UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 475 ALLENDALE ROAD KING OF PRUSSIA, PENNSYLVANIA 19406-1415 August 31, 2006 Mr. Gene St. Pierre Site Vice President FPL Energy Seabrook, LLC Seabrook Station c/o Mr. James M. Peschel P.O. Box 300 Seabrook, NH 03874
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN - SEABROOK STATION
Dear Mr. St. Pierre:
On August 8, 2006, the NRC staff completed its performance review of Seabrook Nuclear Power Station for the first half of the calendar year 2006 assessment cycle. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results over the previous twelve months. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and enclosed inspection plan do not include physical protection information. A separate letter designated and marked as Exempt from Public Disclosure in accordance with 10 CFR 2.390 will include the physical protection review and resultant inspection plan. Although security assessment letters from Seabrook and other plants are not made public, NRC did issue a press release on July 27, 2006, indicating that the NRC had issued a finding of low-to-moderate significance and a fine for two security-related violations at Seabrook.
Plant performance for the most recent quarter at Seabrook Nuclear Power Station was within the Licensee Response column of the NRCs Action Matrix, based on all non-security inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at your facility.
The enclosed inspection plan details the inspections, less those related to physical protection, scheduled through March 31, 2008. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature.
The inspections in the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle review.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's
2 G. St. Pierre document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at 610-337-5120 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Paul G. Krohn, Chief Reactor Projects Branch 6 Division of Reactor Projects Docket No. 50-443 License No: NPF-86
Enclosure:
Seabrook Nuclear Power Station Inspection/Activity Plan
3 G. St. Pierre cc w/encl:
J. A. Stall, FPL Senior Vice President, Nuclear & CNO M. Warner, Vice President, Nuclear Support Services J. M. Peschel, Manager - Regulatory Programs M. Kiley, Plant General Manager - Seabrook Station J. Dent, Assistant Plant Manager R. S. Kundalkar, FPL Vice President - Nuclear Engineering D. G. Roy, Manager, Nuclear Training - Seabrook Station Office of the Attorney General, Commonwealth of Massachusetts P. McLaughlin, Attorney General, State of New Hampshire P. Brann, Assistant Attorney General, State of Maine M. S. Ross, Attorney, Florida Power & Light Company R. Walker, Director, Radiation Control Program, Dept. of Public Health, Commonwealth of MA Director, Bureau of Emergency Management, Dept. of Safety, State of New Hampshire C. McCombs, Director, MEMA Health Physicist, Office of Community & Public Health, State of New Hampshire Administrator, Bureau of Radiological Health, State of New Hampshire J. Roy, Director of Operations, Massachusetts Municipal Wholesale Electric Company T. Crimmins, Polestar Applied Technology R. Backus, Esquire, Backus, Meyer and Solomon, New Hampshire Town of Exeter Board of Selectmen S. Comley, Executive Director, We the People of the United States R. Shadis, New England Coalition Staff M. Metcalf, Seacoast Anti-Pollution League Institute of Nuclear Power Operations (INPO)
4 G. St. Pierre Distribution w/encl: (VIA E-MAIL)
S. Collins, RA M. Dapas, DRA B. Holian, DRP D. Lew, DRP P. Krohn, DRP G. Barber, DRP G. Dentel, DRP - Senior Resident Inspector S. Nelson, DRP - Resident OA B. Sosa, RI OEDO D. Roberts, NRR V. Nerses, NRR, PM T. Valentine, NRR DRS Director and Deputy Director DRS Branch Chiefs (6)
D. Screnci, PAO Region I Docket Room (with concurrences)
SUNSI Review Complete: ___PGK____ (Reviewer's Initials)
DOCUMENT NAME: G:\\DRP\\BRANCH6\\ROP Assessments\\2006 ROP7 Midcycle\\2006 Midcycle letter for Seabrook.wpd After declaring this document An Official Agency Record it will be released to the Public.
