E-mail from B. Mcdermott of USNRC to Various, Regarding Forthcoming Update to NRC Web Page on Indian Point Spent Fuel Pool IssuesML061160469 |
Person / Time |
---|
Site: |
Indian Point |
---|
Issue date: |
11/30/2005 |
---|
From: |
Brian Mcdermott NRC Region 1 |
---|
To: |
Baranski J, Bondi R, Eddy P, Feroe P, Greeley D, Delores Greene, Gross S, Chris Miller, Salame-Alfie A, Shapiro G, Spath J, Stiebeling A, Sutton T, Youngberg B - No Known Affiliation, Entergy Nuclear Operations, Orange County, NY, Putnam County, NY, Rockland County, NY, State of NY, State of NY, Dept of Environmental Conservation, State of NY, Dept of Health, State of NY, Dept of Public Service, Westchester County, NY |
---|
References |
---|
FOIA/PA-2006-0081 |
Download: ML061160469 (5) |
|
|
---|
Category:E-Mail
MONTHYEARML24036A0162024-02-0101 February 2024 NRC Email - Acknowledge and Accept the Indian Point Energy Center Request to Be Removed from NRC Headquarters Operation Officer (Hoo) Morning Authentication Code Calls ML23341A2002023-12-0707 December 2023 Email - Indian Point Energy Center Generating Units 1, 2, and 3 – Implementation Notice of Amendment No. 67, 300 and 276 to Independent Spent Fuel Storage Installation Only Emergency Plan (Ioep) ML23332A0802023-11-0808 November 2023 – Email from State of New York on the Revised License Amendment for Indian Point Energy Center ISFSI Only Emergency Plan ML23331A9542023-11-0808 November 2023 Email - State of New York Comments on the Revised License Amendment for Indian Point Unit 2 and 3 Technical Specification Changes Reflecting Permanent Removal of Spent Fuel ML23325A1632023-11-0808 November 2023 – State of New York Comments on the Revised License Amendment for Indian Point Unit 2 and 3 Technical Specification Changes Reflecting Permanent Removal of Spent Fuel ML23144A3382023-05-25025 May 2023 Dawn Giambalvo of Jersey City, New Jersey Email Against Treated Water Release from Indian Point Site ML23144A3422023-05-25025 May 2023 Peter Duda of Pearl River, New York Email Against Treated Water Release from Indian Point Site ML23144A3452023-05-25025 May 2023 Adam Kahn of Monsey, New York Email Against Treated Water Release from Indian Point Site ML23144A3502023-05-25025 May 2023 Dan Kwilecki of Montebello, New York Email Against Treated Water Release from Indian Point Site ML23144A3392023-05-25025 May 2023 David Morris of New City, New York Email Against Treated Water Release from Indian Point Site ML23144A3442023-05-25025 May 2023 Peggy Kurtz of Rockland County, New York Email Against Treated Water Release from Indian Point Site ML23136B1622023-05-15015 May 2023 – Town of North Salem, County of Westchester, New York Board Resolution Letter Regarding Treated Water Release from Indian Point Site ML23109A0632023-04-17017 April 2023 Email Acceptance Review for IP2 and IP3 Amended Facility License and Technical Specification to Reflect Permanent Removal of Spent Fuel from Spent Fuel Pits ML23055A1112023-02-23023 February 2023 Alyse Peterson Email- NYSERDA No Comments on Indian Point Unit 2 - Regarding Holtec License Amendment Request to Revise Permanently Defueled Technical Specifications and Staffing Requirements with Spent Fuel Transfer to ISFSI (Dockets 50-24 ML23049A0032023-02-14014 February 2023 – NRC Acceptance Email to Holtec for License Amendment Request for Approval of New ISFSI-Only Emergency Plan and Associated EAL Scheme ML22313A1682022-11-0909 November 2022 NRC Response to Updates to the Proposed Amended IP2 Master Trust ML22308A0912022-11-0303 November 2022 Email Acknowledgement for IP2 and IP3 Amended Facility License and Technical Specification to Reflect Permanent Removal of Spent Fuel from Spent Fuel Pits ML22276A1642022-09-29029 September 2022 New York State Revised Draft EA Response E-Mail ML22271A8492022-09-28028 September 2022 E-Mail Transmitting Revised Indian Point Exemption Draft EA ML22269A3452022-09-22022 September 2022 Email