MONTHYEARML24137A1882024-05-16016 May 2024 Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - NRC Presentation Slides ML24100A7672024-04-11011 April 2024 Meeting Slides - Preapplication with Constellation on Planned Fleet Alternative Request to Adopt OMN-2 ML24089A2612024-04-0909 April 2024 Slides - Constellation - Pre-Application Regarding Hooded Masks 4/9/2024 Meeting Slides (L-2024-LLM-0041) ML24029A1742024-01-30030 January 2024 Constellation Pre-Application January 30, 2024, Meeting Slides - Proposed Alternative to Utilize Code Case N-932, Alternative Requirements for Acceptance of Containment Base Metal Corrosion or Erosion ML23317A0712023-11-14014 November 2023 NRC Pre-Submittal Meeting on November 14th, 2023 - TSTF-591 and Selected 50.69 License Condition Updates (EPID L-2023-LLM-0098) (Slides) ML23255A1042023-08-11011 August 2023 Slides - Constellation - Pre-Application EP 9/18/2023 Draft CEG Presubmittal SG Performance Monitoring Plan Meeting Handout ML23157A0352023-06-0606 June 2023 Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - NRC Presentation Slides ML23053A1562023-02-23023 February 2023 NRC Presentation Slides for Public Meeting on February 23, 2023 - 10 CFR 50.69 Alternate Processes License Amendment Request Preliminary Partial Denial ML23076A2812023-02-23023 February 2023 Licensee Presentation on Pressure Boundary Process ML23076A2822023-02-23023 February 2023 Licensee Presentation on Defense-in-Depth Process ML23006A2572023-01-10010 January 2023 Digital Modernization Project Installation Support License Amendment Request and Exemption Request Presentation - January 10, 2023 (EPID L-2022-LRM-0099) (Slides) ML22347A1532022-12-13013 December 2022 Public Meeting Presentation, December 15, 2022 Di&C License Amendment Request ML22319A0012022-11-14014 November 2022 Constellation Energy Generation, Llc'S Presentation for November 10, 2022 Public Meeting with NRC ML22312A4402022-11-10010 November 2022 Public Meeting with Constellation About Acceptance Review: Status of NRC Staff'S Acceptance Review of the Limerick Digital Instrumentation and Controls License Amendment Request ML22249A0972022-09-0808 September 2022 Constellation'S Open Presentation for September 8, 2022 Partially Closed Public Meeting ML22250A4372022-09-0808 September 2022 NRC Staff'S Presentation for September 8, 2022 Partially Closed Public Meeting with Constellation - Review Planning and Tentative Review Timeline ML22249A2202022-09-0606 September 2022 Constellation'S Non-Proprietary Presentation for Limerick Generating Station Digital Modernization Project LAR Pre-submittal Meeting September 8, 2022 ML22164A8082022-06-13013 June 2022 Westinghouse, Presentation GLIMM-RPS-PM-L1-000008, Revision 0 ML22153A3602022-06-0909 June 2022 Constellation'S Presentation for June 9, 2022 Public Meeting About Limerick Generating Station Digital Modernization Project ML22187A0652022-06-0808 June 2022 Joint Annual Assessment Meeting for Pa/Md/Nj/Ny Nuclear Power Plants - NRC Presentation Slides ML22103A2542022-04-19019 April 2022 Draft Request for Additional Information ML22076A1942022-03-23023 March 2022 Constellation Presentation March 23, 2022 NRC Di_C Workshop ML22080A1522022-03-21021 March 2022 Non-Proprietary Presentation for March 31, 2022 Pre-Submittal Meeting with Constellation Energy Generation, LLC Regarding Planned Digital Modernization License Amendment Request for Limerick Generating Station, Units 1 and 2 ML22010A0692022-01-10010 January 2022 Jan 11 2022 LGS Digital Modernization Pre-submittal Meeting Slides ML21335A0772021-12-0707 December 2021 Dec 07 2021 LGS Digital Modernization Pre-submittal Meeting Slides ML21294A3692021-11-15015 November 2021 Summary of October 6, 2021, Public Observation Meeting with Exelon Generation Company, LLC Proposed License Amendment Request to Modify Emergency Diesel Generator and Emregency Core Cooling System Surveillance Requirements ML21314A4472021-11-10010 November 2021 Slides for Presubmittial Meeting for Proposed Alternative