Westinghouse Request for Withholding Information from Public Disclosure by Letter Dated October 3, 2005,
ML062000670
Person / Time
Site: Byron, Braidwood  Constellation icon.png
Issue date: 09/20/2006
From: Robert Kuntz
Plant Licensing Branch III-2
To: Gresham J
Westinghouse
Kuntz, Robert , NRR/DLPM, 415-3733
References
LTR-CAW-05-2033, TAC MC8693, TAC MC8694, TAC MC8695, TAC MC8696, WCAP-16143-P
Download: ML062000670 (5)


Text

September 20, 2006 J. A. Gresham, Manager Regulatory Compliance and Plant Licensing Westinghouse Electric Company LLC Nuclear Services P.O. Box 355 Pittsburgh, PA 15230-0355

SUBJECT:

WESTINGHOUSE ELECTRIC COMPANY LLC, REQUEST FOR WITHHOLDING INFORMATION FROM PUBLIC DISCLOSURE FOR BYRON STATION, UNIT NOS. 1 AND 2, AND BRAIDWOOD STATION, UNIT NOS. 1 AND 2 (TAC MC8693, MC8694, MC8695 AND MC8696)

Dear Mr. Gresham:

By letter to the Nuclear Regulatory Commission (NRC) dated October 3, 2005, Exelon Generation Company, LLC, submitted an affidavit dated July 29, 2005, executed by you requesting that the information contained in the following document be withheld from public disclosure pursuant to Title 10 of the Code of Federal Regulations (10 CFR), Part 2, Section 2.390:

Westinghouse Electric Company LLC, LTR-CAW-05-2033, WCAP-16143-P,

?Reactor Vessel Closure Head/Vessel Flange Requirements Evaluation for Byron/Braidwood Units 1 and 2, dated July 27, 2005 A nonproprietary copy of this document has been placed in the NRC's Public Document Room and added to the Agencywide Documents Access and Management System Public Electronic Reading Room.

The affidavit stated that the submitted information should be considered exempt from mandatory public disclosure for the following reasons:

(i)

The information sought to be withheld from public disclosure is owned and has been held in confidence by Westinghouse.

(ii)

The information is of a type customarily held in confidence by Westinghouse and not customarily disclosed to the public.

(iii)

The information is being transmitted to the Commission in confidence and, under the provisions of 10 CFR Section 2.390, it is to be received in confidence by the Commission.

(iv)

The information sought to be protected is not available in public sources or available information has not been previously employed in the same original manner or method to the best of our knowledge and belief.

J. Gresham We have reviewed your application and the material in accordance with the requirements of 10 CFR 2.390 and, on the basis of your statements, have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure.

Therefore, the version of the submitted information marked as proprietary will be withheld from public disclosure pursuant to 10 CFR 2.390(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.

Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.

If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.

If you have any questions regarding this matter, I may be reached at 301-415-3733.

Sincerely,

/RA/

Robert F. Kuntz, Project Manager Licensing Plant Branch III-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. STN 50-454, STN 50-455, STN 50-456 and STN 50-457 cc: See next page

J. Gresham We have reviewed your application and the material in accordance with the requirements of 10 CFR 2.390 and, on the basis of your statements, have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure.

Therefore, the version of the submitted information marked as proprietary will be withheld from public disclosure pursuant to 10 CFR 2.390(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.

Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.

If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.

If you have any questions regarding this matter, I may be reached at 301-415-3733.

Sincerely,

/RA/

Robert F. Kuntz, Project Manager Licensing Plant Branch III-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. STN 50-454, STN 50-455, STN 50-456 and STN 50-457 cc: See next page DISTRIBUTION:

PUBLIC RidsAcrsAcnwMailCenter LPL3-2 R/F RidsNrrDciCvib RidsNrrPMRKuntz RidsRgn3MailCenter RidsNrrLADClarke RidsNrrDorlLpl3-2 ADAMS Accession Number:ML062000670 OFFICE PM:LPL3-2 LA:LPL3-2 CVIB:BC BC:LPD3-2 NAME RKuntz:mw DClarke MMitchell DCollins DATE 9/14/2006 9/13/2006 9/18/2006 9/20/2006 OFFICIAL RECORD COPY

Byron/Braidwood Stations cc:

Dwain W. Alexander, Project Manager Westinghouse Electric Corporation Energy Systems Business Unit Post Office Box 355 Pittsburgh, PA 15230-0355 Howard A. Learner Environmental Law and Policy Center of the Midwest 35 East Wacker Dr., Suite 1300 Chicago, IL 60601-2110 U.S. Nuclear Regulatory Commission Byron Resident Inspectors Office 4448 N. German Church Road Byron, IL 61010-9750 Regional Administrator, Region III U.S. Nuclear Regulatory Commission Suite 210 2443 Warrenville Road Lisle, IL 60532-4351 Ms. Lorraine Creek RR 1, Box 182 Manteno, IL 60950 Chairman, Ogle County Board Post Office Box 357 Oregon, IL 61061 Mrs. Phillip B. Johnson 1907 Stratford Lane Rockford, IL 61107 Attorney General 500 S. Second Street Springfield, IL 62701 Illinois Emergency Management Agency Division of Disaster Assistance &

Preparedness 110 East Adams Street Springfield, IL 62701-1109 Plant Manager - Byron Station Exelon Generation Company, LLC 4450 N. German Church Road Byron, IL 61010-9794 Site Vice President - Byron Exelon Generation Company, LLC 4450 N. German Church Road Byron, IL 61010-9794 U.S. Nuclear Regulatory Commission Braidwood Resident Inspectors Office 35100 S. Rt. 53, Suite 79 Braceville, IL 60407 County Executive Will County Office Building 302 N. Chicago Street Joliet, IL 60432 Plant Manager - Braidwood Station Exelon Generation Company, LLC 35100 S. Rt. 53, Suite 84 Braceville, IL 60407-9619 Ms. Bridget Little Rorem Appleseed Coordinator 117 N. Linden Street Essex, IL 60935 Document Control Desk - Licensing Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 Site Vice President - Braidwood Exelon Generation Company, LLC 35100 S. Rt. 53, Suite 84 Braceville, IL 60407-9619 Senior Vice President - Operations Support Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555

Byron/Braidwood Stations Director - Licensing and Regulatory Affairs Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 Manager Regulatory Assurance - Braidwood Exelon Generation Company, LLC 35100 S. Rt. 53, Suite 84 Braceville, IL 60407-9619 Manager Regulatory Assurance - Byron Exelon Generation Company, LLC 4450 N. German Church Road Byron, IL 61010-9794 Assistant General Counsel Exelon Generation Company, LLC 200 Exelon Way Kennett Square, PA 19348 Vice President - Regulatory & Legal Affairs Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 Manager Licensing - Braidwood/Byron Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 Senior Vice President - Midwest Operations Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555