ML061590235

From kanterella
Jump to navigation Jump to search

Request for Additional Information Regarding Relief Requests 1A, 14A, and 15A
ML061590235
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 06/16/2006
From: Moroney B
Plant Licensing Branch III-2
To: Stall J
Florida Power & Light Co
Moroney B, NRR/DORL, 415-3974
References
TAC MD0205, TAC MD0206
Download: ML061590235 (5)


Text

June 16, 2006 Mr. J. A. Stall Senior Vice President, Nuclear and Chief Nuclear Officer Florida Power and Light Company P.O. Box 14000 Juno Beach, Florida 33408-0420

SUBJECT:

TURKEY POINT PLANT, UNITS 3 AND 4 - REQUEST FOR ADDITIONAL INFORMATION REGARDING RELIEF REQUESTS 1A, 14A AND 15A (TAC NOS. MD0205 AND MD0206)

Dear Mr. Stall:

By letter dated February 20, 2006, Florida Power & Light Company requested relief from certain requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code,Section XI, due to limitations that were identified during the third 10-year inservice inspection interval at Turkey Point Units 3 and 4.

The U.S. Nuclear Regulatory Commission staff has reviewed your requests and finds that a response to the enclosed Request for Additional Information is needed before we can complete the review.

This request was discussed with members of your staff on June 1, and on June 14, 2006, Ms. Stavroula Mihalakea agreed that a response would be provided within 30 days of the date of this letter. If you have any questions, please contact me at (301) 415-3974.

Sincerely,

/RA/

Brendan T. Moroney, Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-250 and 50-251

Enclosure:

As stated cc w/encl: See next page

June 16, 2006 Mr. J. A. Stall Senior Vice President, Nuclear and Chief Nuclear Officer Florida Power and Light Company P.O. Box 14000 Juno Beach, Florida 33408-0420

SUBJECT:

TURKEY POINT PLANT, UNITS 3 AND 4 - REQUEST FOR ADDITIONAL INFORMATION REGARDING RELIEF REQUESTS 1A, 14A AND 15A (TAC NOS. MD0205 AND MD0206)

Dear Mr. Stall:

By letter dated February 20, 2006, Florida Power & Light Company requested relief from certain requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code,Section XI, due to limitations that were identified during the third 10-year inservice inspection interval at Turkey Point Units 3 and 4.

The U.S. Nuclear Regulatory Commission staff has reviewed your requests and finds that a response to the enclosed Request for Additional Information is needed before we can complete the review.

This request was discussed with members of your staff on June 1, and on June 14, 2006, Ms. Stavroula Mihalakea agreed that a response would be provided within 30 days of the date of this letter. If you have any questions, please contact me at (301) 415-3974.

Sincerely,

/RA/

Brendan T. Moroney, Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-250 and 50-251

Enclosure:

As stated cc w/encl: See next page Distribution:

PUBLIC LPL2-2 R/F RidsNrrPMBMoroney RidsNrrDorlLpl2-2 RidsNrrLABClayton RidsNrrDciCpnb RidsOgcRp RidsRgn2MailCenter RidsAcrsAcnwMailCenter TLupold, NRR ADAMS ACCESSION No.: ML061590235 NRR-088 OFFICE LPL2-2/PM LPL2-2/LA CPNB/BC LPL2-2/BC NAME BMoroney BClayton TChan MMarshall by memo dated DATE 6/14/06 6/14/06 05/30/06 6/16/06 OFFICIAL RECORD COPY

REQUEST FOR ADDITIONAL INFORMATION TURKEY POINT UNITS 3 AND 4 RELIEF REQUEST NOS. 1A, 14A, AND 15A DOCKET NOS. 50-250 AND 50-251 General

1. Relief Requests 1A, 14A and 15A indicated that the third 10-year inservice inspection (ISI) interval ended February 21, 2004, for Unit 3 and April 14, 2004, for Unit 4. By letter dated October 20, 2004, the NRC authorized extension of the third 10-year interval to February 21, 2005, for Unit 3 and to April 14, 2005, for Unit 4. Please indicate the proper end dates for the Unit 3 and Unit 4 third 10-year ISI intervals.

Relief Request 1A:

2. In Florida Power and Light Company (FPL) letter dated February 20, 2006, it is stated the objective of Relief Request 1A is to resubmit the previously approved Relief Request No.1. The request also states that this revision submits the examination volume coverage obtained during the third 10-year ISI interval inspection. In comparing Relief Request 1 with Relief Request 1A, the upper shell-to-flange weld is included in both requests. Welds 3-DO-A, 3-DO-B, 3-DO-C, 4-DO-A, 4-DO-B, 4-DO-C are included in Relief Request 1, but they are not included in relief request 1A. Relief Request 1A contains additional examinations that had limited coverage, welds 3-WR-9 and 4-WR-9 and the 1-inch annular surface of flange surrounding each reactor vessel stud hole.

