E-mail from B. Wittick of USNRC to Various, Regarding IPEC Isfi Status Teleconference
ML060950202
Person / Time
Site: Indian Point  Entergy icon.png
Issue date: 04/13/2005
From: Brian Wittick
NRC Region 1
To: Peter Habighorst, Hall J, Hinrichs G, Thomas Hipschman, Diane Jackson, Robert Lewis, Long C, Brian Mcdermott, Milano P, Schwartz G
NRC/EDO
References
FOIA/PA-2006-0020
Download: ML060950202 (4)


Text

!riitu,3iier Lully - Ircu l;i:ro ,)I I uz> I tLJI'INrtrI~'tZ4L~t Page 1 From: Brian Wittick To: Brian McDermott; Christopher Long; Donald Jackson; Gary Hinrichs; Geoffrey Schwart:; James Randall Hall; Patrick Milano; Peter Habighorst; Robert Lewis; Thomas Hipschman Date: 4/13/05 9:10AM

Subject:

IPEC ISFSI STATUS TELECONFERENCE The subject teleconference h s been scheduled for Tuesday, 19 April at 1000. The conference phone no.

is: 800-638-8081; passcode i)_

Request all addees provide desired agenda inputs and handout materials for consolidation and distribution NLT Thursday, April 16.

The teleconference moderator will be: Patrick Milano from NRC HQ (301) 415-1457.

Attached please find preliminary information on the subject (1 Word, 1 WPD and 4 PPT files) provided by Geoffrey Schwartz of IPEC for your consideration.

Brian D. Wittick U.S. NR(C, Region I (610) 337-6968 "Maintairing Public Health, Safety, and Trustu CC: bdw2

  • Information In this record was deleted in accordance with the Fr edom of In'maDo Acexm Ati n m Pac-b Ms m+,&

0--,

-11MAUPIWI LV11Y - Ir-Ma U%_,0 0Kt:!U.UUV Page 1

  • IOILUitJIIt:fl LUII - IZCL, LJ.jO OiQU.UUL Page 1

-- EnteWgy Indian Point Energy Center Dry Cask Storage Project Geoff Schwartz, Senior Project Manager (914) 734-6684 Gary Hinrichs, Licensing Project Manager (914) 734-6690 John Skonieczny, P.E., Project Engineer (914) 827-7772 Dave Smith, QA and Scheduling Project Manager (914) 734-6691 Target Schedule as of April 1, 2005 Activitv Schedule (C)=Complete (IP)= In Progress Scoping studies Jan 02- Feb 03 (C)

Major design engineering Mar 03 - Sep 04 (C)

Replace Unit 2 Fuel Storage Building (FSB) loading bay floor Jan 04- Jul 06 (IP)

End modify FSB access roadway' Fabricate/install new Unit 2 spent fuel handling bridge crane Jan -Aug 04 (C)

F-abricate 110-ton singe-failure-proof gantry-cantilever crane Jun 03- Dec 04 (C)

Fabricate Low Profile Transporter Jan 04 - May 05 (IP)

Fabricate casks and ancillary equipment Apr 03 - Jun 06 (IP)

Construct equipment staging facility May 04 -Jun 06 (IP)

I:SFSI construction permitting process Jan 03- Sep 04 (C)

Construct ISFSI pad and security system Sep 04 - Jun 06 (IP)

Concrete pour - May 2005 Prepare draft 10CFR72.212 report, 10CFR50.68 analysis and Jun 03- Dec 05 (IP) exemption request or LAR, and gantry crane LAR Develop procedures and training Jun 03- Dec 05 (IP) issemble loading team Jun - Dec 05 Install 11 0-ton singe-failure-proof gantry-cantilever crane May 06 - Aug 06 And Low Profile Transporter system in FSB Site Training Apr 04 - Sep 06 (IP)

All licensing actions complete Sep 06 Operational demonstration (dry run) Sep - Oct 06 Commence cask loading Nov 06 I FSB physical modification work suspended Sep-Nov 2004 and Mar-May 2006 for Unit 2 refueling outages

hristopher LoQg - IPE-( DUS(: 4-05.ppt Page'1 hristopherLorjg IPkU

- L)CS4-05.ppt Page 1

-Entergy Indian Point Energy Center Dry Cask Storage Project Overview and Status April 2005

  • General License approach
  • Holtec cask system
  • Site modifications

- Engineering complete

- ISFSI pad construction 50% complete - rebar installation In progress, pour concrete early May

- Spent Fuel Building structural modifications 40% complete

- Licensing submittals, procedures and training development In progress

  • First cask loading campaign fall 2006
  • Proactive public outreach program 1

,mrisiopner Long - let't Lubi 4-Ub.ppT Page

.nristopner Long - ltu uUi 4-U*ppt Page 2 2

D'EIndian Point Energy Center Dry Cask Storage Project Accomplishments

"~Energy2003-04

  • Designed Independent Spent Fuel Storage Installation (ISFSI) pad and electrlcallsecurity systems
  • Designed ISFSI staging facility to be used for storage of empty casks and tools, and cask on-site assembly
  • Designed Unit 2 Fuel Storage Building (FSB) loading bay floor and access alleyway upgrade, Including embedded systems for gantry-cantilever crane and low profile transporter
  • Designed modifications to remove various Interferences in FSB
  • Developed and Implemented ISFSI permitting strategy
  • Obtained ISFSI construction permits
  • Cleared land and excavated 78-cask ISFSI pad, installed engineered fill (12,000 tons), commenced rebar Installation
  • Installed ISFSI equipment staging facility concrete pads
  • Installed 90% of Interference removal modifications In FSB, Including rerouting building exhaust ventilation to exterior
  • Removed FSB loading bay floor sla
  • Designed, fabricated and Installed new spent fuel handling bridge crane In FSB; used during 2R16 refueling outage to save dose and time
  • Designed, fabricated and tested Industry-unique 110-ton gantry-cantilever crane (in storage at crane vendor)
  • Fabricated gantry crane 100-ton counterweight system (in storage)
  • Fabricated six overpack casks (in storage at cask vendor)
  • Fabricated transfer cask (in storage at cask vendor)
  • Fabricated cask handling tools (in storage at cask vendor)
  • Fabricated vertical cask transport vehicle (crawler, In storage at cask vendor)
  • Fabricated 90% Industry-unique low profile cask transporter system
  • Inspected 300 spent fuel assemblies for qualification for Initial cask loading
  • Developed and Implemented Informational outreach program
  • Developed and submitted License Amendment Request for gantry crane Developed cask loading procedures and training and accomplished training for Engineering Department 2