to Adopt ASME Code Case N-921 to Extend the Inservice Inspection Interval ML21278A5452021-10-20020 October 2021 Digital Modernization Project LAR Pre-submittal Meeting Presentation Slides October 20, 2021 ML21174A0852021-06-23023 June 2021 Digital Modernization Project LAR Pre-submittal Meeting ML21165A1942021-06-16016 June 2021 Joint Annual Assessment Meeting for Pa/Md/Nj/Ny Nuclear Power Plants - Webinar Presentation ML21165A2882021-06-16016 June 2021 Joint Annual Assessment for Pa/Md/Nj/Ny Nuclear Power Plants - Webinar Presentation (Updated) ML21063A1192021-03-0404 March 2021 Digital Modernization Project LAR Pre-submittal Meeting - March 16, 2021 (EPID L-2020-LRM-0041) (Slides) ML21049A3102021-02-19019 February 2021 CFR 50.69 Alternative Categorization LAR ML21034A6032021-02-0303 February 2021 External Presentation Am Connelly_ISG-6 Workshop Presentation ML20261G7322020-09-16016 September 2020 Pre-Submittal Slides Extend 120-month Isi/Ist Interval Under 50.55a ML20178A4202020-06-30030 June 2020 NEI Slides for June 30, 2020, Public Meeting on COVID-19 Response ML20175A8722020-06-23023 June 2020 Risk-Informed Inservice Inspection - U.S Nuclear Regulatory Commission (NRC) - Four Element Risk-Informed Approach ML20170B0212020-06-23023 June 2020 NRC Pre-Submittal Meeting Byron Unit 2 One-Time Deferral of Reactor Pressure Vessel Head Penetration Nozzle (Rpvhpn) Inspections ML20169A5592020-06-16016 June 2020 Steam Generator License Amendment Request Pre-Submittal Meeting (NRC) - Byron Unit 2 LAR for One-Time Deferral of Steam Generator Inspections (Rev 1) ML20163A6552020-06-16016 June 2020 6-16-20 Byron Unit 2 Steam Generator License Amendment Request Pre-Submittal Meeting (NRC) - Byron Unit 2 LAR for One-Time Deferral of Steam Generator Inspections ML20168A3192020-06-15015 June 2020 Joint Annual Assessment Meeting for Pa/Md Power Plants - Webinar Presentation ML20162A0192020-06-10010 June 2020 NRC Staff Presentation for June 12, 2020, Public Pre-Application Meeting: ISG-06 Alternate Review Process Lessons Learned from Pre-Application Meetings ML20160A0532020-06-0808 June 2020 Digital Modernization Project LAR - Presubmittal Meeting - NRC Presubmittal Meeting Telecon June 12, 2020 ML19318F9512019-11-20020 November 2019 Presentation Slides for November 20, 2019, Pre-Application Meeting - Request for Revision to Quality Assurance Program Internal Audit Frequency ML19317C9952019-11-12012 November 2019 In-Service Testing Supplemental Position Indication Relief Request NRC Pre-Application Meeting November 18, 2019 ML19157A0542019-06-0606 June 2019 Joint Annual Assessment Meeting (Webinar) for Pennsylvania Power Plants - NRC Presentation Slides ML19161A2572019-06-0404 June 2019 BWR Fleet Msv/Srv - Testing Frequency Relief Request NRC Pre-Application Meeting June 4, 2019 ML19151A6602019-05-31031 May 2019 BWR Fleet Mssv/Srv Testing Frequency Relief Request NRC Pre-Application Meeting June 4, 2019 ML19022A2002019-01-23023 January 2019 Request for Use of ASME Code Case N-879 for Exelon Nuclear Power Plants ML18347B3142018-12-19019 December 2018 Bwrvip/Asme Relief Request Discussion December 19, 2018 2024-05-16
[Table view] Category:Slides and Viewgraphs
MONTHYEARML24249A3092024-09-0606 September 2024 September 6, 2024, Public Meeting Related to Digital Instrumentation and Control Amendment Slides ML24137A1882024-05-16016 May 2024 Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - NRC Presentation Slides ML24100A7672024-04-11011 April 2024 Meeting Slides - Preapplication with Constellation on Planned Fleet Alternative Request to Adopt OMN-2 ML24089A2612024-04-0909 April 2024 Slides - Constellation - Pre-Application Regarding Hooded Masks 4/9/2024 Meeting Slides (L-2024-LLM-0041) ML24029A1742024-01-30030 January 2024 Constellation Pre-Application January 30, 2024, Meeting Slides - Proposed Alternative to Utilize Code Case N-932, Alternative Requirements for Acceptance of Containment Base Metal Corrosion or Erosion ML23317A0712023-11-14014 November 2023 NRC