MONTHYEARML24038A0322024-02-0707 February 2024 (Vcsns), Unit 1, 10 CFR 21 Report - Emergency Diesel Generator Flash Contactor Relay IR 05000395/20230042024-01-31031 January 2024 Integrated Inspection Report 05000395/2023004 ML24022A1582024-01-22022 January 2024 (Vcsns), Unit 1 - Reply to a Notice of Violation: EA-23-093 ML24022A1202024-01-22022 January 2024 Notification of Target Set Inspection and Request for Information (NRC Inspection Report 05000395/2024403) ML24018A0112024-01-18018 January 2024 CFR 21 Report Emergency Diesel Generator Fuel Oil Piping IR 05000395/20240112024-01-17017 January 2024 Notification of VC Summer Station Comprehensive Engineering Team Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000395/2024011 ML23361A1042023-12-21021 December 2023 Inservice Testing Program for Pumps and Valves Fifth Interval Update and Associated Relief and Alternative Requests IR 05000395/20230912023-12-21021 December 2023 Final Significance Determination of a White Finding and Notice of Violation and Assessment Followup Letternrc Inspection Report 05000395/2023091 ML23354A1802023-12-20020 December 2023 301 Examination Report with Cover Letter ML23347A0492023-12-12012 December 2023 Technical Specification Bases Changes Updated Through November 2023 ML23334A2462023-11-30030 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23334A2372023-11-30030 November 2023 (Vvsns), Unit 1 - Annual Commitment Change Summary Report ML23332A1942023-11-28028 November 2023 (Vcsns), Unit 1, Correction of Typographical Error in License Amendment Request - Inverter Allowed Outage Time (AOT) Extension ML23317A2242023-11-0909 November 2023 (Vcsns), Unit 1 - License Amendment Request - Inverter Allowed Outage Time (AOT) Extension ML23289A1172023-11-0303 November 2023 Tribal Request for Scoping Comments Concerning the Environmental Review of the V.C. Summer SLRA ML23289A1152023-11-0303 November 2023 Ltr to R. Nelson - Request for Scoping Comments Concerning the Environmental Review of the V.C. Summer SLRA ML23289A1162023-11-0303 November 2023 Ltr to W. Emerson - Request for Scoping Comments Concerning the Environmental Review of the V.C. Summer SLRA IR 05000395/20234032023-11-0101 November 2023 Material Control and Accounting Program Inspection Report 05000395/2023403 Cover IR 05000395/20230032023-11-0101 November 2023 Integrated Inspection Report 05000395/2023003 ML23284A1792023-10-16016 October 2023 Subsequent License Renewal Application Online Reference Portal ML23275A0142023-10-11011 October 2023 SLRA - Acceptance and Opportunity for Hearing - Letter ML23284A1662023-10-10010 October 2023 (Vcsns), Unit 1 - Request for Regulatory Conference; (EA-23-093) IR 05000395/20230902023-10-0404 October 2023 NRC Inspection Report 05000395/2023090 and Preliminary Yellow Finding and Apparent Violation IR 05000395/20230112023-09-27027 September 2023 Focused Engineering Inspection Report 05000395/2023011 ML23250A3112023-09-20020 September 2023 Request to Revise Reactor Vessel Material Surveillance Capsule Withdrawal Schedules ML23244A2352023-09-18018 September 2023 Request to Use a Subsequent Edition of the ASME Code, Section XI ML23230A0012023-09-15015 September 2023 Request to Use a Provision of a Previous Edition of the ASME Boiler and Pressure Vessel Code, Section XI, for Non-Destructive Examinations ML23235A0432023-09-0505 September 2023 Receipt and Availability of the Subsequent License Renewal Application IR 05000395/20234012023-08-30030 August 2023 Security Baseline Inspection Report 05000395/2023401 ML23242A1192023-08-29029 August 2023 (Vcsns), Unit 1 - Inservice Inspection (ISI) Owner'S Activity Report (OAR) for Refueling Outage 27 ML23243B0362023-08-25025 August 2023 Request for FEMA Consultation on the Dominion Energy Proposal to Consolidate the Emergency Operations Facility for the Virgil C. Summer Nuclear Station Unit 1 IR 05000395/20230052023-08-23023 August 2023 Updated Inspection Plan for Virgil C. Summer Nuclear Station (Report 05000395 2023005) ML23233A1752023-08-17017 August 2023 Application for Subsequent Renewed Operating License IR 05000395/20230022023-08-14014 August 2023 Integrated Inspection Report - Integrated Inspection Report 05000395/2023002 and Apparent Violation IR 