ML062430350
ML062430350 | |
Person / Time | |
---|---|
Site: | Watts Bar |
Issue date: | 08/30/2006 |
From: | Reactor Projects Region 2 Branch 6 |
To: | |
Shared Package | |
ML062430343 | List: |
References | |
Download: ML062430350 (3) | |
Text
Page 1 of 3 Watts Bar 08/30/2006 12:36:21 Inspection / Activity Plan Report 22 09/01/2006 - 03/31/2008 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type 2515/169 - TI 2515/169 - MSPI VERIFICATION 1 1 IP 2515/169 Mitigating Systems Performance Index Verification 08/01/2006 12/31/2006 Safety Issues PS2-EP - EP INSP 1 1 IP 7111402 Alert and Notification System Testing 09/04/2006 09/08/2006 Baseline Inspections 1 IP 7111403 Emergency Response Organization Augmentation Testing 09/04/2006 09/08/2006 Baseline Inspections 1 IP 7111404 Emergency Action Level and Emergency Plan Changes 09/04/2006 09/08/2006 Baseline Inspections 1 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 09/04/2006 09/09/2006 Baseline Inspections 1 IP 71151 Performance Indicator Verification 09/04/2006 09/09/2006 Baseline Inspections OL EXAM - INITIAL EXAM 3 1 V23241 WATTS BAR/SEPTEMBER 2006 EXAM AT POWER FACILITIES 09/05/2006 09/15/2006 Not Applicable EB3-SGRP - SG REPLACEMENT 1 1 IP 50001 Steam Generator Replacement Inspection 09/08/2006 09/08/2006 Other Routine RP BR6 - UNIT 2 SYSTEMS LAY-UP INSPECTION 1 1 IP 92050 Review Of Quality Assurance For Extended Construction Delays 09/25/2006 09/29/2006 Other Routine EB3-ISI - U1 INSERVICE INSPECTION 1 1 IP 7111108P Inservice Inspection Activities - PWR 10/02/2006 10/06/2006 Baseline Inspections EB3SGRP - SG REPLACEMENT 3 1 IP 50001 Steam Generator Replacement Inspection 10/02/2006 10/06/2006 Other Routine PSB1-RP - RP BASELINE OCCUPATIONAL & S/G REPL-WK1 2 1 IP 50001 Steam Generator Replacement Inspection 10/02/2006 10/06/2006 Other Routine 1 IP 7112101 Access Control to Radiologically Significant Areas 10/02/2006 10/06/2006 Baseline Inspections 1 IP 7112102 ALARA Planning and Controls 10/02/2006 10/06/2006 Baseline Inspections 1 IP 71151 Performance Indicator Verification 10/02/2006 10/06/2006 Baseline Inspections EB3-SGRP - SG REPLACEMENT 2 1 IP 50001 Steam Generator Replacement Inspection 10/16/2006 10/20/2006 Other Routine PSB1-RP - RP BASELINE OCCUPATIONAL & S/G REPL WK2 1 1 IP 50001 Steam Generator Replacement Inspection 10/16/2006 10/20/2006 Other Routine 1 IP 7112101 Access Control to Radiologically Significant Areas 10/16/2006 10/20/2006 Baseline Inspections EB3-SGRP - SG REPLACEMENT 2 1 IP 50001 Steam Generator Replacement Inspection 10/30/2006 11/03/2006 Other Routine EB1-SUMP - PWR CONTAINMENT SUMP BLOCKAGE TI (U-1) 2 1 IP 2515/166 Pressurized Water Reactor Containment Sump Blockage [NRC GENERIC LETTER 2004-02] 11/05/2006 11/11/2006 Safety Issues EB1-CDB - COMPONENT DESIGN BASES INSPECTION 5 1 IP 7111121 Component Design Bases Inspection 01/29/2007 02/02/2007 Baseline Inspections 1 IP 7111121 Component Design Bases Inspection 02/12/2007 02/16/2007 Baseline Inspections This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Enclosure
