Letter to the Administrative Judges from Counsel for Entergy Following Up on One of the Two Matters Raised at Last Weeks Prehearing Conference
ML062020235
Person / Time
Site: Pilgrim
Issue date: 07/13/2006
From: Gaukler P
Entergy Nuclear Generation Co, Pillsbury, Winthrop, Shaw, Pittman, LLP
To: Cole R, Nicholas Trikouros, Austin Young
Atomic Safety and Licensing Board Panel
Giitter R
References
06-848-02-LR, 50-293-LR, RAS 11995
Download: ML062020235 (2)


Text

2300 N Street NW Tel 202.663.8000 DI~

DCKEEDWashington. DC 20037-1122 Fax 202.663.8007 Pillsb~ury DOKTDwww.pillsburylaw.com Winthrop USNRC Shaw July 19, 2006 (3:35pm)

Pitt man,.

OFFICE OF SECRETARY RULEMAKINGS AND

July13, 006ADJUDICATIONS STAFF Paul A. Gaukier Phone: 202.663.8304 paul.gaukler@pillsburylaw.com Ann Marshall Young, Esq., Chair Dr. Nicholas G. Trikouros Administrative Judge Administrative Judge Atomic Safety and Licensing Board Atomic Safety and Licensing Board U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Washington, DC 20555 Washington, DC 20555 Dr. Richard F! Cole Administrative Judge Atomic Safety and Licensing Board U.S. Nuclear Regulatory Commission Washington, DC 20555 Re:

Entergy Nuclear Generation Company and Entergy Nuclear Operations', Inc. (Pilgrim Nuclear Power Station)

Docket No. 50-293-LR

Dear Administrative Judges:

This letter addresses one of the two matters raised at last week's prehearing conference that Entergy promised to follow-up on and report back to the Licensing Board and the parties. With respect to providing the parties copies of Pilgrim licensing correspondence, we have arranged to have counsel for the parties placed on Pilgrim's distribution list for licensing correspondence on the license renewal docket.

Accordingly, counsel for the parties will be sent Entergy's responses to RAls and any amendments to the license renewal application. We will address later in a separate letter the second matter concerning whether there are any additional buried pipes or tanks that are within the scope of the Pilgrim license renewal application.

Sincerely, Paul A. Gaukler, Esq.

Counsel for Entergy E

-N 0

July 13, 2006 Page 2 cc:

Service List 400423224 vi