Pre-Submittal Meeting on November 14th, 2023 - TSTF-591 and Selected 50.69 License Condition Updates (EPID L-2023-LLM-0098) (Slides) ML23255A1042023-08-11011 August 2023 Slides - Constellation - Pre-Application EP 9/18/2023 Draft CEG Presubmittal SG Performance Monitoring Plan Meeting Handout ML23157A0352023-06-0606 June 2023 Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - NRC Presentation Slides ML23053A1562023-02-23023 February 2023 NRC Presentation Slides for Public Meeting on February 23, 2023 - 10 CFR 50.69 Alternate Processes License Amendment Request Preliminary Partial Denial ML23076A2812023-02-23023 February 2023 Licensee Presentation on Pressure Boundary Process ML23076A2822023-02-23023 February 2023 Licensee Presentation on Defense-in-Depth Process NEI 99-01, Slides - Constellation - Pre-Application EP 2/23/2023 Meeting Slides2023-02-21021 February 2023 Slides - Constellation - Pre-Application EP 2/23/2023 Meeting Slides ML23006A2572023-01-10010 January 2023 Digital Modernization Project Installation Support License Amendment Request and Exemption Request Presentation - January 10, 2023 (EPID L-2022-LRM-0099) (Slides) ML22347A1532022-12-13013 December 2022 Public Meeting Presentation, December 15, 2022 Di&C License Amendment Request ML22319A0012022-11-14014 November 2022 Constellation Energy Generation, Llc'S Presentation for November 10, 2022 Public Meeting with NRC ML22250A4372022-09-0808 September 2022 NRC Staff'S Presentation for September 8, 2022 Partially Closed Public Meeting with Constellation - Review Planning and Tentative Review Timeline ML22249A0972022-09-0808 September 2022 Constellation'S Open Presentation for September 8, 2022 Partially Closed Public Meeting ML22249A2202022-09-0606 September 2022 Constellation'S Non-Proprietary Presentation for Limerick Generating Station Digital Modernization Project LAR Pre-submittal Meeting September 8, 2022 ML22195A2172022-07-12012 July 2022 D3 Audit Open Items List (Non-Proprietary) (07-12-22)_redacted ML22164A8082022-06-13013 June 2022 Westinghouse, Presentation GLIMM-RPS-PM-L1-000008, Revision 0 ML22153A3602022-06-0909 June 2022 Constellation'S Presentation for June 9, 2022 Public Meeting About Limerick Generating Station Digital Modernization Project ML22187A0652022-06-0808 June 2022 Joint Annual Assessment Meeting for Pa/Md/Nj/Ny Nuclear Power Plants - NRC Presentation Slides ML22076A1942022-03-23023 March 2022 Constellation Presentation March 23, 2022 NRC Di_C Workshop ML22080A1522022-03-21021 March 2022 Non-Proprietary Presentation for March 31, 2022 Pre-Submittal Meeting with Constellation Energy Generation, LLC Regarding Planned Digital Modernization License Amendment Request for Limerick Generating Station, Units 1 and 2 ML22010A0692022-01-10010 January 2022 Jan 11 2022 LGS Digital Modernization Pre-submittal Meeting Slides ML21335A0772021-12-0707 December 2021 Dec 07 2021 LGS Digital Modernization Pre-submittal Meeting Slides ML21294A3692021-11-15015 November 2021 Summary of October 6, 2021, Public Observation Meeting with Exelon Generation Company, LLC Proposed License Amendment Request to Modify Emergency Diesel Generator and Emregency Core Cooling System Surveillance Requirements ML21314A4472021-11-10010 November 2021 Slides for Presubmittial Meeting for Proposed Alternative to Adopt ASME Code Case N-921 to Extend the Inservice Inspection Interval ML21278A5452021-10-20020 October 2021 Digital Modernization Project LAR Pre-submittal Meeting Presentation Slides October 20, 2021 ML21294A3792021-10-0606 October 2021 WCAP-17308 Implementation Licensing Amendment Request Pre-Submittal Meeting Presentation, October 6, 2021 ML21175A1732021-06-29029 June 2021 Digital Modernization Project LAR Pre-submittal Meeting ML21174A0852021-06-23023 June 2021 Digital Modernization Project LAR Pre-submittal Meeting ML21165A2882021-06-16016 June 2021 Joint Annual Assessment for Pa/Md/Nj/Ny Nuclear Power Plants - Webinar Presentation (Updated) ML21165A1942021-06-16016 June 2021 Joint Annual