August 31, 2006 Mr. Christopher M. Crane President and Chief Nuclear Officer Exelon Nuclear Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -
LASALLE COUNTY STATION, UNITS 1 AND 2
Dear Mr. Crane:
On August 7, 2006, the NRC staff completed its performance review of the LaSalle County Station, Units 1 and 2 for the first half of the calender year 2006 assessment cycle. Our technical staff reviewed the performance indicators (PIs) for the most recent quarter and inspection results over the previous 12 months. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and enclosed inspection plan do not include physical protection information. A separate letter designated and marked as Exempt from Public Disclosure in Accordance with 10 CFR 2.390 will include the physical protection review and resultant inspection plan.
Plant performance for the most recent quarter at the LaSalle County Station, Units 1 and 2 was within the Licensee Response column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at your facility.
The enclosed inspection plan details the inspections, less those related to physical protection scheduled through March 31, 2008. Significant inspections planned include a Component Design Basis Inspection in August 2007, and a Problem Identification and Resolution Inspection (PI&R) in November 2007. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite.
Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last 9 months of the inspection plan are tentative and may be revised at the end-of-cycle review.
C. Crane In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at (630) 829-9629 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Bruce Burgess, Chief Reactor Projects Branch 2 Division of Reactor Projects Docket Nos. 50-373; 50-374 License Nos. NPF-11; NPF-18
Enclosure:
LaSalle Inspection/Activity Plan DISTRIBUTION:
See next page
C. Crane In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at (630) 829-9629 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Bruce Burgess, Chief Reactor Projects Branch 2 Division of Reactor Projects Docket Nos. 50-373; 50-374 License Nos. NPF-11; NPF-18
Enclosure:
LaSalle Inspection/Activity Plan DISTRIBUTION:
See next page DOCUMENT NAME:G:\\Branch TSS\\ALL MOC\\midcycle 2005 to 2006\\lasalle\\LaSalle 2006 MOC Letter.wpd X Publicly Available G Non-Publicly Available G Sensitive X Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII RIII NAME SSheldon:sls BBurgess DATE 08/30/2006 08/30/2006 OFFICIAL RECORD COPY
C. Crane cc w/encl:
Site Vice President - LaSalle County Station LaSalle County Station Plant Manager Regulatory Assurance Manager - LaSalle County Station Chief Operating Officer Senior Vice President - Nuclear Services Senior Vice President - Mid-West Regional Operating Group Vice President - Mid-West Operations Support Vice President - Licensing and Regulatory Affairs Director Licensing - Mid-West Regional Operating Group Manager Licensing - Clinton and LaSalle Senior Counsel, Nuclear, Mid-West Regional Operating Group Document Control Desk - Licensing Assistant Attorney General Illinois Emergency Management Agency State Liaison Officer Chairman, Illinois Commerce Commission Grundy County Board Chairman Mayor of Ottawa Mayor of Streator City Manager of Streator Director, Grundy County Emergency Management Agency Mayor of Seneca Mayor of Grand Ridge Mayor of Ransom Sheriff, LaSalle County LaSalle County Board Chairman Director, LaSalle County Emergency Management Agency Mayor of Marseilles Mayor of Verona Mayor of Kinsman INPO
C. Crane ADAMS Distribution:
TEB DXC1 DMS6 RidsNrrDirsIrib GEG KGO DEK CAA1 LSL (electronic IRs only)
