E-mail from G. Schwartz of Entergy to Various, Regarding Unit 2 Pool Wall Update
ML060930121
Person / Time
Site: Indian Point Entergy icon.png
Issue date: 10/03/2005
From: Schwartz G
Entergy Nuclear Operations
To: Axeison W, Comiotes J, Conroy P, Cox M, Dacimo F, Hinrichs G, Jones T, Leach D, Limpias O, Mayer D, Mcmullin K, Rubin P, Santis H, Schwartz G, Skonieczny J, Steets J, Ventosa J
- No Known Affiliation, Office of Nuclear Reactor Regulation
References
FOIA/PA-2006-0019
Download: ML060930121 (1)


Text

Cox, Mark From: Schwartz, Geoffrey Sent: Monday, October 03, 2005 3:42 PM To: Leach, Don; Dacimo, Fred; Rubin, Paul; Ventosa, John; Hinrichs, Gary; Comiotes, Jim; Mayer, Don; Conroy, Pat; Jones, T. R.; Limpias, Oscar; Steets, Jim; McMullin, Kathy; Axelson, William L; Santis, Hank; Skonieczny, John; Cox, Mark Cc: Schwartz, Geoffrey

Subject:

Unit 2 pool wall update 10/3/05 update.

  • Collected 2000 mL per 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> last three days. Concentrations were consistent with previous readings.
  • Samples from the 3 wells located within the Unit 2 PA taken 9/29 should return from off-site lab by Thursday.
  • Instructed D. Quinn to request proposal from Mass Testing Corp. for a mass balance calculation for water loss from pool from all possible means.
  • Excavation along the south wall continuing. FYI the ballast box foundation will be poured on the southwest side of the loading bay (opposite side from where the cracks are) tomorrow.
  • Proposal received today from Underwater Construction Corp. for camera inspection of accessible SFP liner weld seams, proposal is broken into options and is under review.
  • Draft white paper received from GZA regarding site hydrology and environmental monitoring recommendations, white paper under review.
  • NRC hydrology specialist is expected to visit IPEC next week. We will be preparing for his visit.