Request for Additional Information for the Review of Vermont Yankee Nuclear Power Station License Renewal Application
ML061950021
Person / Time
Site: Vermont Yankee File:NorthStar Vermont Yankee icon.png
Issue date: 07/13/2006
From: Rowley J
NRC/NRR/ADRO/DLR/RLRB
To: Kansler M
Entergy Nuclear Operations
Rowley J, NRR/DRIP/RLRB, 415-4053
References
%dam200611
Download: ML061950021 (7)


Text

July 13, 2006 Mr. Michael Kansler President Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601-1839

SUBJECT:

REQUESTS FOR ADDITIONAL INFORMATION FOR THE REVIEW OF VERMONT YANKEE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION

Dear Mr. Kansler:

By letter dated January 25, 2006, as supplemented by letter dated March 15, 2006, the U.S. Nuclear Regulatory Commission (NRC) received the Entergy Nuclear Operations, Inc.

application for renewal of Operating License No. DPR-28 for the Vermont Yankee Nuclear Power Station (VYNPS). The NRC staff is reviewing the information contained in the license renewal application (LRA) and has identified, in the enclosure, areas where additional information is needed to complete the review. The enclosed requests for additional information are from Section 2.3, Scoping and Screening Results: Mechanical Systems, of the VYNPS LRA, specifically Subsection 2.3.1 and Subsection 2.3.2.

Based on discussions with Mr. Jim DeVincentis of your staff, a mutually agreeable date for your response is within 30 days of the date of this letter. If you have any questions regarding this letter or if circumstances result in your need to revise the response date, please contact me at 301-415-4053 or by e-mail at jgr@nrc.gov.

Sincerely,

/RA/

Jonathan Rowley, Project Manager License Renewal Branch B Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-271

Enclosure:

Requests for Additional Information cc w/encl: See next page

ML061950021 Document Name: E:\\Filenet\\ML061950021.wpd OFFICE PM:RLRB:DLR LA:DLR BC:RLRB;DLR NAME JRowley IKing JZimmerman DATE 07/ 13 /06 07/ 13 /06 07/ 13 /06

Letter to Michael Kansler from Jonathan Rowley dated July 13, 2006

SUBJECT:

REQUEST FOR ADDITIONAL INFORMATION FOR THE REVIEW OF VERMONT YANKEE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION HARD COPY DLR R/F E-MAIL:

JFair RWeisman AMurphy RPettis GGalletti DShum GBagchi SSmith (srs3)

SDuraiswamy YL (Renee) Li RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDe RidsNrrDci RidsNrreEemb RidsNrrDeEeeb RidsNrrDeEqva RidsNrrDss RidsNrrDnrl RidsOgcMailCenter RidsNrrAdes DLR Staff JEads JRowley RLaufer JShea CAnderson, RI MSykes, RI DScrenci, RI MModes, RI DPelton, Sr. Resident MLemoncelli RidsOpaMail

Vermont Yankee Nuclear Power Station cc:

Regional Administrator, Region I U. S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406-1415 Mr. David R. Lewis Pillsbury, Winthrop, Shaw, Pittman, LLP 2300 N Street, N.W.

Washington, DC 20037-1128 Mr. David OBrien, Commissioner Vermont Department of Public Service 112 State Street Montpelier, VT 05620-2601 Mr. James Volz, Chairman Public Service Board State of Vermont 112 State Street Montpelier, VT 05620-2701 Chairman, Board of Selectmen Town of Vernon P.O. Box 116 Vernon, VT 05354-0116 Operating Experience Coordinator Vermont Yankee Nuclear Power Station 320 Governor Hunt Road Vernon, VT 05354 G. Dana Bisbee, Esq.

Deputy Attorney General 33 Capitol Street Concord, NH 03301-6937 Chief, Safety Unit Office of the Attorney General One Ashburton Place, 19th Floor Boston, MA 02108 Ms. Deborah B. Katz Box 83 Shelburne Falls, MA 01370 Ms. Carla A. White, RRPT, CHP Radiological Health Vermont Department of Health P.O. Box 70, Drawer #43 108 Cherry Street Burlington, VT 05402-0070 Mr. James M. DeVincentis Manager, Licensing Vermont Yankee Nuclear Power Station P.O. Box 0500 185 Old Ferry Road Brattleboro, VT 05302-0500 Resident Inspector Vermont Yankee Nuclear Power Station U. S. Nuclear Regulatory Commission P.O. Box 176 Vernon, VT 05354 Director, Massachusetts Emergency Management Agency ATTN: James Muckerheide 400 Worcester Rd.

Framingham, MA 01702-5399 Jonathan M. Block, Esq.

