000301/2016006) ML17039B0182017-02-0808 February 2017 Information Request to Support Upcoming Temporary Instruction 2515/191 Inspection at Point Beach Nuclear Plant, Units 1 and 2 - Inspection Report 05000266/2017008; 05000301/2017008 IR 05000266/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Point Beach Nuclear Plant Units 1 and 2 (Report 05000266/2016005; 05000301/2016005) IR 05000266/20150062016-03-0202 March 2016 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Inspection Report 05000266/2015006 and 05000301/2015006) IR 05000266/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2015005; 05000301/2015005) ML15131A3132015-05-0808 May 2015 Ltr. 05/08/15 Point Beach Nuclear Plant, Units 1 and 2 - Information Request for an NRC Triennial Permanent Modifications and 10 CFR 50.59 (Mod/50.59) Baseline Inspection 05000266/2015010; 05000301/2015010 (Jjc) ML15124A9012015-05-0101 May 2015 Ltr. 05/01/15 Point Beach Nuclear Plant, Unit 2 - Notification of NRC Inspection and Request for Information (Msh) IR 05000266/20140012015-03-0404 March 2015 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2014001; 05000301/2014001) ML15050A2702015-02-19019 February 2015 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Point Beach Nuclear Plant, Units 1 and 2 ML14245A1662014-09-0202 September 2014 Mid-Cycle Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 IR 05000266/20130012014-03-0404 March 2014 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2013001; 05000301/2013001) ML14038A3472014-02-0606 February 2014 ISI Request for Information ML13246A2212013-09-0303 September 2013 2013 Point Beach MOC Letter Combined ML13172A4072013-06-20020 June 2013 Notification of NRC Triennial Fire Protection Baseline Inspection Request for Information 05000266-13-010; 05000301-13-010 ML13129A1952013-05-0909 May 2013 Ltr 5/9/13 Point Beach Ti 2515-182 Phase 2 Request for Information IR 05000266/20120012013-03-0404 March 2013 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (05000266/2012001; 05000301/2012001) 2024-02-05
[Table view] Category:Letter
MONTHYEARML24036A2652024-02-0505 February 2024 Notice of Inspection and Request for Information for the NRC Age-Related Degradation Inspection: Inspection Report 05000266/2024010 and 05000301/2024010 IR 05000266/20230042024-02-0101 February 2024 Integrated Inspection Report 05000266/2023004 and 05000301/2023004 ML24030A0352024-01-30030 January 2024 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection L-2024-001, Relief Request CISl-03-01 for Relief Concerning Containment Unbonded Post-Tensioning System Inservice Inspection Requirements2024-01-26026 January 2024 Relief Request CISl-03-01 for Relief Concerning Containment Unbonded Post-Tensioning System Inservice Inspection Requirements L-2024-010, Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3)2024-01-25025 January 2024 Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3) ML24005A3242024-01-24024 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0040 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23352A2752024-01-23023 January 2024 Issuance of Amendment Nos. 274 and 276 Regarding Revision to Technical Specification 5.5.17, Pre-Stressed Concrete Containment Tendon Surveillance Program L-2023-173, Quality Assurance Topical Report (FPL-1) Revision 30 Update2023-12-15015 December 2023 Quality Assurance Topical Report (FPL-1) Revision 30 Update L-2023-174, Subsequent License Renewal Application - Third Annual Update2023-12-13013 December 2023 Subsequent License Renewal Application - Third Annual Update L-2023-176, Supplement to Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule2023-11-29029 November 2023 Supplement to Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule L-2023-155, Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-06542023-11-28028 November 2023 Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, L-2023-159, Part 3 Exemption Request Regarding Enhanced Weapons, Firearms Background Checks and Security Event Notifications Final Rule2023-11-16016 November 2023 Part 3 Exemption Request Regarding Enhanced Weapons, Firearms Background Checks and Security Event Notifications Final Rule IR 05000266/20234022023-11-14014 November 2023 Security Baseline Inspection Report 05000266/2023402 and 05000301/2023402 ML23279A0672023-11-0909 November 2023 Issuance of Relief Request I6 RR 02 - Examination of the Unit 2 Steam Generator Feedwater Nozzle Extension to Nozzle Weld Sixth 10 Year Inservice Inspection Program Interval IR 05000266/20230032023-10-16016 October 2023 Integrated Inspection Report 05000266/2023003 and 05000301/2023003 ML23346A1322023-10-0606 October 2023 Communication from C-10 Research & Education Foundation Regarding NextEra Common Emergency Fleet Plan License Amendment Request and Related Documents Subsequently Published L-2023-128, License Amendment Request to Revise TS 5.5.17, Pre-Stressed Concrete Containment Tendon Surveillance