05000395/20230102023-08-12012 August 2023 Biennial Problem Identification and Resolution Inspection Report 05000395/2023010 ML23207A1102023-07-26026 July 2023 NRC Regulatory Issues Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations IR 05000395/20234412023-07-17017 July 2023 95001 Supplemental Inspection Report 05000395/2023441 and Follow Up Assessment Letter ML23190A0012023-07-0909 July 2023 Special Report 2023-003 Inoperable Radiation Monitoring Instrumentation Channel ML23187A5092023-07-0606 July 2023 Request for Federal Emergency Management Agency Consultation on the Dominion Energy Proposal to Consolidate the Emergency Operations Facility for the Virgil C. Summer Nuclear Station Unit 1 ML23178A1682023-06-26026 June 2023 2022 Annual Report of Emergency Core Cooling System (ECCS) Model Changes Pursuant to the Requirements of 10 CFR 50.46 ML23173A1052023-06-22022 June 2023 Special Report 2023-002 Inoperable Loose-Part Monitoring System Channel ML23163A2352023-06-12012 June 2023 Request to Use a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI, for the SPS Sixth Inservice Inspection (Isi) Intervals and VCSNS Fifth ISI Interval ML23159A2332023-06-0808 June 2023 License Amendment Request - Emergency Response Organization Augmentation Time Change, Emergency Operations Facility Relocation and Other Emergency Plan Changes ML23156A3092023-06-0505 June 2023 Requalification Program Inspection Virgil C. Summer Nuclear Station Unit 1 - 05000395/2023003 2024-02-07
[Table view] |
Text
September 20, 2006 Mr. Jeffery B. Archie Vice President, Nuclear Operations South Carolina Electric & Gas Company Virgil C. Summer Nuclear Station Post Office Box 88 Jenkinsville, SC 29065
SUBJECT:
NRC RECEIPT OF VIRGIL C. SUMMER NUCLEAR STATION RESPONSE TO GENERIC LETTER 2006-03, POTENTIALLY NONCONFORMING HEMYC AND MT FIRE BARRIER CONFIGURATIONS (TAC NO, MD1636)
Dear Mr. Archie:
The Nuclear Regulatory Commission (NRC) acknowledges the receipt of your responses to Generic Letter 2006-03, Potentially Nonconforming Hemyc and MT Fire Barrier Configurations. Under oath or affirmation, you have stated that your nuclear power plant does not rely on either the Hemyc or MT fire barrier system. You have submitted documentation under oath or affirmation that other 1 or 3-hour fire barriers that separates redundant safe shutdown trains located within the same fire area have been designed and installed in accordance with current NRC guidance. Based on your responses, dated June 5 and August 4, 2006, the basis for stating that this other fire barriers have been designed and installed in accordance with NRC guidance should be maintained on site, and will be subject to inspection during the normal NRC inspection process.
If you have any questions regarding this response, please contact me at 301-415-1493 or rem@nrc.gov.
Sincerely,
/RA/
Robert E. Martin, Senior Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-395 cc: See next page
ML061660200 NRR-106 OFFICE LPL2-1/PM LPL2-1 LPL2-1/LA AFPB/FPE LPL2-1/BC NAME RMartin RJervey CSola D. Frumkin EMarinos DATE 9/11/06 7/07/06 9/11/06 9/04/06 9/20/06 Mr. Jeffrey B. Archie VIRGIL C. SUMMER NUCLEAR STATION South Carolina Electric & Gas Company cc:
Mr. R. J. White Nuclear Coordinator S.C. Public Service Authority c/o Virgil C. Summer Nuclear Station Post Office Box 88, Mail Code 802 Jenkinsville, South Carolina 29065 Resident Inspector/Summer NPS c/o U.S. Nuclear Regulatory Commission 576 Stairway Road Jenkinsville, South Carolina 29065 Chairman, Fairfield County Council Drawer 60 Winnsboro, South Carolina 29180 Mr. Henry Porter, Assistant Director Division of Waste Management Bureau of Land & Waste Management Dept. of Health & Environmental Control 2600 Bull Street Columbia, South Carolina 29201 Mr. Thomas D. Gatlin, General Manager Nuclear Plant Operations South Carolina Electric & Gas Company Virgil C. Summer Nuclear Station Post Office Box 88, Mail Code 300 Jenkinsville, South Carolina 29065 Mr. Robert G. Sweet, Manager Nuclear Licensing South Carolina Electric & Gas Company Virgil C. Summer Nuclear Station Post Office Box 88, Mail Code 830 Jenkinsville, South Carolina 29065 Ms. Kathryn M. Sutton Morgan, Lewis & Bockius LLP 111 Pennsylvania Avenue, NW.
Washington, DC 20004