Does Relief Request 1A supersede Relief Request 1, or is it in addition to Relief Request 1? If Relief Request 1A is to supersede Relief Request 1, was essentially full coverage obtained on welds 3-DO-A, 3-DO-B, 3-DO-C, 4-DO-A, 4-DO-B, 4-DO-C? If Relief Request 1A is to be in addition to Relief Request 1, is the request for relief with regard to welds 3-WR-18 and 4-WR-18 any different than the request for relief made under Relief Request 1 (other than 71-percent coverage was obtained vs. 68-percent projected)?

3. Relief Request 1A states that the examination of the Figure1 IWB-2500-12 A-B-C-D-E-F-G-H volume is limited when scanning the carbon steel base material surrounding the stud holes due to the sealing surfaces configuration. Please explain how the sealing surfaces configuration limits access to the required examination volume, and whether any alternate scanning angles can be used to achieve coverage in this area.

Relief Request 14A:

4. FPL letter dated February 20, 2006, states the objective of Relief Requests 14A and 15A is to resubmit the previously approved Relief Request 14 and 15 for Class 1 and 2 vessel inside radius, vessel welds, and piping welds that did not receive code-required volume. In comparing Relief Request 14 and Relief Request 14A, there are four components (29"-RCS-1305-3, 8"-SI-2309-22, 8"-SI-2309-24, and 6"-BDA-2301-8) that are listed in Relief Request 14 but not in Relief Request 14A. Please explain why the four components are not included in Relief Request 14A.
5. In Relief Request 14, component 3-SRGN-01-IR is listed under examination category B-D, item No. B3.120, which is applicable to the Pressurizer. In Relief Request 14A, component 3-SRGN-01-IR is listed as applicable to examination category B-D, item No. B3.140. Please explain this change in classification of component 3-RGN-01-IR.
6. Table 1 identifies the applicable code requirement for component Spray Nozzle-SP 1-IR as examination category B-D, item No. B3.140, which is applicable to steam generators. Please clarify whether this is a pressurizer spray nozzle or if it is applicable to steam generators.
7. Table 1 of Relief Request 14A indicates 66-percent coverage from the elbow side for component 31"-RCS-1302-10 was achieved. Relief Request 14 indicates 75-percent coverage from the elbow side for component 31"-RCS-1302-10 was achieved. Please explain the difference in coverage reported between the FPL August 8, 1996, letter and the February 20, 2006, letter.
8. Describe any flaws or relevant indications identified adjacent to the areas that could not be examined.

Relief Request 15A:

9. Describe any flaws or relevant indications identified adjacent to the areas that could not be examined.

Mr. J. A. Stall TURKEY POINT PLANT Florida Power and Light Company cc:

Mr. William E. Webster Mr. Craig Fugate, Director Vice President, Nuclear Operations Division of Emergency Preparedness Florida Power & Light Company Department of Community Affairs P.O. Box 14000 2740 Centerview Drive Juno Beach, FL 33408-0420 Tallahassee, Florida 32399-2100 Attorney General M. S. Ross, Managing Attorney Department of Legal Affairs Florida Power & Light Company The Capitol P.O. Box 14000 Tallahassee, Florida 32304 Juno Beach, FL 33408-0420 Michael O. Pearce Marjan Mashhadi, Senior Attorney Plant General Manager Florida Power & Light Company Turkey Point Nuclear Plant 801 Pennsylvania Avenue, NW. Florida Power and Light Company Suite 220 9760 SW. 344th Street Washington, DC 20004 Florida City, FL 33035 T. O. Jones, Site Vice President Walter Parker Turkey Point Nuclear Plant Licensing Manager Florida Power and Light Company Turkey Point Nuclear Plant 9760 SW. 344th Street 9760 SW 344th Street Florida City, FL 33035 Florida City, FL 33035 County Manager Mark Warner, Vice President Miami-Dade County Nuclear Operations Support 111 Northwest 1 Street, 29th Floor Florida Power and Light Company Miami, Florida 33128 P.O. Box 14000 Juno Beach, FL 33408-0420 Senior Resident Inspector Turkey Point Nuclear Plant Mr. Rajiv S. Kundalkar U.S. Nuclear Regulatory Commission Vice President - Nuclear Engineering 9762 SW. 344th Street Florida Power & Light Company Florida City, Florida 33035 P.O. Box 14000 Juno Beach, FL 33408-0420 Mr. William A. Passetti, Chief Department of Health Bureau of Radiation Control 2020 Capital Circle, SE, Bin #C21 Tallahassee, Florida 32399-1741