Page 2 of 3 Watts Bar 08/30/2006 12:36:21 Inspection / Activity Plan Report 22 09/01/2006 - 03/31/2008 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type EB1-CDB - COMPONENT DESIGN BASES INSPECTION 5 1 IP 7111121 Component Design Bases Inspection 02/26/2007 03/02/2007 Baseline Inspections 1 IP 7111121 Component Design Bases Inspection 03/12/2007 03/16/2007 Baseline Inspections PSB1-RP - RP PRE-INSPECTION VISIT 1 1 IP 7112101 Access Control to Radiologically Significant Areas 04/30/2007 05/04/2007 Baseline Inspections TFP - TFP INFO TRIP 5 1 IP 7111105T Fire Protection [Triennial] 05/08/2007 05/10/2007 Baseline Inspections PSB1-RP - RP OCCUPATIONAL BASELINE INSPECTION 3 1 IP 7112101 Access Control to Radiologically Significant Areas 05/21/2007 05/25/2007 Baseline Inspections 1 IP 7112102 ALARA Planning and Controls 05/21/2007 05/25/2007 Baseline Inspections 1 IP 7112202 Radioactive Material Processing and Transportation 05/21/2007 05/25/2007 Baseline Inspections 1 IP 71151 Performance Indicator Verification 05/21/2007 05/25/2007 Baseline Inspections TFP - TRIENNIAL FIRE PROTECTION INSPECTION 5 1 IP 7111105T Fire Protection [Triennial] 05/28/2007 06/01/2007 Baseline Inspections 1 IP 7111105T Fire Protection [Triennial] 06/11/2007 06/15/2007 Baseline Inspections EB3-HS - HEAT SINK 2 1 IP 7111107B Heat Sink Performance 06/25/2007 06/29/2007 Baseline Inspections RPB6-PIR - BIENNIAL PI&R INSPECTION 4 1 IP 71152B Identification and Resolution of Problems 08/27/2007 08/31/2007 Baseline Inspections 1 IP 71152B Identification and Resolution of Problems 09/10/2007 09/14/2007 Baseline Inspections EB1-MODS - MODIFICATIONS-10CFR50.59 3 1 IP 7111102 Evaluation of Changes, Tests, or Experiments 10/29/2007 11/02/2007 Baseline Inspections 1 IP 7111117B Permanent Plant Modifications 10/29/2007 11/02/2007 Baseline Inspections PS2-EP - EP EXERCISE 2 1 IP 7111401 Exercise Evaluation 11/05/2007 11/09/2007 Baseline Inspections 1 IP 7111404 Emergency Action Level and Emergency Plan Changes 11/05/2007 11/09/2007 Baseline Inspections 1 IP 71151 Performance Indicator Verification 11/05/2007 11/09/2007 Baseline Inspections EB3-MR - MR EFFECTIVENESS 1 1 IP 7111112B Maintenance Effectiveness 12/10/2007 12/14/2007 Baseline Inspections OL PREP - INITIAL EXAM PREP 3 1 V23277 WATTS BAR/JANUARY 2008 EXAM AT POWER FACILITIES 01/07/2008 01/11/2008 Not Applicable OL EXAM - INITIAL EXAM 2 1 V23277 WATTS BAR/JANUARY 2008 EXAM AT POWER FACILITIES 01/28/2008 02/08/2008 Not Applicable EB3-ISI - UNIT 1 - ISI 1 1 IP 7111108P Inservice Inspection Activities - PWR 02/18/2008 02/22/2008 Baseline Inspections This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 3 of 3 Watts Bar 08/30/2006 12:36:21 Inspection / Activity Plan Report 22 09/01/2006 - 03/31/2008 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type EB3RPV - REACTOR HEAD PENETRATIONS TI150 1 1 IP 2515/150 Reactor Pressure Vessel Head and Vessel Head Penetration Nozzles (NRC ORDER EA 02/18/2008 02/22/2008 Safety Issues This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.