E-mail from Meyer to Bixler, Salem Slides for Chairman Diaz
ML062210197
Person / Time
Site: Salem, Hope Creek  PSEG icon.png
Issue date: 02/05/2004
From: Meyer G
NRC Region 1
To: Cyndy Bixler
NRC Region 1
References
FOIA/PA-2005-0194
Download: ML062210197 (2)


Text

j Genni~Iyer-alem slides oChrmnDa ri n-1-m e-y-e iammn-mr-I From:

To:

Date:

Subject:

Glenn Meyer Cynthia Bixler 2/5/04 3:00PM Salem slides for Chairman Diaz Cyndy - The attached file (G:Br.3\\assessment\\Diaz slides) provides the slides for discussion of Salem Issues. Randy's comments were included.

CC:

A. Randolph Blough; Brian Holian; Cynthia O'Daniell; Scott Barber Information in this record was deleted in accordance With the Freedom ot informaatio Act, exemptions.-

FOIA.

,,o..r -p

Salem & Hope Creek I1.

Numerous cases of poor corrective action within past 18 months.

2.

Salem & Hope Creek frequently challenged by plant events. Could be most difficult, highly reactive site to manage; 3 units, 2 designs Hope Creek manual scram - MSIVs closing on January 12 Hope Creek shutdown - RWCU leak on December 5 Salem 2 manual trip - dropped rods on November 23 Salem 1 shutdown -jammed feed reg valve on October 15 Hope Creek manual scram - EHC leak on #4 CIV on October 3 Hope Creek auto scram - switchyard salting on September 19 Salem I & 2 shutdown - switchyard salting on September 19 Salem I auto trip - Load reject and partial LOOP on July 29 Combined with a refueling outage every 6 months, new site management, and an organizational realignment, management has been severely stressed and progress has been very limited.

2.

Ongoing special review of Work Environment Tailored approach guided by senior Region I management Extensive NRC review of allegations (40+ interviews)

January 28e letter requested PSEG self-assessment PSEG plan to be submitted in late February

3.

Regulatory oversight continues to focus on Salem & Hope Creek End of Cycle Review of 2003 completed on Wednesday Substantive cross-cutting issue - Problem Identification and Resolution (PI&R) - continued for 31 time (1 Y4year period) 0