To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE R1/DRP E
R1/DRP E
R1/DRP NAME SBarber/GSB GDentel/PGK for PKrohn/PGK DATE 08/11/2006 08/31/2006 08/31/2006 OFFICIAL RECORD COPY
Seabrook Inspection / Activity Plan 07/01/2006 - 03/31/2008 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 08/31/2006 09:44:55 Report 22 2
TI-169
- MSPI VERIFICATION Safety Issues 09/11/2006 09/15/2006 1
2515/169 IP Mitigating Systems Performance Index Verification 1
7111108P
- INSERVICE INSPECTION Safety Issues 10/02/2006 10/20/2006 1
2515/150 IP Reactor Pressure Vessel Head and Vessel Head Penetration Nozzles (NRC ORDER EA-03-009)
Baseline Inspections 10/02/2006 10/20/2006 1
7111108P IP Inservice Inspection Activities - PWR 1
7112102
- OCC RAD SAFETY - ALARA Baseline Inspections 10/23/2006 10/27/2006 1
7112102 IP ALARA Planning and Controls 4
- PI&R Baseline Inspections 11/27/2006 12/01/2006 1
71152B IP Identification and Resolution of Problems Baseline Inspections 12/04/2006 12/08/2006 1
71152B IP Identification and Resolution of Problems 1
7112101
- OCC RAD SAFETY Baseline Inspections 01/29/2007 02/02/2007 1
7112101 IP Access Control to Radiologically Significant Areas 6
7111121
- CDBI (COMPONENT DESIGN BASES INSPECTION)
Baseline Inspections 03/19/2007 03/23/2007 1
7111121 IP Component Design Bases Inspection Baseline Inspections 04/02/2007 04/06/2007 1
7111121 IP Component Design Bases Inspection Baseline Inspections 04/16/2007 04/20/2007 1
7111121 IP Component Design Bases Inspection Baseline Inspections 04/23/2007 04/27/2007 1
7111121 IP Component Design Bases Inspection 1
7112201
- PUB RAD SAFETY - RETS Baseline Inspections 04/09/2007 04/13/2007 1
7112201 IP Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 2
7111107
- HEAT SINK INSP Baseline Inspections 05/14/2007 05/18/2007 1
7111107B IP Heat Sink Performance 4
7/09+EXM
- LICENSED OPERATOR INITIAL EXAMS Not Applicable 06/11/2007 06/15/2007 1
U01666 FY07-SEABROOK INITIAL OPERATOR EXAM Not Applicable 07/09/2007 07/13/2007 1
U01666 FY07-SEABROOK INITIAL OPERATOR EXAM 1
71114
- EP PRGM INSP Baseline Inspections 08/27/2007 08/31/2007 1
7111402 IP Alert and Notification System Testing Baseline Inspections 08/27/2007 08/31/2007 1
7111403 IP Emergency Response Organization Augmentation Testing Baseline Inspections 08/27/2007 08/31/2007 1
7111404 IP Emergency Action Level and Emergency Plan Changes Baseline Inspections 08/27/2007 08/31/2007 1
7111405 IP Correction of Emergency Preparedness Weaknesses and Deficiencies Baseline Inspections 08/27/2007 08/31/2007 1
71151-EP01 IP Drill/Exercise Performance Baseline Inspections 08/27/2007 08/31/2007 1
71151-EP02 IP ERO Drill Participation Baseline Inspections 08/27/2007 08/31/2007 1
71151-EP03 IP Alert & Notification System 3
7111111B
- L.O. REQUAL. PROG. + P/F REVIEW Baseline Inspections 11/26/2007 11/30/2007 1
7111111B IP Licensed Operator Requalification Program Baseline Inspections 12/03/2007 12/07/2007 1
7111111B IP Licensed Operator Requalification Program This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Seabrook Inspection / Activity Plan 07/01/2006 - 03/31/2008 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 08/31/2006 09:44:55 Report 22 1
7112203
- PUB RAD SAFETY - REMP Baseline Inspections 09/03/2007 09/07/2007 1
7112203 IP Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control Program 1
7112102
- OCC RAD SAFETY - ALARA Baseline Inspections 12/03/2007 12/07/2007 1
7112102 IP ALARA Planning and Controls 1
7112103
- OCC RAD SAFETY - INSTRUMENTS Baseline Inspections 12/17/2007 12/21/2007 1
7112103 IP Radiation Monitoring Instrumentation and Protective Equipment 1
7112101
- OCC RAD SAFETY - ACCESS Baseline Inspections 01/28/2008 02/01/2008 1
7112101 IP Access Control to Radiologically Significant Areas 4
MODS
- MODS AND 50.59 Baseline Inspections 02/04/2008 02/08/2008 1
7111102 IP Evaluation of Changes, Tests, or Experiments Baseline Inspections 02/04/2008 02/08/2008 1
7111117B IP Permanent Plant Modifications This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.