Program2023-09-19019 September 2023 License Amendment Request to Revise TS 5.5.17, Pre-Stressed Concrete Containment Tendon Surveillance Program ML23243A9102023-09-0606 September 2023 Closeout of Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors IR 05000266/20235012023-08-29029 August 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000266/2023501 and 05000301/2023501 ML23208A2262023-08-28028 August 2023 Exemption from the Requirements of 10 CFR 50,46, Acceptance Criteria for Emergency Core Cooling Systems for Light Water Nuclear Power Reactors (EPID L-2022-LLE-0026) - Letter ML23208A0952023-08-28028 August 2023 Issuance of Amendment Nos. 273 and 275 Regarding Revising Licensing Basis to Address Generic Safety Issue-191 and Respond to Generic Letter 2004-02 Using a Risk Informed Approach IR 05000266/20230052023-08-24024 August 2023 Updated Inspection Plan for Point Beach Nuclear Plant (Report 05000266/2023005 and 05000301/2023005) ML23160A0642023-08-21021 August 2023 Issuance of Amendment Nos. 272 and 274 Regarding Revision to Use Beacon Power Distribution Monitoring System L-2023-114, Proposed Turkey Point Units 6 and 7; Seabrook Station; Point Beach Units 1 and 2 - Official Service List Update2023-08-17017 August 2023 Proposed Turkey Point Units 6 and 7; Seabrook Station; Point Beach Units 1 and 2 - Official Service List Update ML23221A0522023-08-0909 August 2023 Confirmation of Initial License Examination, March 2024 L-2023-098, and Point Beach Units 1 and 2 - Response to Request for Additional Information Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 22023-08-0707 August 2023 and Point Beach Units 1 and 2 - Response to Request for Additional Information Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 2 ML23201A0872023-08-0303 August 2023 Audit Plan in Support of Review of License Amendment L-2023-089, Refueling Outage Owner'S Activity Report (OAR-1) Unit 2 for Inservice Inspections2023-07-24024 July 2023 Refueling Outage Owner'S Activity Report (OAR-1) Unit 2 for Inservice Inspections IR 05000266/20230022023-07-18018 July 2023 Integrated Inspection Report 05000266/2023002 and 05000301/2023002 IR 05000266/20234012023-07-13013 July 2023 Public-Point Beach Nuclear Plant-Security Baseline Inspection Report 05000266/2023401; 05000301/2023401; Independent Spent Fuel Storage Security Inspection Report 07200005/2023401 L-2023-087, Florida Power & Light/Nextera Energy, Results of the Safety Culture Program Effectiveness Review, March 20, 2023 (ADAMS Accession No. ML22340A452)2023-06-29029 June 2023 Florida Power & Light/Nextera Energy, Results of the Safety Culture Program Effectiveness Review, March 20, 2023 (ADAMS Accession No. ML22340A452) ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III L-2023-088, 10 CFR 50.55a Requests, Relief Requests I6-RR-1, I6-RR-2, and I6-RR-3 Sixth Ten-Year Inservice Inspection Program Interval2023-06-27027 June 2023 10 CFR 50.55a Requests, Relief Requests I6-RR-1, I6-RR-2, and I6-RR-3 Sixth Ten-Year Inservice Inspection Program Interval ML23171B1062023-06-21021 June 2023 Info Meeting with a Question and Answer Session to Discuss NRC 2022 EOC Plant Performance Assessment of Ptbh, Units 1 and 2 ML23163A2422023-06-13013 June 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000266/2023004 L-2023-075, Response to Request for Additional Information (RAI) Regarding Exemption Request, License Amendment Request and Revised Response in Support of a Risk-Informed Resolution of Generic Letter 2004-022023-06-0909 June 2023 Response to Request for Additional Information (RAI) Regarding Exemption Request, License Amendment Request and Revised Response in Support of a Risk-Informed Resolution of Generic Letter 2004-02 L-2023-073, Subsequent License Renewal Application, Second Annual Update Request for Additional Information Set 1 Response2023-06-0101 June 2023 Subsequent License Renewal Application, Second Annual Update Request for Additional Information Set 1 Response ML23103A1332023-06-0101 June 2023 Issuance of Amendment Nos. 271 and 273 Regarding Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b L-2023-071, NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 29 and Florida Power and Light Company Quality Assurance Program Description for 10 CFR Part 52 Licenses (FPL-2) Revision 11, Annual Submittal2023-05-22022 May 2023 NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 29 and Florida Power and Light Company Quality Assurance Program Description for 10 CFR Part 52 Licenses (FPL-2) Revision 11, Annual Submittal ML23118A1762023-05-0404 May 2023 Audit Summary for License Amendment Request Regarding Risk-Informed Approach for Closure of Generic Safety Issue 191 IR 05000266/20230012023-05-0101 May 2023 Integrated Inspection Report 05000266/2023001 and 05000301/2023001 ML23114A1222023-04-25025 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection L-2023-058, 2022 Annual Monitoring Report2023-04-10010 April 2023 2022 Annual Monitoring Report L-2023-021, Units, 1 and 2, Turkey Point, Units 3 and 4, Seabrook Station and Point Beach, Units 1 and 2 - Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update2023-03-28028 March 2023 Units, 1 and 2, Turkey Point, Units 3 and 4, Seabrook Station and Point Beach, Units 1 and 2 - Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update L-2023-028, and Point Beach Units 1 and 2, 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications2023-03-27027 March 2023 and Point Beach Units 1 and 2, 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications 2024-02-05