Main Street P.O. Box 566 Putney, VT 05346-0566 Mr. John F. McCann Director, Licensing Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601 Mr. Gary J. Taylor Chief Executive Officer Entergy Operations 1340 Echelon Parkway Jackson, MS 39213

Vermont Yankee Nuclear Power Station cc:

Mr. John T. Herron Sr. VP and Chief Operating Officer Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601 Mr. Oscar Limpias Vice President, Engineering Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601 Mr. Christopher Schwartz Vice President, Operations Support Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601 Mr. Michael J. Colomb Director of Oversight Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601 Mr. Travis C. McCullough Assistant General Counsel Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601 Mr. Ted Sullivan Site Vice President Entergy Nuclear Operations, Inc.

Vermont Yankee Nuclear Power Station P.O. Box 0500 185 Old Ferry Road Brattleboro, VT 05302-0500 Mr. James H. Sniezek 5486 Nithsdale Drive Salisbury, MD 21801 Ms. Stacey M. Lousteau Treasury Department Entergy Services, Inc.

639 Loyola Avenue New Orleans, LA 70113 Mr. Raymond Shadis New England Coalition Post Office Box 98 Edgecomb, ME 04556 Mr. James P. Matteau Executive Director Windham Regional Commission 139 Main Street, Suite 505 Brattleboro, VT 05301 Mr. William K. Sherman Vermont Department of Public Service 112 State Street Drawer 20 Montpelier, VT 05620-2601 Mr. Michael D. Lyster 5931 Barclay Lane Naples, FL 34110-7306 Ms. Charlene D. Faison Manager, Licensing 440 Hamilton Avenue White Plains, NY 10601 Mr. James Ross Nuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, DC 20006-3708

Enclosure VERMONT YANKEE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION REQUESTS FOR ADDITIONAL INFORMATION (RAIs)

RAI 2.3.1.1-1 In Table 2.3.1-1 of the license renewal application (LRA), the reactor vessel leakage monitoring piping was not identified as a component within scope requiring an aging management review (AMR). The staff requests the applicant to identify the subject components within scope, because it is considered as part of the pressure boundary, and accordingly, it should be within the scope of license renewal and subject to AMR. If, however, the applicant believes that the components need not require an AMR, then they should provide plant-specific justification based on the description of the subject components, or any other relevant information, as to why the components need not be subjected to an AMR.

RAI 2.3.1.1-2 The staff believes that the scram discharge piping and volume should be in scope requiring aging management. However, it appears that the subject component was not identified in Table 2.3.1-1 of the LRA. Please justify.

RAI 2.3.1.1-3 The staff understands that the control rod drive housing supports (CRDHS) limit the travel of a control rod in the event that a control rod housing is ruptured. The supports prevent a nuclear excursion as a result of a housing failure, thus protecting the fuel barrier, and limiting radioactive releases. In addition, following a postulated failure of the drive housing at the attachment weld at the same time the control rod is withdrawn, and if the collet were to stay unlatched, the housing would separate from the vessel, and the drive and housing would be blown downward against the CRDHS. If credit is taken for the CRDHS; and since, the CRDHS are passive and long-lived, the staff believes that the subject components should be within the scope of license renewal requiring aging management. It appears, however, that the subject components and their intended function of limiting travel of the control rod following control rod housing rupture have not been identified in Table 2.3.1-1 of the LRA. Therefore, the staff requests the applicant to provide an explanation.

RAI 2.3.2.1-1 The low pressure coolant injection coupling was identified in the Boiling Water Reactor Vessel and Internals Project (BWRVIP) -06 report as a safety-related component. It appears, however, that the component was not identified in Table 2.3.2-1 of the LRA requiring an AMR.

If the component exists at Vermont Yankee, then the staff requests the applicant to justify its exclusion from aging management; otherwise, submit an AMR for the subject component.

RAI 2.3.2.1-2 Please clarify whether the passive components, namely, vortex breakers used in pump suction lines, which could be located inside the emergency core cooling system tanks or in the sump, and whose intended functions are to protect the pumps from cavitation, are subject to an AMR.

If so, identify which of these tanks are equipped with such passive components, and where in the LRA are the AMRs for these components, or provide justifications for exclusion of these components from aging management requirements.

RAI 2.3.2.4-1 The steam supply and return lines for high pressure coolant injection and reactor core isolation cooling (RCIC) perform safety functions, and therefore, should be in scope of license renewal in accordance with 10 CFR 50.4(a)(1). The staff requests the applicant to clarify whether the subject components are in scope requiring an AMR.

RAI 2.3.3.13-1 In Page 2.3-68 of the LRA, it was stated that the safety function of the neutron monitoring system is to detect conditions in the core that threaten the overall integrity of the fuel barrier due to excessive power generation and provide signals to the reactor protection system so that the release of radioactive material from the fuel barrier is limited, and that these signals are provided from the intermediate range monitor (IRM) and average power range monitor (APRM).

The staff believes that in addition to IRM and APRM, rod block monitor, local power range monitor, and oscillating power range monitor also perform safety functions, and therefore, these components and the related electrical cables should also be in the scope of license renewal requiring an AMR.