August 23, 2006 Mr. Eugene S. Grecheck Vice President - Nuclear Support Services Dominion Nuclear Connecticut, Inc.

Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711

SUBJECT:

MILLSTONE POWER STATION, UNIT NO. 3 - REQUEST FOR ADDITIONAL INFORMATION RELATED TO RELIEF REQUEST TO USE AN ALTERNATIVE BRAZED JOINT METHODOLOGY (TAC NO. MC8893)

Dear Mr. Grecheck:

By letter dated June 9, 2005, Dominion Nuclear Connecticut, Inc. requested approval for the use of an alternative brazed joint assessment methodology. The approval of the request would provide the structural integrity analysis and acceptance criteria needed for resolution of nonconforming conditions on American Society of Mechanical Engineers Boiler and Pressure Vessel Code Class 3, moderate energy system piping with brazed joints as part of the Millstone Power Station, Unit No. 3, inservice inspection program.

The Nuclear Regulatory Commission staff has determined that a response to the request for additional information is necessary in order for the staff to complete its review. These questions, in draft form, were sent by fax to Mr. Paul Willoughby of your staff on March 24, 2006. A conference call with your staff was held to discuss the questions on May 11, 2006, in which a common understanding of the questions was reached.

In order to complete our timely review of your relief request, we require your response within 30 days from the date of this letter. Please note that if you do not respond to this letter within 30 days, we may reject your application under the provisions of Title 10 of the Code of Federal Regulations, Section 2.108(b). If you have any questions, I can be reached at (301) 415-1484.

Sincerely,

/RA by G. Ed Miller for/

Victor Nerses, Senior Project Manager Plant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-423 cc w/encl: See next page

August 23, 2006 Mr. Eugene S. Grecheck Vice President - Nuclear Support Services Dominion Nuclear Connecticut, Inc.

Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711

SUBJECT:

MILLSTONE POWER STATION, UNIT NO. 3 - REQUEST FOR ADDITIONAL INFORMATION RELATED TO RELIEF REQUEST TO USE AN ALTERNATIVE BRAZED JOINT METHODOLOGY (TAC NO. MC8893)

Dear Mr. Grecheck:

By letter dated June 9, 2005, Dominion Nuclear Connecticut, Inc. requested approval for the use of an alternative brazed joint assessment methodology. The approval of the request would provide the structural integrity analysis and acceptance criteria needed for resolution of nonconforming conditions on American Society of Mechanical Engineers Boiler and Pressure Vessel Code Class 3, moderate energy system piping with brazed joints as part of the Millstone Power Station, Unit No. 3, inservice inspection program.

The Nuclear Regulatory Commission staff has determined that a response to the request for additional information is necessary in order for the staff to complete its review. These questions, in draft form, were sent by fax to Mr. Paul Willoughby of your staff on March 24, 2006. A conference call with your staff was held to discuss the questions on May 11, 2006, in which a common understanding of the questions was reached.

In order to complete our timely review of your relief request, we require your response within 30 days from the date of this letter. Please note that if you do not respond to this letter within 30 days, we may reject your application under the provisions of Title 10 of the Code of Federal Regulations, Section 2.108(b). If you have any questions, I can be reached at (301) 415-1484.

Sincerely,

/RA by G. Ed Miller for/

Victor Nerses, Senior Project Manager Plant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-423 cc w/encl: See next page DISTRIBUTION:

PUBLIC LPL1-2 R/F RidsNrrDorlLpl1-2 RidsNrrLACRaynor RidsNrrDlpmDpr RidsNrrPMVNerses RidsOgcRp RidsAcrsAcnwMailCenter RidsRgnIMailCenter RidsNrrDeEeeb ADAMS Accession Number: ML062300005 OFFICE LPL1-2/PM LPL1-2/LA LPL1-2/BC (A)

NAME VNerses:rsa CRaynor BPoole (GMiller for)

DATE 8/23/06 8/23/06 8/23/06 OFFICIAL RECORD COPY

Millstone Power Station, Unit No. 3 cc:

Lillilan M. Cuoco, Esquire Mr. Joseph Roy, Senior Counsel Director of Operations Dominion Resources Services, Inc. Massachusetts Municipal Wholesale Building 475, 5th Floor Electric Company Rope Ferry Road Moody Street Waterford, CT 06385 P.O. Box 426 Ludlow, MA 01056 Edward L. Wilds, Jr., Ph.D.

Director, Division of Radiation Mr. J. Alan Price Department of Environmental Protection Site Vice President 79 Elm Street Dominion Nuclear Connecticut, Inc.

Hartford, CT 06106-5127 Building 475, 5th Floor Rope Ferry Road Regional Administrator, Region I Waterford, CT 06385 U.S. Nuclear Regulatory Commission 475 Allendale Road Mr. Chris Funderburk King of Prussia, PA 19406 Director, Nuclear Licensing and Operations Support First Selectmen Dominion Resources Services, Inc.

Town of Waterford 5000 Dominion Boulevard 15 Rope Ferry Road Glen Allen, VA 23060-6711 Waterford, CT 06385 Mr. David W. Dodson Mr. J. W. "Bill" Sheehan Licensing Supervisor Co-Chair NEAC Dominion Nuclear Connecticut, Inc.

19 Laurel Crest Drive Building 475, 5th Floor Waterford, CT 06385 Rope Ferry Road Waterford, CT 06385 Mr. Evan W. Woollacott Co-Chair Nuclear Energy Advisory Council 128 Terry's Plain Road Simsbury, CT 06070 Senior Resident Inspector Millstone Power Station c/o U.S. Nuclear Regulatory Commission P. O. Box 513 Niantic, CT 06357 Ms. Nancy Burton 147 Cross Highway Redding Ridge, CT 00870