[Table view] |
Text
August 31, 2006 Mr. Dennis L. Koehl Site Vice President Point Beach Nuclear Plant Nuclear Management Company, LLC 6590 Nuclear Road Two Rivers, WI 54241-9516
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -
POINT BEACH NUCLEAR PLANT
Dear Mr. Koehl:
On August 7, 2006, the NRC staff completed its performance review of the Point Beach Nuclear Plant for the first half of the calendar year 2006 assessment cycle. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results over the previous 12 months. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and enclosed inspection plan do not include physical protection information. A separate letter, designated and marked Exempt from Public Disclosure in Accordance with 10 CFR 2.390, will include the physical protection review and resultant inspection plan.
Overall, Point Beach Nuclear Plant Units 1 and 2 operated in a manner that preserved public health and safety and met all cornerstone objectives. Plant performance for the most recent quarter remained within the Multiple/Repetitive Degraded Cornerstone Column of the Action Matrix. This is based on two Red findings for Unit 1 and Unit 2 associated with the auxiliary feedwater and instrument air systems, and a Yellow finding for Unit 1 and a Red finding for Unit 2 associated with the potential failure of the auxiliary feedwater pumps due to plugging of recirculation line orifices. All of these findings were in the Mitigating Systems cornerstone. The Nuclear Management Company (NMC) was initially notified that Point Beach Nuclear Plant had entered the Multiple/Repetitive Degraded Cornerstone Column in a letter dated April 2, 2003.
The NRC will continue to closely monitor Point Beach performance consistent with the guidance in Inspection Manual Chapter (IMC) 0305, Operating Reactor Assessment Program.
In addition to the routine NRC inspection and mid-cycle and end-of-cycle assessment activities, Point Beach performance is being evaluated quarterly. Consistent with IMC 0305, plants in the Multiple/Repetitive Degraded Cornerstone Column are given consideration at each quarterly performance assessment review for: (1) declaring plant performance to be unacceptable in accordance with the guidance in IMC 0305; (2) transferring to the IMC 0350 Oversight of Operating Reactor Facilities in a Shutdown Condition with Performance Problems process; and (3) taking additional regulatory actions, as appropriate. Our quarterly assessment results, to date, have concluded that Point Beach has been operated in a manner that preserved the public health and safety; therefore, the plant will remain in Column IV of the NRC Action Matrix.
D. Koehl On April 21, 2004, a Confirmatory Action Letter (CAL) 3-04-001 was issued to document your commitments to address the Red inspection findings and implement other improvement initiatives. The CAL listed five areas of regulatory concern: Human Performance, Engineering Design Control, Engineering/Operations Interface, Emergency Preparedness, and the Corrective Action Program. On April 14, 2006, the CAL was revised after NRC inspections had shown that adequate progress had been made in addressing four of the five areas. The remaining area, Engineering Design Control, will remain open pending a satisfactory review by the NRC of, at least, the initial implementation of the engineering assessment commitments, continued progress in the calculation upgrade project, and effectiveness of previous improvement initiatives and corrective actions in engineering. Specifically, the NMC needs to continue to demonstrate the ability to understand and recognize complex engineering questions/problems at Point Beach. These matters then need to be dispositioned in an accurate and comprehensive manner, taking into account all relevant design and licensing basis information and reaching a sound, justified conclusion without the need for extensive NRC involvement. As we determined in the Inspection Procedure 95003 inspection in 2003, engineering and design control weaknesses were found to be the root causes of the Red finding associated with the auxiliary feedwater and instrument air. As a result, it will be necessary for NMC to demonstrate sustained improvements in the Engineering Design Control area prior to the NRC closing these two Red findings.