Objection to Holtec IP2 Master Decommissioning Trust Agreement for Indian Point Nuclear Generating Facility Unit 1 and 2, EPID L-2022-LLA-0072 ML22259A1992022-09-0202 September 2022 Acceptance for License Amendment Request to Modify Staffing Requirements Following SFP Transfer to Dry Storage ML22265A0142022-08-31031 August 2022 Email Acknowledgement for Amended and Restated Holtec IP3 Master Decommissioning Trust Agreement for Indian Point Nuclear Generating Facility Unit 3 ML22242A2592022-08-19019 August 2022 E-mail from K. Sturzebecher, NRC, to B. Noval, HDI, Acknowledgement for Amended and Restated Holtec IP2 Master Decommissioning Trust Agreement for Indian Point Nuclear Generating Facility Unit 1 and 2 ML22228A1332022-08-0909 August 2022 Acknowledgement for License Amendment Request to Modify Staffing Requirements Following SFP Transfer to Dry Storage ML22215A0432022-08-0101 August 2022 E-Mail Transmitting NYS NSA Exemption Comments & Draft EA Review Completion ML22208A0292022-07-19019 July 2022 E-Mail Transmitting Indian Point Exemption Draft EA ML22168A0072022-06-16016 June 2022 Acceptance Review for License Amendment Request to Revise License Condition to Eliminate Cyber Security Plan Requirements ML22112A0102022-04-21021 April 2022 Acceptance Review: Request for Exemption from 10 CFR 50.54(w)(1) Concerning Indian Point Energy Center Onsite Property Damage Insurance ML22112A0122022-04-21021 April 2022 Acceptance Review: Request for Exemption from 10 CFR 140.11(a)(4) Concerning Primary and Secondary Liability Insurance for Indian Point Energy Center ML22103A2432022-04-13013 April 2022 E-mail - Request for Additional Information - License Amendment Request to Revise Emergency Plan and Emergency Action Level Scheme for Permanently Defueled Condition for Indian Point Energy Center ML22104A0342022-04-13013 April 2022 E-mail from Z. Cruz, NRC to J. Fleming, Holtec - Request for Additional Information Related to Request for Exemption from Portions of 10 CFR 50.47 and Part 50 Appendix E for Indian Point Energy Center ML22038A2572022-02-0707 February 2022 E-mail from Z. Cruz, NRC, to J. Fleming, HDI - Acceptance Review: License Amendment Request to Revise Emergency Plan and Emergency Action Level Scheme to Address Permanently Defueled Condition for Indian Point Energy Center ML22035A1862022-02-0404 February 2022 E-mail to J. Fleming, Holtec, from Z. Cruz Perez, NRC - Acceptance Review: Exemption Requests from Portions of 10 CFR 50.47 and 10 CFR Part 50, Appendix E, Section IV for Indian Point Energy Center ML22028A1032022-01-28028 January 2022 E-mail Dated 1/28/2022, Transmittal of Draft Safety Evaluation for Proposed License Amendment Revision to Licensing Basis to Incorporate the Installation and Use of of New Auxiliary Lifting Device ML22038A1592022-01-24024 January 2022 NRR E-mail Capture - (External_Sender) 2021 IPEC Annual Sturgeon Impingement Report ML22006A0442022-01-0505 January 2022 Email from Z Cruz to J Fleming Request for Additional Information - HDI Indian Point Post-Shutdown Decommissioning Activities Report ML21337A2952021-12-0303 December 2021 Subsequent Request for Additional Information License Amendment Request to Revise Licensing Basis for New Auxiliary Lifting Device (E-mail Dated 12/3/2021) ML21335A3692021-12-0101 December 2021 Acceptance Review: Indian Point Energy Center - Exemption Request from 10 CFR Part 20 App G Section Iii.E ML21266A2972021-08-18018 August 2021 8/18/2021 E-mail from H. Specter to R. Guzman Public Comments to NRC, Indian Point Post-Shutdown Decommissioning Activities Report Public Meeting on July 29, 2021 ML21225A5012021-08-0909 August 2021 Email from NRC to the Shinnecock Indian Nation Announcing the IPEC PSDAR Public Meeting on August 18, 2021 ML21224A3032021-08-0909 August 2021 Email from NRC to the Mashantucket Pequot Tribe of Connecticut Announcing the IPEC PSDAR Public Meeting on August 18, 2021 ML21225A6142021-08-0909 