Assessment Meeting for Pa/Md/Nj/Ny Nuclear Power Plants - Webinar Presentation ML21162A3322021-06-11011 June 2021 BWR Fleet Relief Request Associated with RPV Instrument Nozzle Repairs ML21063A1192021-03-0404 March 2021 Digital Modernization Project LAR Pre-submittal Meeting - March 16, 2021 (EPID L-2020-LRM-0041) (Slides) ML21049A3102021-02-19019 February 2021 CFR 50.69 Alternative Categorization LAR ML21034A6032021-02-0303 February 2021 External Presentation Am Connelly_ISG-6 Workshop Presentation ML20261G7322020-09-16016 September 2020 Pre-Submittal Slides Extend 120-month Isi/Ist Interval Under 50.55a ML20178A4202020-06-30030 June 2020 NEI Slides for June 30, 2020, Public Meeting on COVID-19 Response ML20170B0212020-06-23023 June 2020 NRC Pre-Submittal Meeting Byron Unit 2 One-Time Deferral of Reactor Pressure Vessel Head Penetration Nozzle (Rpvhpn) Inspections ML20175A8722020-06-23023 June 2020 Risk-Informed Inservice Inspection - U.S Nuclear Regulatory Commission (NRC) - Four Element Risk-Informed Approach ML20163A6542020-06-18018 June 2020 2020 NRC Annual Assessment Webinar Presentation - Pennsylvania and Maryland Facilities (Beaver Valley, Calvert Cliffs, Limerick, Peach Bottom, Susquehanna) ML20163A6552020-06-16016 June 2020 6-16-20 Byron Unit 2 Steam Generator License Amendment Request Pre-Submittal Meeting (NRC) - Byron Unit 2 LAR for One-Time Deferral of Steam Generator Inspections ML20169A5592020-06-16016 June 2020 Steam Generator License Amendment Request Pre-Submittal Meeting (NRC) - Byron Unit 2 LAR for One-Time Deferral of Steam Generator Inspections (Rev 1) ML20168A3192020-06-15015 June 2020 Joint Annual Assessment Meeting for Pa/Md Power Plants - Webinar Presentation ML20162A0192020-06-10010 June 2020 NRC Staff Presentation for June 12, 2020, Public Pre-Application Meeting: ISG-06 Alternate Review Process Lessons Learned from Pre-Application Meetings ML20160A0532020-06-0808 June 2020 Digital Modernization Project LAR - Presubmittal Meeting - NRC Presubmittal Meeting Telecon June 12, 2020 ML19304A8752019-11-0505 November 2019 Presentation Slides for Limerick/Nrc Pre-Submittal Meeting (Technical Specification 4.05 License Amendment Request) - November 5, 2019 ML19157A0542019-06-0606 June 2019 Joint Annual Assessment Meeting (Webinar) for Pennsylvania Power Plants - NRC Presentation Slides 2024-09-06
[Table view] |
Text
Limerick Generating Station Annual Assessment Meeting Reactor Oversight Program - CY 2005 Nuclear Regulatory Commission - Region I King of Prussia, Pennsylvania April 20, 2006
Purpose of Todays Meeting z A public forum for discussion of the licensees performance z NRC will address the licensee performance identified during the assessment period z Exelon will respond to the information in the letter and inform the NRC of new or existing programs to maintain or improve their performance
Agenda z Introduction z Review of Reactor Oversight Process z National Summary of Plant Performance z Discussion of Plant Performance Results z Licensee Response and Remarks z NRC Closing Remarks z Break z NRC available to address public questions
NRC Representatives z James Trapp, Branch Chief
- (610) 337-5186 z Samuel Hansell, Senior Resident Inspector
- (610) 327-1344 z Carey Bickett, Resident Inspector
- (610) 327-1344
Region I Organization Samuel J. Collins Regional Administrator Marc L. Dapas Deputy Regional Administrator Brian E. Holian A. Randolph Blough Director Division of Reactor Projects Director Division of Reactor Safety David C. Lew Marsha K. Gamberoni Deputy Director Deputy Director James M. Trapp Regional Specialists Branch Chief Project Engineers Cheryl Khan Thomas Setzer Susquehanna Limerick Peach Bottom Resident Inspectors Resident Inspectors Resident Inspectors Alan Blamey Samuel Hansell Fred Bower Frederick Jaxheimer Carey Bickett Daniel Schroeder
