July 18, 2006 Mr. David A. Christian Sr. Vice President and Chief Nuclear Officer Dominion Nuclear Connecticut, Inc.
Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711
SUBJECT:
MILLSTONE POWER STATION, UNIT NOS. 2 AND 3 - ACTING BRANCH CHIEF, PLANT LICENSING BRANCH 1-2
Dear Mr. Christian:
This letter is to inform you that, effective July 10, 2006, Ms. Brooke Poole was assigned the position of Acting Chief, Section 2, Plant Licensing Branch 1, Division of Operating Reactor Licensing, Office of Nuclear Reactor Regulation, for a period of three months. Ms. Pooles mail stop is O8B-1A and her phone number is 301-415-1430. Ms. Pooles e-mail address remains BDP@nrc.gov.
Sincerely,
/RA/
Cornelius F. Holden Deputy Director Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-336 and 50-423 cc: See following pages
Millstone Power Station, Unit Nos. 2 and 3 cc:
Lillian M. Cuoco, Esquire Senior Counsel Dominion Resources Services, Inc.
Building 475, 5th Floor Rope Ferry Road Waterford, CT 06385 Edward L. Wilds, Jr., Ph.D.
Director, Division of Radiation Department of Environmental Protection 79 Elm Street Hartford, CT 06106-5127 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 First Selectmen Town of Waterford 15 Rope Ferry Road Waterford, CT 06385 Charles Brinkman, Director Washington Operations Nuclear Services Westinghouse Electric Company 12300 Twinbrook Pkwy, Suite 330 Rockville, MD 20852 Senior Resident Inspector Millstone Power Station c/o U.S. Nuclear Regulatory Commission P. O. Box 513 Niantic, CT 06357 Mr. J. W. "Bill" Sheehan Co-Chair NEAC 19 Laurel Crest Drive Waterford, CT 06385 Ms. Nancy Burton 147 Cross Highway Redding Ridge, CT 00870 Mr. Evan W. Woollacott Co-Chair Nuclear Energy Advisory Council 128 Terrys Plain Road Simsbury, CT 06070 Mr. Joseph Roy Director of Operations Massachusetts Municipal Wholesale Electric Company P.O. Box 426 Ludlow, MA 01056 Mr. David W. Dodson Licensing Supervisor Dominion Nuclear Connecticut, Inc.
Building 475, 5th Floor Roper Ferry Road Waterford, CT 06385 Mr. J. Alan Price Site Vice President Dominion Nuclear Connecticut, Inc.
Building 475, 5th Floor Rope Ferry Road Waterford, CT 06385 Mr. Chris L. Funderburk Director, Nuclear Licensing and Operations Support Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711
July 18, 2006 Mr. David A. Christian Sr. Vice President and Chief Nuclear Officer Dominion Nuclear Connecticut, Inc.
Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711
SUBJECT:
MILLSTONE POWER STATION, UNIT NOS. 2 AND 3 - ACTING BRANCH CHIEF, PLANT LICENSING BRANCH 1-2
Dear Mr. Christian:
This letter is to inform you that, effective July 10, 2006, Ms. Brooke Poole was assigned the position of Acting Chief, Section 2, Plant Licensing Branch 1, Division of Operating Reactor Licensing, Office of Nuclear Reactor Regulation, for a period of three months. Ms. Pooles mail stop is O8B-1A and her phone number is 301-415-1430. Ms. Pooles e-mail address remains BDP@nrc.gov.
Sincerely,
/RA/
Cornelius F. Holden Deputy Director Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-336 and 50-423 cc: See next page DISTRIBUTION:
PUBLIC RidsDorlLpl1-2 RidsNrrOd LPL1-2 Reading File RidsNrrDorl RidsNrrAdor RidsNrrPMVNerses RidsOgsRp LBerry, DORL RidsNrrLACRaynor RidsAcrsAcnwMailCenter RidsRgn1MailCenter ADAMS Accession Number: ML061990421 OFFICE LPL1-2/LA LPL1-2/PM LPL1-2/BC(A)
DORL/DD NAME CRaynor VNerses BPoole CHolden DATE 7/12/06 7/14/06 7/14/06 7/18/06 OFFICIAL RECORD COPY