In our Annual Assessment Letter dated March 2, 2006, we advised you that we had closed the substantive cross-cutting issues in the areas of Human Performance and Problem Identification and Resolution (PI&R). For the Human Performance area, this was based on a low number of findings and the lack of a common causal theme. For the PI&R area, where the number of findings exceeded our threshold, this was based on the NRCs assurance with the scope of your efforts in addressing the problems. Our 2006 Mid-Cycle Assessment concluded that your successful efforts in the Human Performance area continue. In the PI&R area, the number of problems with the same cross-cutting aspect again exceeded our threshold; however, the number of problems identified in the past 6 months of the assessment period has declined from the first 6 months, giving us assurance with your progress and the scope of your efforts to address these problems. Consequently, the substantive cross-cutting issues in the Human Performance and PI&R areas will remain closed.
On March 23, 2006, the NRC held a public meeting with NMC to discuss the actions taken or planned based on the results of a safety culture survey conducted at the plant in late 2004. A similar survey is planned for August 2006. The results of this survey, which should be indicative of the overall effectiveness of the actions taken in response to the 2004 survey, will be reviewed during the NRCs baseline Problem Identification and Resolution inspection scheduled for December 2006.
The enclosed inspection plan details the inspections scheduled through March 2008. The enclosed inspection plan is provided to minimize the resource impact on your staff and to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last 9 months of the inspection plan are tentative and may be revised at the end-of-cycle review meeting.
D. Koehl In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact Patrick Louden at (630) 829-9627 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
James L. Caldwell Regional Administrator Docket Nos. 50-266; 50-301 License Nos. DPR-24; DPR-27
Enclosure:
Point Beach Inspection/Activity Plan DISTRIBUTION See next page
D. Koehl In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact Patrick Louden at (630) 829-9627 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
James L. Caldwell Regional Administrator Docket Nos. 50-266; 50-301 License Nos. DPR-24; DPR-27
Enclosure:
Point Beach Inspection/Activity Plan DISTRIBUTION See next page DOCUMENT NAME:G:\Branch TSS\ALL MOC\midcycle 2005 to 2006\point beach\Point Beach MOC letter 2006.wpd X Publicly Available G Non-Publicly Available G Sensitive X Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII RIII NAME PLouden for PLouden MSatorius JCaldwell MKunowski:sls DATE 08/21/2006 08/21/2006 08/25/2006 08/29/2006 OFFICIAL RECORD COPY
D. Koehl cc w/encl: F. Kuester, President and Chief Executive Officer, We Generation D. Cooper, Senior Vice President, Group Operations J. McCarthy, Site Director of Operations D. Weaver, Nuclear Asset Manager Plant Manager Regulatory Affairs Manager Training Manager Site Assessment Manager Site Engineering Director Emergency Planning Manager J. Rogoff, Vice President, Counsel & Secretary K. Duveneck, Town Chairman Town of Two Creeks Chairperson Public Service Commission of Wisconsin J. Kitsembel, Electric Division Public Service Commission of Wisconsin State Liaison Officer Chairman, Manitowoc County Board County Executive, Manitowoc Director, Manitowac County Emergency Management Agency Chairman, Kewaunee County Board Mayor of Kewaunee City Manager, Two Rivers Director, Kewaunee County Emergency Management Agency President, Village of Mishicot Chairman, Village of Two Creeks INPO
D. Koehl ADAMS Distribution:
EMH1 LXR1 CFL TEB RidsNrrDirslpab JLC1 GEG KGO RML2 SRI Point Beach DRPIII DRSIII PLB1 TXN ROPreports@nrc.gov (inspection reports, final SDP letters, any letter with an IR number)
