Forthcoming Meeting with R.E. Ginna Nuclear Power Plant, LLC
ML061590439
Person / Time
Site: Ginna Constellation icon.png
Issue date: 06/08/2006
From: Milano P
Plant Licensing Branch III-2
To: Richard Laufer
Plant Licensing Branch III-2
Milano P, NRR/DLPM 415-1457
References
Download: ML061590439 (6)


Text

June 8, 2006 MEMORANDUM TO: Richard J. Laufer, Chief Plant Licensing Branch I-1 Division of Operating Reactor Licensing FROM: Patrick D. Milano, Senior Project Manager /RA/

Plant Licensing Branch I-1 Division of Operating Reactor Licensing

SUBJECT:

FORTHCOMING MEETING WITH R.E. GINNA NUCLEAR POWER PLANT, LLC DATE & TIME: Tuesday, June 27, 2006 10:00 a.m. - 2:00 p.m.

LOCATION: U.S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike, Room O-14B8 Rockville, Maryland PURPOSE: Discuss the inspection plans proposed for the reactor vessel and internals, including the bottom mounted instrument penetrations, during the fall 2006 refueling outage.

CATEGORY 1:* This is a Category 1 Meeting. The public is invited to observe this meeting and will have one or more opportunities to communicate with the NRC after the business portion, but before the meeting is adjourned.

MEETING CONTACTS: P. D. Milano, NRR J. Boska, NRR 301-415-1457 301-415-2901 pdm@nrc.gov xxx@nrc.gov

  • Commission's Policy Statement on Enhancing Public Participation in NRC Meetings (67 FR 36920), May 28, 2002

PARTICIPANTS: Participants from the NRC include members of the Office of Nuclear Reactor Regulation (NRR) and Region I (R-I).

NRC Ginna LLC P. Milano, NRR G. Verdin M. Mitchell, NRR J. Pacher E. Sullivan, NRR A. Butcavage B. Elliott, NRR R. Randall G. Cheruvenki, NRR et al.

E. Gray, R-I T. OHara, R-I B. Bickett, R-I Docket No. 50-244

Enclosure:

Agenda cc w/encl: See next page

PARTICIPANTS: Participants from the NRC include members of the Office of Nuclear Reactor Regulation (NRR) and Region I (R-I).

NRC Ginna LLC P. Milano, NRR G. Verdin M. Mitchell, NRR J. Pacher E. Sullivan, NRR A. Butcavage B. Elliott, NRR R. Randall G. Cheruvenki, NRR et al.

E. Gray, R-I T. OHara, R-I B. Bickett, R-I Docket No. 50-244

Enclosure:

Agenda cc w/encl: See next page Distribution PUBLIC B. Bickett, R-I LPLI-1 Reading T. OHara, R-I B. Boger RidsNrrAdro R. Jasinski C. Haney RidsNrrDorl C. Anderson RidsRgn1MailCenter R. Laufer RidsNrrDorlLpl-1 D. Screnci, OPA R-I P. Milano RidsNrrPMPMilano B. Sosa, EDO RidsEdoMailCenter S. Little RidsNrrLASLittle OPA RidsOpaMail M. Mitchell RidsNrrDciCvib OGC RidsOgcMailCenter E. Sullivan ACRS RidsAcrsAcnwMailCenter B. Elliott G. Cheruvenki PMNS, Meeting Announcement Coordinator E. Gray, R-I Receptionists, OWFN and TWFN Accession Number: ML061590439 OFFICE LPLI-1\PM LPLI-1\LA CVIB\BC LPLI-1\BC NAME PMilano SLittle MMitchell RLaufer DATE 06/08/06 06/08/06 06/08/06 06/08/06 OFFICIAL RECORD COPY

MEETING AGENDA WORKING-LEVEL MEETING TO DISCUSS INFORMATION AND OTHER SUPPORTING ANALYSES REGARDING EXAMINATION PLAN FOR REACTOR VESSEL AND INTERNALS R.E. GINNA NUCLEAR POWER PLANT, LLC R.E. GINNA NUCLEAR POWER PLANT DOCKET NO. 50-244 Schedule Discussion Topics 10:00 a.m. - 10:15 a.m. Introduction 10:15 a.m. - 11:00 a.m. Strategy for performing visual inspections of the reactor vessel bottom head penetrations.

11:00 a.m. - 11:30 p.m. Discussion of methods and intentions regarding licensee renewal commitments on reactor vessel internals inspection.

11:30 a.m. - 12:30 p.m. Strategy for coordinating reactor vessel 10-year inservice inspection and license renewal inspection commitments.

12:30 p.m. - 1:00 p.m. Additional Questions/Comments and Summary Enclosure

R.E. Ginna Nuclear Power Plant cc:

Mr. Michael J. Wallace Mr. Charles Donaldson, Esquire President Assistant Attorney General R.E. Ginna Nuclear Power Plant, LLC New York Department of Law c/o Constellation Energy 120 Broadway 750 East Pratt Street New York, NY 10271 Baltimore, MD 21202 Ms. Thelma Wideman, Director Mr. John M. Heffley Wayne County Emergency Management Senior Vice President and Office Chief Nuclear Officer Wayne County Emergency Operations Constellation Generation Group Center 1997 Annapolis Exchange Parkway 7336 Route 31 Suite 500 Lyons, NY 14489 Annapolis, MD 21401 Ms. Mary Louise Meisenzahl Mrs. Mary G. Korsnick Administrator, Monroe County Vice President R.E. Ginna Nuclear Power Office of Emergency Preparedness Plant 1190 Scottsville Road, Suite 200 R.E. Ginna Nuclear Power Plant, LLC Rochester, NY 14624 1503 Lake Road Ontario, NY 14519 Mr. Paul Eddy New York State Department of Kenneth Kolaczyk, Sr. Resident Inspector Public Service R.E. Ginna Nuclear Power Plant 3 Empire State Plaza, 10th Floor U.S. Nuclear Regulatory Commission Albany, NY 12223 1503 Lake Road Ontario, NY 14519 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Mr. Peter R. Smith, President New York State Energy, Research, and Development Authority 17 Columbia Circle Albany, NY 12203-6399 Mr. Carey W. Fleming, Esquire Senior Counsel - Nuclear Generation Constellation Generation Group, LLC 750 East Pratt Street, 17th Floor Baltimore, MD 21202