August 31, 2006 Florida Power and Light Company ATTN: Mr. J. A. Stall, Senior Vice President Nuclear and Chief Nuclear Officer P. O. Box 14000 Juno Beach, FL 33408-0420
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN - ST. LUCIE NUCLEAR PLANT
Dear Mr. Scarola:
On August 2, 2006, the NRC staff completed its performance review of the St. Lucie Nuclear Power Plant for the first half of the calendar year 2006 assessment cycle. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results over the previous twelve months. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and the enclosed inspection plan do not include physical protection information. A separate letter designated and marked as Exempt from Public Disclosure in Accordance with 10 CFR 2.390 will include the physical protection review and a resultant inspection plan.
Overall, both St. Lucie Units operated in a manner that preserved public health and safety and fully met all cornerstone objectives. Plant performance for St. Lucie Units 1 and 2 for the most recent quarter was in the Licensee Response Column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at your facility. In addition to the ROP baseline inspections, we plan to conduct non-baseline inspections involving containment sump blockage, verification of Mitigating Systems Performance Index, and Independent Spent Fuel Storage Installation.
The enclosed inspection plan details the inspections, less those related to physical protection, scheduled through March 31, 2008. The inspection plan is provided to minimize the resource impact on your staff and to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last twelve months of the inspection plan are tentative and may be revised at the end-of-cycle review meeting.
FP&L 2 In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at (404) 562-4560 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Joel T. Munday, Chief Reactor Projects Branch 3 Division of Reactor Projects Docket Nos.: 50-335, 50-389, 72-61 License Nos.: DPR-67, NPF-16
Enclosure:
St. Lucie Inspection/Activity Plan cc w/encl: (See page 3)
FP&L 3 cc w/encl:
William E. Webster William A. Passetti Vice President, Nuclear Operations Bureau of Radiation Control Florida Power & Light Company Department of Health Electronic Mail Distribution Electronic Mail Distribution Gordon L. Johnston Craig Fugate, Director Acting Vice President Division of Emergency Preparedness St. Lucie Nuclear Plant Department of Community Affairs Florida Power & Light Company Electronic Mail Distribution Electronic Mail Distribution J. Kammel Christopher R. Costanzo Radiological Emergency Acting Plant General Manager Planning Administrator St. Lucie Nuclear Plant Department of Public Safety Electronic Mail Distribution Electronic Mail Distribution Bill Parks Douglas Anderson Acting Operations Manager County Administrator St. Lucie Nuclear Plant St. Lucie County Electronic Mail Distribution 2300 Virginia Avenue Ft. Pierce, FL 34982 Terry L. Patterson Licensing Manager St. Lucie Nuclear Plant Electronic Mail Distribution Mark Warner, Vice President Nuclear Operations Support Florida Power & Light Company Electronic Mail Distribution Rajiv S. Kundalkar Vice President - Nuclear Engineering Florida Power & Light Company Electronic Mail Distribution M. S. Ross, Managing Attorney Florida Power & Light Company Electronic Mail Distribution Marjan Mashhadi, Senior Attorney Florida Power & Light Company Electronic Mail Distribution
Page 1 of 3 Saint Lucie 08/30/2006 15:18:22 Inspection / Activity Plan Report 22 09/01/2006 - 03/31/2008 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type 2515/169 - TI 2515/169 - MSPI VERIFICATION 1 1, 2 IP 2515/169 Mitigating Systems Performance Index Verification 08/01/2006 12/31/2006 Safety Issues EB2-TFP - TRIENNIAL FP PRE-INSPECTION VISIT 5 1, 2 IP 7111105T Fire Protection [Triennial] 09/05/2006 09/07/2006 Baseline Inspections EB2-TFP - TRIENNIAL FIRE PROTECTION INSPECTION 4 1, 2 IP 7111105T Fire Protection [Triennial] 10/02/2006 10/06/2006 Baseline Inspections 1, 2 IP 7111105T Fire Protection [Triennial] 10/16/2006 10/20/2006 Baseline Inspections PSB1-RP - RP PUBLIC PRE-INSP VISIT 1 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 10/09/2006 10/11/2006 Baseline Inspections PSB1-RP - RP PUBLIC BASELINE INSP 4 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 10/30/2006 11/03/2006 Baseline Inspections 1, 2 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 10/30/2006 11/03/2006 Baseline Inspections 1, 2 IP 7112201 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 10/30/2006 11/03/2006 Baseline Inspections 1, 2 IP 7112203 Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control P 10/30/2006 11/03/2006 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 10/30/2006 11/03/2006 Baseline Inspections EB3-HS - HEAT SINK 2 1, 2 IP 7111107B Heat Sink Performance 01/08/2007 01/12/2007 Baseline Inspections PS2-EP - EP INSP 1 1, 2 IP 7111402 Alert and Notification System Testing 02/05/2007 02/09/2007 Baseline Inspections 1, 2 IP 7111403 Emergency Response Organization Augmentation Testing 02/05/2007 02/09/2007 Baseline Inspections 1, 2 IP 7111404 Emergency Action Level and Emergency Plan Changes 02/05/2007 02/09/2007 Baseline Inspections 1, 2 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 02/05/2007 02/09/2007 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 02/05/2007 02/09/2007 Baseline Inspections EB1-MODS - MODIFICATIONS/10CFR50.59 4 1, 2 IP 7111102 Evaluation of Changes, Tests, or Experiments 02/26/2007 03/02/2007 Baseline Inspections 1, 2 IP 7111117B Permanent Plant Modifications 02/26/2007 03/02/2007 Baseline Inspections PSB1-RP - RP OCCUPATIONAL BASELINE INSPECTION 1 1 IP 7112101 Access Control to Radiologically Significant Areas 04/02/2007 04/06/2007 Baseline Inspections EB3-ISI - U1 INSERVICE INSPECTION 1 1 IP 7111108P Inservice Inspection Activities - PWR 04/09/2007 04/13/2007 Baseline Inspections EB3SGISI - U1 STEAM GENERATOR ISI 1 1 IP 7111108P Inservice Inspection Activities - PWR 04/16/2007 04/20/2007 Baseline Inspections EB1-SUMP - PWR CONTAINMENT SUMP BLOCKAGE TI (U-1) 1 1 IP 93812 Special Inspection 04/22/2007 04/27/2007 Event Response Insp This report does not include INPO and OUTAGE activities. Enclosure This report shows only on-site and announced inspection procedures.