Page 1 of 2 Point Beach 08/30/2006 13:02:47 Inspection / Activity Plan Report 22 09/01/2006 - 03/31/2008 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type HEAD - SPECIAL INSPECTION OF HEAD DROP ANALYSIS 3 1, 2 IP 93812 Special Inspection 04/01/2006 12/31/2006 Event Response Insp CDBI - COMPONENT DESIGN BASES INSPECTION 7 1, 2 IP 95003 Inspection For Repetitive Degraded Cornerstones, Multiple Degraded Cornerstones, Multiple 06/01/2006 09/29/2006 Supplemental Program 1, 2 IP 7111121 Component Design Bases Inspection 08/28/2006 09/29/2006 Baseline Inspections ISI - POINT BEACH UNIT 2 ISI INSPECTION 1 2 IP 7111108P Inservice Inspection Activities - PWR 10/23/2006 11/03/2006 Baseline Inspections BI - OUTAGE ACCESS CONTROL (ALARA) 1 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 10/23/2006 11/03/2006 Baseline Inspections 1, 2 IP 7112102 ALARA Planning and Controls 10/23/2006 11/03/2006 Baseline Inspections 71114 - BIENNIAL EP EXERCISE 1 1, 2 IP 7111401 Exercise Evaluation 12/04/2006 12/08/2006 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 12/04/2006 12/08/2006 Baseline Inspections PI&R - PI&R TEAM INSPECTION 5 1, 2 IP 71152B Identification and Resolution of Problems 11/20/2006 12/15/2006 Baseline Inspections 7112102 - POST OUTAGE ALARA (ACCESS CONTROL) 1 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 12/04/2006 12/08/2006 Baseline Inspections 1, 2 IP 7112102 ALARA Planning and Controls 12/04/2006 12/08/2006 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 12/04/2006 12/08/2006 Baseline Inspections BI - RAD INSTUMENTATION 1 1, 2 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 03/12/2007 03/16/2007 Baseline Inspections ISI - ISI BASELINE INSPECTION 1 1 IP 7111108P Inservice Inspection Activities - PWR 04/02/2007 04/27/2007 Baseline Inspections 7112101 - OUTAGE ACCESS CONTROL AND ALARA 2 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 04/16/2007 04/27/2007 Baseline Inspections 1, 2 IP 7112102 ALARA Planning and Controls 04/16/2007 04/27/2007 Baseline Inspections FY 2007 - POINT BEACH INIT PREP 06/2007 3 1 W90164 OL - INITIAL EXAM - POINT BEACH - JUN/JUL 2007 06/18/2007 06/22/2007 Not Applicable FPI - FIRE PROTECTION INSPECTION - TRIENNIAL 3 1, 2 IP 7111105T Fire Protection [Triennial] 06/25/2007 07/13/2007 Baseline Inspections FY 2007 - POINT BEACH INIT EXAM 07/2007 3 1 W90164 OL - INITIAL EXAM - POINT BEACH - JUN/JUL 2007 07/09/2007 07/20/2007 Not Applicable 7112102 - POST OUTAGE ALARA AND ACCESS CONTROL 1 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 08/20/2007 08/24/2007 Baseline Inspections 1, 2 IP 7112102 ALARA Planning and Controls 08/20/2007 08/24/2007 Baseline Inspections This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 2 of 2 Point Beach 08/30/2006 13:02:47 Inspection / Activity Plan Report 22 09/01/2006 - 03/31/2008 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type 7112102 - POST OUTAGE ALARA AND ACCESS CONTROL 1 1, 2 IP 71151 Performance Indicator Verification 08/20/2007 08/24/2007 Baseline Inspections EP BI - BASELINE EP INSPECTION 1 1, 2 IP 7111402 Alert and Notification System Testing 11/05/2007 11/09/2007 Baseline Inspections 1, 2 IP 7111403 Emergency Response Organization Augmentation Testing 11/05/2007 11/09/2007 Baseline Inspections 1, 2 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 11/05/2007 11/09/2007 Baseline Inspections 1, 2 IP 71151-EP01 Drill/Exercise Performance 11/05/2007 11/09/2007 Baseline Inspections 1, 2 IP 71151-EP02 ERO Drill Participation 11/05/2007 11/09/2007 Baseline Inspections 1, 2 IP 71151-EP03 Alert & Notification System 11/05/2007 11/09/2007 Baseline Inspections 7112202 - RADWASTE AND TRANSPORTATION 1 1, 2 IP 7112202 Radioactive Material Processing and Transportation 10/22/2007 10/26/2007 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 10/22/2007 10/26/2007 Baseline Inspections MAINRULE - MAINTENANCE EFFECTIVENESS INSPECTION 2 1, 2 IP 7111112B Maintenance Effectiveness 10/29/2007 11/02/2007 Baseline Inspections 71111.11 - LIC OPERATOR REQUAL PROGRAM EVALUATION 2 1, 2 IP 7111111B Licensed Operator Requalification Program 11/12/2007 11/16/2007 Baseline Inspections MOD5059 - MODIFICATIONS/50.59 INSPECTION 2 1, 2 IP 7111102 Evaluation of Changes, Tests, or Experiments 11/26/2007 12/14/2007 Baseline Inspections 1, 2 IP 7111117B Permanent Plant Modifications 11/26/2007 12/14/2007 Baseline Inspections HEATSINK - HEAT SINK INSOECTION 1 1, 2 IP 7111106 Flood Protection Measures 02/11/2008 02/15/2008 Baseline Inspections This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.