ML061810085

From kanterella
Jump to navigation Jump to search
Getr, EVESR and Vbwr Organization Changes
ML061810085
Person / Time
Site: Vallecitos Nuclear Center, Vallecitos
Issue date: 06/26/2006
From: Doreen Turner
General Electric Co
To:
Document Control Desk, NRC/FSME
References
Download: ML061810085 (1)


Text

GE Infrastructure Energy, Nuclear David W. Turner Manager. Vaolecitos Nuclear Center 6705 Vallecitos Rd Sunol, CA 94586 USA ATTN: Document Control Desk T925 862 4344 U.S. Nuclear RegulatoryCommission F910 341 2577 Washington, DC 20555-0001 davidw.turner@ge.com Monday, June 26th, 2006 Subj: GETR, EVESR and VBWR Organization Changes RE: (1) -

(2) License DR-1O, Docket 505-183 (EVESR)

(3) License DPR-1, Docket 50-18 (VBWR)

On January 19th, 2006 1relieved Scott Bump as the Manger, Vallecitos Nuclear Center. To support this move, Chuck Bassett temporarily was assigned responsibility for the Regulatory Compliance function.

Today, Latonya Martin assumes the responsibilities within the three referenced licenses for Regulatory Compliance &EHS. These positions are referenced in the technical specifications of the above referenced licenses as follows License Manger, Vallecitos Nuclear Center Regulatory Compliance & EHS TR-1 (GETR) Level 1 Organization Head Radiation Safety DR-10 (EVESR) & References to supervision at various References to safety or licensing DPR-1 (VBWR) levels functions Ref. 1, requires a report within 30 days per Tech Spec 6.6.2(2) for Level 1 and Level 2 organizational changes, Refs. 2 and 3 do not contain specific requirements of this nature, but are reported here for completeness. This Level 1 report was made by telephone and e-mail on January 23rd, 2006, from David Turner to the NRC.

If you have any questions in the above matters, please contact me at the address above, davidw.turner@ge.com, by phone at 925.862.4344 or Tanya Martin at latonya.martin@ge.com or 925.862.4360.

Sincerely yours, Digitally signed by David W. Turner Date: 2006.0626 14:00:01 -07'00' David W.Turner Manager, Vallecitos Nuclear Center cc Marvin Mendonco, Project Manger oo(P Gerero BectricCompany Ge,,,,~lecricot~~ooyOWT-2006-19 Oganizational ChangesforGEIR.EVER andVBw~doc