August 2021 Email from NRC to the Tuscarora Nation Announcing the IPEC PSDAR Public Meeting on August 18, 2021 ML21225A5682021-08-0909 August 2021 Email from NRC to the Stockbridge-Munsee Community Band of Mohican Indians Announcing the IPEC PSDAR Public Meeting on August 18, 2021 ML21225A4252021-08-0909 August 2021 Email from NRC to the Oneida Nation of Wisconsin Announcing the IPEC PSDAR Public Meeting on August 18, 2021 ML21225A3142021-08-0606 August 2021 Email from NRC to the Oneida Indian Nation Announcing the IPEC PSDAR Public Meeting on August 18, 2021 ML21225A4402021-08-0606 August 2021 Email from NRC to the Onondaga Nation of Wisconsin Announcing the IPEC PSDAR Meeting on August 18, 2021 ML21225A5352021-08-0606 August 2021 Email from NRC to the Tonawanda Band of Seneca Announcing the IPEC PSDAR Public Meeting on August 18, 2021 ML21225A5462021-08-0606 August 2021 Email from NRC to the St. Regis Mohawk Tribe Announcing the IPEC PSDAR Public Meeting on August 18, 2021 ML21266A2942021-07-25025 July 2021 E-mail from Paul Blanch to NRC (N. Sheehan, D. Screnci) Public Comments to NRC, Indian Point Post-Shutdown Decommissioning Activities Report Public Meeting, July 29, 2021 ML21197A2002021-07-16016 July 2021 (E-mail 7/16/2021) NRC Staff Assessment and RAI Closeout HDI Fleet Decommissioning Quality Assurance Program and Indian Point Energy Center Quality Assurance Program Manual 2024-02-01
[Table view] |
Text
viIauz1-11 -I.- ru2 flAJII I'1I MI vpudIu ivl WauI~ rayq Lfla ,IjuicuitrvisaII ~ uaLPP 100OU~r roqu II From: Brian McDermott To: Adam Stiebeling; Alela Salame-Alfie; Barbara Youngberg; C.J. Miller; Daniel Greeley; dleach@3ntergy.com; Dominick Greene; Geri Shapiro; Jack Spath; James Baranski; Paul Eddy; Peter Feroe; Robert Bondi; Steve Gross; Tony Sutton Date: Wed, Nov 30, 2005 11:46 AM
Subject:
FYI: Forthcoming Update to NRC Web Page on Indian Point Spent Fuel Pool Issues Attached for your information is a status update on the Indian Point 2 Spent Fuel Pool investigation that will be posted to the NRC's Web Page in the next day or so. Ifyou have any questions, please feel free to give me a call or raise your questions during our next conference call - tomorrow, Thursday 1211 at 3:30 p.m.
The existing NRC Web Page on the Indian Point 2 Spent Fuel Pool and tritium contamination can be found at:
http://wwN.nrc.pov/reactors/Plant-soecific-itemslindian-ooint-issues.html Regards, Brian Brian J. McDermott, Chief, Projects Branch 2 U.S. Nuclear Regulatory Commission - Region I 475 Allendale Road King of Prussia, PA 19406 ork: 610-337-5233 Cell _:
&M*
ax: E 0-337-5349 bjm nrc.gov CC: John Boska; John White; Raeann Shane Information inthis record was deleted inaccordance withthe Freedom of lnmnation Act exemptons _
FDIA. =L-M
!2)
.vte3IIlJU.2VV j~sjuuv i a uvar raye Mail Envelope Properties (438DD75F.20F: 12: 55450)
Subjecit: FYI: Forthcoming Update to NRC Web Page on Indian Point Spent Fuel Pool Issues Creation Date: Wed, Nov 30,2005 11:46 AM From: Brian McDermott Created By: BJM@nrc.gov Recipients Action Date & Time aol.com Transferred 11/30 11:46 AM GeriShapiro (Geri Shapiro) bestweb.net Transferred 11/30 11:47 AM Abs]?cbes (Adam Stiebeling) co.orange.ny.us Transferred 11/30 11:47 AM dgreene (Dominick Greene)
SGross (Steve Gross) co.rockland.ny.us Transferred 11/30 11:47 AM greeleyd (Daniel Greeley) mill -rc (C.J. Miller) dps.stal:e.ny.us Transferred 11/30 11:47AM pde (Paul Eddy) entergy.com Transferred 11/30 11:47 AM dleach (dleach@entergy.com) gw.dec.state.ny.us Transferred 11/30 11:47AM bayoungb (Barbara Youngberg) health. ;tate.ny.us Transferred 11/30 11:47 AM asa0l. (Alela Salame-Alfie) mail.house.gov Transferred 11/30 11:47 AM Petcr.Feroe (Peter Feroe) nrc.gov TWGWPO02.HQGWDO01 Delivered 11/30 11:46 AM RMS2 CC (Raeann Shane) Opened 11/30 11:59 AM nrc.gov kplpo.KPDO Delivered 11/30 11:46 AM
.U ItI LOJ\
A. WVtUVv I. I11\\11