C. Pederson, DRS (hard copy - IRs only)
DRPIII DRSIII PLB1 TXN ROPreports@nrc.gov (inspection reports, final SDP letters, any letter with an IR number)
LaSalle Inspection / Activity Plan 09/01/2006 - 03/31/2008 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 08/30/2006 13:01:04 Report 22 3
HS
- HEAT SINK INSPECTION Baseline Inspections 08/28/2006 09/01/2006 1, 2 7111107B IP Heat Sink Performance 1
BI
- RAD INSTRUMENTATION Baseline Inspections 09/25/2006 09/29/2006 1, 2 7112103 IP Radiation Monitoring Instrumentation and Protective Equipment 3
FY 2007
- LASALLE INIT PREP 10/2006 Not Applicable 10/23/2006 10/27/2006 1
W90146 OL - INITIAL EXAM - LASALLE - OCT/NOV 2006 3
- EP EXERCISE BASELINE Baseline Inspections 11/13/2006 11/17/2006 1, 2 7111401 IP Exercise Evaluation Baseline Inspections 11/13/2006 11/17/2006 1, 2 71151 IP Performance Indicator Verification 3
FY 2007
- LASALLE INIT EXAM 11/2006 Not Applicable 11/13/2006 11/21/2006 1
W90146 OL - INITIAL EXAM - LASALLE - OCT/NOV 2006 1
- TRANSPORTATION Baseline Inspections 01/22/2007 01/26/2007 1, 2 7112202 IP Radioactive Material Processing and Transportation 1
- ISI BASELINE INSPECTION Baseline Inspections 03/05/2007 03/09/2007 2
7111108G IP Inservice Inspection Activities - BWR 1
BI
- OUTAGE ACCESS CONTROL AND ALARA Baseline Inspections 03/12/2007 03/16/2007 1
7112101 IP Access Control to Radiologically Significant Areas Baseline Inspections 03/12/2007 03/16/2007 1
7112102 IP ALARA Planning and Controls 1
MOD5059
- MODIFICATIONS/50.59 INSPECTION Baseline Inspections 04/30/2007 05/18/2007 1, 2 7111102 IP Evaluation of Changes, Tests, or Experiments Baseline Inspections 04/30/2007 05/18/2007 1, 2 7111117B IP Permanent Plant Modifications 1
BI
- GAS AND LIQUID EFFLUENTS Baseline Inspections 05/21/2007 05/25/2007 1, 2 7112201 IP Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 1
EP BI
- BASELINE EP INSPECTION Baseline Inspections 07/23/2007 07/27/2007 1, 2 7111402 IP Alert and Notification System Testing Baseline Inspections 07/23/2007 07/27/2007 1, 2 7111403 IP Emergency Response Organization Augmentation Testing Baseline Inspections 07/23/2007 07/27/2007 1, 2 7111405 IP Correction of Emergency Preparedness Weaknesses and Deficiencies Baseline Inspections 07/23/2007 07/27/2007 1, 2 71151-EP01 IP Drill/Exercise Performance Baseline Inspections 07/23/2007 07/27/2007 1, 2 71151-EP02 IP ERO Drill Participation Baseline Inspections 07/23/2007 07/27/2007 1, 2 71151-EP03 IP Alert & Notification System 1
BI
- REMP Baseline Inspections 07/09/2007 07/13/2007 1, 2 7112203 IP Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control P 5
- COMPONENT DESIGN BASES INSPECTION Baseline Inspections 08/27/2007 09/28/2007 1, 2 7111121 IP Component Design Bases Inspection This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
LaSalle Inspection / Activity Plan 09/01/2006 - 03/31/2008 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 08/30/2006 13:01:04 Report 22 2
- LIC OPERATOR REQUAL PROGRAM EVALUATION Baseline Inspections 11/05/2007 11/09/2007 1, 2 7111111B IP Licensed Operator Requalification Program 3
- PI&R BIENNIAL INSPECTION Baseline Inspections 11/26/2007 12/14/2007 1, 2 71152B IP Identification and Resolution of Problems 1
- ISI INSPECTION Baseline Inspections 02/12/2008 02/27/2008 1
7111108G IP Inservice Inspection Activities - BWR 1
BI
- OUTAGE ACCESS CONTROL AND ALARA Baseline Inspections 02/18/2008 02/22/2008 1
7112101 IP Access Control to Radiologically Significant Areas Baseline Inspections 02/18/2008 02/22/2008 1
7112102 IP ALARA Planning and Controls This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.