E-Mail from Meyer to Holden and Jolicoeur, Salem/Hc Work Environment Letter
ML062210123
Person / Time
Site: Salem, Hope Creek  
(DPR-070, NPF-057)
Issue date: 01/26/2004
From: Meyer G
NRC Region 1
To: Holden C, John Jolicoeur
NRC/IRO
References
FOIA/PA-2005-0194
Download: ML062210123 (3)


Text

4ohnJ.Lcoeun-Fwd: Salem/HC Work Environment Letter From:

To:

Date:

Subject:

Glenn Meyer r -

Cornelius Holden; John Jolicoeur Mon, Jan 26, 2004 12:57 PM Fwd: Salem/HC Work Environment Letter Letter to PSEG on work environment as discussed previously. This version has regional concurrence and is ready for headquarters agreement.

CC:

A. Randolph Blough; Tad Marsh X-<

nformatuon in this record was deleted n crlance Wsth the-freedom of l.b tg Acts exemptions :5-FOIA-__------_

joiin jýQ!iceu"r-Rev. 7 of Salem/HC Wo-rk Environment Letter Pia eie 1]

. v

.1 From:

To:

Date:

Subject:

David Vito e-',-*

SALEMHCSCWE Mon, Jan 26, 2004 12:53 PM Rev. 7 of Salem/HC Work Environment Letter Glenn, et. al.

The attached represents the latest version fo the letter, based on changes suggested at the meeting this morning.

)hn Jolicoeur -Salem/HG issues v'aoe I

)hn Jolicoeur -Salem/I-IC issues raae 1 m

From:

Brian Holian

"/

To:

ArB; David Vito; Eileen Neff; Ernest Wilson; Glenn Meyer Date:

Tue, Jan 6, 2004 5:22 PM

Subject:

Salem/HC issues the following are short notes from a discussion I had with David Lochbaum today. Dave called to tell me he had met with the high profile Salem/HC alleger....He, along with Riccio and Billie Guarde met and discussed the issues. Although the alleger believes the NRC is doing a lot of effort.., a concern remains over "how long it will takem... (losing patience were the words used).

Lochbaum stated that from their perspective...they informed the alleger that these reviews take time...and from what they could see...Region was doing the right things.

Lochbaum called me to inform me that although the alleger was willing to go public (mentioned the O'Reilly show)....he thought that would not be the next step.

However, NRC could expect to see letters from the NJ pongressional delegation to the Chman on this subject.

The letters would state they know these Issues are being investigated....and would ask for two things - an estimated completion date, and the NRC's report when we are finished. He stated that they would also let Jill Lipoti, State of NJ know.

He felt that these actions would help to ensure that NRC had the resources and schedule focus to finish...

I gave Dave a general indication that the NRC is progressing...and he understood that.

He understands from the alleger that the NRC has numerous transcripts to review, etc.

The region has a routine status meeting on this issue scheduled for Thursday at 10 am. Branch 3, other than providing an update, is evaluating the merits of a chilling effect letter to the licensee.

CC:

Cornelius Holden; HJM1; John Jolicoeur; JTW1