NRC Performance Goals z Safety: Ensure protection of the public health and safety and the environment z Security: Ensure the secure use and management of radioactive materials z Openness: Ensure openness in our regulatory process z Effectiveness: Ensure that NRC actions are effective, efficient, realistic, and timely z Management: Ensure excellence in agency management to carry out the NRC strategic objective
Reactor Oversight Process Strategic Performance Areas Safety Cornerstones Baseline Inspection Performance Indicator Results Results Significance Significance Threshold Threshold Action Matrix Regulatory Response
Examples of Baseline Inspections z Equipment Alignment ~80 hrs/yr z Triennial Fire Protection ~200 hrs every 3 yrs z Operator Response ~125 hrs/yr z Emergency Preparedness ~80 hrs/yr z Rad Release Controls ~110 hrs every 2 yrs z Worker Radiation Protection ~90 hrs/yr z Corrective Action Program ~250 hrs every 2 yrs z Corrective Action Case Reviews ~60 hrs/yr
Significance Threshold Performance Indicators Green: Baseline Inspection White: Increased NRC oversight Yellow: Requires more NRC oversight Red: Requires more NRC oversight Inspection Findings Green: Very low safety issue White: Low to moderate safety issue Yellow: Substantial safety issue Red: High safety issue
Action Matrix Concept Licensee Regulatory Degraded Multiple/Rep. Unacceptable Response Response Cornerstone Degraded Performance Cornerstone Increasing Safety Significance Increasing NRC Inspection Efforts Increasing NRC/Licensee Management Involvement Increasing Regulatory Actions
National Summary of Plant Performance Status at End of CY 2005 Licensee Response 84 Regulatory Response 12 Degraded Cornerstone 4 Multiple/Repetitive Degraded Cornerstone 3 Unacceptable 0 Total 103
National Summary z Performance Indicator Results (at end of CY 2005)
Green 1850 White 4 Yellow 0 Red 0 z Total Inspection Findings (CY 2005)
Green 849 White 10 Yellow 1 Red 0
Limerick Inspection Activities (Jan 1 - Dec 31, 2005) z 4733 hours0.0548 days <br />1.315 hours <br />0.00783 weeks <br />0.0018 months <br /> of inspection related activities z 2 resident inspectors assigned to the site z ~11 regional inspector visits
- Included two team inspections (SSDI, EP Exercise Evaluation) z Unit 2 Refueling Outage
- February - March 2005
Limerick Units 1 & 2 Assessment Results (Jan 1 - Dec 31, 2005) z Operated safely throughout the Assessment Period z Licensee response column of the Action Matrix for all of 2005 (cornerstone objectives fully met) z Inspection Findings
- 4 findings of very low safety significance (Green)
- 3 findings were common to both units
- 1 finding associated with Unit 2 z NRC will conduct baseline inspections during the remainder of the cycle
Unit 1 - 4Q Performance Indicators z www.NRC.GOV/NRR/oversight/assess/index.html
- click on plant name on left side of page
Unit 2 - 4Q Performance Indicators z www.NRC.GOV/NRR/oversight/assess/index.html
- click on plant name on left side of page
Performance Indicator (PI) Example z www.NRC.GOV/NRR/oversight/assess/index.html
- click on plant name on left side of page, then on PI
Unit 1 - Inspection Results z www.NRC.GOV/NRR/oversight/assess/index.html
- click on plant name on left side of page
Unit 2 - Inspection Results z www.NRC.GOV/NRR/oversight/assess/index.html
- click on plant name on left side of page
Limerick Annual Assessment Summary January 1 - December 31, 2005 z Exelon operated Limerick Units 1 & 2 in a manner that protected public health and safety z Licensee response column of the Action Matrix (All cornerstone objectives were fully met) z NRC plans baseline inspections at Limerick for the remainder of the 2006 assessment period
Licensee Response and Remarks Contacting the NRC z Report an emergency
- (301) 816-5100 (call collect) z Report a safety concern:
- (800) 695-7403
- Allegation@nrc.gov z General information or questions
- www.nrc.gov
- Select What We Do for Public Affairs
Reference Sources z Reactor Oversight Process
- http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html z Public Electronic Reading Room
- http://www.nrc.gov/reading-rm.html z Public Document Room 800-397-4209 (Toll Free)