April 18, 2006
Paul D. Hinnenkamp
Vice President - Operations
Entergy Operations, Inc.
River Bend Station
5485 US Highway 61N
St. Francisville, LA 70775
SUBJECT:
ACKNOWLEDGMENT OF RECEIPT OF DENIAL OF NONCITED VIOLATION
IN NRC INSPECTION REPORT 05000458/2005005
Dear Mr. Hinnenkamp:
Thank you for your letter dated March 24, 2006, in response to our February 13, 2006, letter
and integrated inspection report. In your letter you contested one Green noncited violation
concerning implementation of Technical Specification (TS) 3.4.1.A, Condition A, required
Action A.1. The NRC inspection report concluded that a Green noncited violation of TS
Action 3.4.1.A.1 occurred when River Bend Station failed to restore compliance with Limiting
Condition for Operation (LCO) 3.4.1 or shut down one reactor recirculation loop within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />
of determining the reactor recirculation loop flow mismatch was greater than 5 percent at power
with greater than 70 percent rated core flow. Entergys position is that River Bend Station
complied with the requirements of TS 3.4.1; therefore, a violation did not occur. You have
requested that the NRC reconsider our conclusion and find that a violation of TS 3.4.1 did not
occur.
The NRC is reviewing your request and will inform you of the results of our review by separate
correspondence.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and
your response (if any) will be made available electronically for public inspection in the NRC
Public Document Room or from the Publicly Available Records (PARS) component of the
NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at
http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Kriss M. Kennedy, Chief
Project Branch C
Division of Reactor Projects
Entergy Operations, Inc.
-2-
Docket: 50-458
License: NPF-47
cc:
Senior Vice President and
Chief Operating Officer
Entergy Operations, Inc.
P.O. Box 31995
Jackson, MS 39286-1995
Vice President
Operations Support
Entergy Operations, Inc.
P.O. Box 31995
Jackson, MS 39286-1995
General Manager
Plant Operations
Entergy Operations, Inc.
River Bend Station
5485 US Highway 61N
St. Francisville, LA 70775
Director - Nuclear Safety
Entergy Operations, Inc.
River Bend Station
5485 US Highway 61N
St. Francisville, LA 70775
Wise, Carter, Child & Caraway
P.O. Box 651
Jackson, MS 39205
Winston & Strawn LLP
1700 K Street, N.W.
Washington, DC 20006-3817
Manager - Licensing
Entergy Operations, Inc.
River Bend Station
5485 US Highway 61N
St. Francisville, LA 70775
Entergy Operations, Inc.
-3-
The Honorable Charles C. Foti, Jr.
Attorney General
Department of Justice
State of Louisiana
P.O. Box 94005
Baton Rouge, LA 70804-9005
H. Anne Plettinger
3456 Villa Rose Drive
Baton Rouge, LA 70806
Bert Babers, President
West Feliciana Parish Police Jury
P.O. Box 1921
St. Francisville, LA 70775
Michael E. Henry, State Liaison Officer
Department of Environmental Quality
Permits Division
P.O. Box 4313
Baton Rouge, LA 70821-4313
Brian Almon
Public Utility Commission
William B. Travis Building
P.O. Box 13326
1701 North Congress Avenue
Austin, TX 78711-3326
Entergy Operations, Inc.
-4-
Electronic distribution by RIV:
Regional Administrator (BSM1)
DRP Director (ATH)
DRS Director (DDC)
DRS Deputy Director (RJC1)
Senior Resident Inspector (PJA)
Branch Chief, DRP/C (KMK)
Senior Project Engineer, DRP/C (WCW)
Team Leader, DRP/TSS (RLN1)
RITS Coordinator (KEG)
M. Vasquez, ACES (GMV)
OEMAIL
SUNSI Review Completed: __kmk_ ADAMS: : Yes
G No Initials: __kmk_
- Publicly Available G Non-Publicly Available G Sensitive
- Non-Sensitive
R:\\_REACTORS\\_RBS\\2005\\RB2005-05AK.wpd
DAISY 33-06
RIV:SPE:DRP/C
C:DRP/C
WCWalker;df
KMKennedy
/RA/
/RA/
4/18/06
4/18/06
OFFICIAL RECORD COPY
T=Telephone E=E-mail F=Fax