Page 2 of 3 Saint Lucie 08/30/2006 15:18:22 Inspection / Activity Plan Report 22 09/01/2006 - 03/31/2008 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type 60854 - ISFSI CONSTRUCTION 1 1 IP 60854 Preoperational Testing Of An ISFSI 07/09/2007 07/13/2007 Other Routine EB1-CDB - COMPONENT DESIGN BASES INSPECTION 6 1, 2 IP 7111121 Component Design Bases Inspection 09/17/2007 09/21/2007 Baseline Inspections 1, 2 IP 7111121 Component Design Bases Inspection 10/01/2007 10/05/2007 Baseline Inspections 1, 2 IP 7111121 Component Design Bases Inspection 10/15/2007 10/19/2007 Baseline Inspections 1, 2 IP 7111121 Component Design Bases Inspection 10/29/2007 11/02/2007 Baseline Inspections PSB1-RP - RP OCCUPATIONAL PRE-INSP VISIT 1 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 10/09/2007 10/11/2007 Baseline Inspections EB3-ISI - U2 INSERVICE INSPECTION 1 2 IP 7111108P Inservice Inspection Activities - PWR 10/22/2007 10/26/2007 Baseline Inspections OL RQ - LICENSED OPERATOR REQUAL INSPECTION 4 1, 2 IP 7111111B Licensed Operator Requalification Program 10/22/2007 10/26/2007 Baseline Inspections EB3SGRP - STEAM GENERATOR REPLACEMENT 7 2 IP 50001 Steam Generator Replacement Inspection 10/29/2007 11/02/2007 Other Routine 2 IP 50001 Steam Generator Replacement Inspection 11/26/2007 11/30/2007 Other Routine 2 IP 50001 Steam Generator Replacement Inspection 12/17/2007 12/21/2007 Other Routine EB3HEAD - REACTOR HEAD REPLACEMENT 2 2 IP 71007 Reactor Vessel Head Replacement Inspection 11/05/2007 11/09/2007 Other Routine PSB1-RP - RP OCCUPATIONAL BASLINE INSP WK 1 2 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 11/05/2007 11/09/2007 Baseline Inspections 1, 2 IP 7112102 ALARA Planning and Controls 11/05/2007 11/09/2007 Baseline Inspections 1, 2 IP 7112202 Radioactive Material Processing and Transportation 11/05/2007 11/09/2007 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 11/05/2007 11/09/2007 Baseline Inspections PSB1-RP - RP OCCUPATIONAL BASELINE INSP WK 2 2 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 11/26/2007 11/30/2007 Baseline Inspections 1, 2 IP 7112102 ALARA Planning and Controls 11/26/2007 11/30/2007 Baseline Inspections 1, 2 IP 7112202 Radioactive Material Processing and Transportation 11/26/2007 11/30/2007 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 11/26/2007 11/30/2007 Baseline Inspections EB1-SUMP - PWR CONTAINMENT SUMP BLOCKAGE TI (U-2) 1 2 IP 93812 Special Inspection 12/16/2007 12/21/2007 Event Response Insp PS2-EP - EP EXERCISE 2 1, 2 IP 7111401 Exercise Evaluation 02/18/2008 02/22/2008 Baseline Inspections 1, 2 IP 7111404 Emergency Action Level and Emergency Plan Changes 02/18/2008 02/22/2008 Baseline Inspections 1, 2 IP 71151-EP01 Drill/Exercise Performance 02/18/2008 02/22/2008 Baseline Inspections This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 3 of 3 Saint Lucie 08/30/2006 15:18:22 Inspection / Activity Plan Report 22 09/01/2006 - 03/31/2008 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type PS2-EP - EP EXERCISE 2 1, 2 IP 71151-EP02 ERO Drill Participation 02/18/2008 02/22/2008 Baseline Inspections 1, 2 IP 71151-EP03 Alert & Notification System 02/18/2008 02/22/2008 Baseline Inspections This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.