- --- ---- U raye e-JRi'l1 CC (John White) Opened 11/30 12:47 PM nrc.gov owf4_.po.OWFN_DO Delivered 11/30 11:46 AM JPB1 CC (John Boska) Opened 12/06 7:19 AM nyserda.org Transferred 11/30 11:47 AM jps (Jack Spath)
PutnamrCountyNY.com Transferred 11/30 11:47 AM Robrt.Bondi (Robert Bondi) semo.sltate.ny.us Transferred 11/30 11:47 AM james.baranski (James Baranski) westchestergov .com Transferred 11/30 11:47 AM aws I (Tony Sutton)
Post Office Delivered Route aol.com bestweb.net co.orange.ny.us co.rockland.ny.us dps.state.ny.us entergy.com gw.dec.state.ny.u; health.state.ny.us mail.house.gov TWGWPO02.HQGWDO01 11/30 11:46 AM nrc.gov kpl.pD.KPLDO 11/30 11:46 AM nrc.gov owf4,_po.OWFN_DO 11/30 11:46 AM. nrc.gov nyserda.org PutnamCountyNY.com semo.state.ny.us westchestergov.com Files SiU 5e Date & Time MESSAGE 20A Wednesday, November 30, 2005 11:46 AM NRC VebPageUpdatel 1-30-05.pdf 15798 Wednesday, Noverr.ber 30, 2005 11:44 AM Options Auto ]Delete: No
S*v raycts-!
Expiration Date: None Notify Recipients: No Priority: High Reply Requested: No Return Notification: None Concealed
Subject:
No Security: Standard To Be Delivered: Immediate Status Tracking: All Information
On-going Activities; 11/29/2005 Unit 2 spent Fuel Pool: Entergy has completed visual examination and video taping of about 50% of the spent fuel pool liner surface in an effort to identify locations of potential leakage.
This represents all the surfaces that can be accessed with the currently available video camera equipment. Stored spent fuel in portions of the pool prevent full examination with currently available video equipment. Accordingly, Entergy has informed the NRC that it is investigating the use of other video equipment to affect more complete examination of the pool liner. Divers physically examined three locations of interest with a vacuum box to determine if leakage wEas present., however, in each case, leakage was not positively detected. Notwithstanding, Entergy is examining methods to apply an underwater coating to these locations to assure these areas of interest remain leak-tight.
The leak rate from the previously identified cracks in the spent fuel pool concrete wall is current y about 10 to 25 milliliters per day. Previously, leakage was measured to be about 1)300 to 150C milliliters per day. Entergy is investigating the cause of the decreased leak rate.
Monitoring Wells: Entergy has completed drilling of one of nine wells currently planned in its initial effort to characterize groundwater flow and the on-site tritium contamination. Tritium concentration in this well (MW-30, located in the Unit 2 Fuel Handling Building, in the excavated area adjacent to the Unit 2 Spent Fuel Pool, i.e., within 5 feet of the pool) ranged as high as 6 E-4 uCi/ml. For comparison, the EPA Drinking Water standard for tritium is 20000 pCVL, i.e., 2 E-5 uCi/ml. Drilling activities for the remaining initial wells are in progress. Entergy informed the NRC that additional wells will be constructed, as necessary, to characterize the tritium contamination.
Unit 1 Spent Fuel Pool Conditions: Entergy is continuing efforts to monitor and investigate the leakage from the Unit 1 Spent Fuel Pool system. Entergy reports that the information gathered to-date from water inventory balance activities and tritium measurements continue to indicate that the Unit I curtain drain and sphere foundation sump systems effectively capture the leakage from the Unit 1 spent fuel pool systems. Currently, Entergy is investigating data that suggests that more tritium activity, than has been attributed to Unit I spent fuel pool system leakage, is being captured within the Unit 1 drain system. Notwithstanding the investigation of the data, all leakage from the Unit I drain system continues to be processed and released as a monitored liquid effluent discharge in accordance with NRC regulatory requirements; and radiological effluent discharges continue to be a faction of NRC regulatory limits.