Florida Power and Light: Alleged Field Engineer Planner with Day & Zimmerman NPS Who Willfully Failed to Follow a Modification Package Revision Procedure (Office of Investigations Case Number 2-2005-019)
ML060880110
Person / Time
Site: Saint Lucie  NextEra Energy icon.png
Issue date: 03/28/2006
From: Joel Munday
NRC/RGN-II/DRP/RPB3
To: Stall J
Florida Power & Light Co
References
2-2005-019
Download: ML060880110 (4)


Text

March 28, 2006 Florida Power and Light Company ATTN:

Mr. J. A. Stall Senior Vice President - Nuclear and Chief Nuclear Officer P. O. Box 14000 Juno Beach, FL 33408-0420

SUBJECT:

FLORIDA POWER AND LIGHT: ALLEGED FIELD ENGINEER PLANNER WITH DAY & ZIMMERMANN NPS WHO WILLFULLY FAILED TO FOLLOW A MODIFICATION PACKAGE REVISION PROCEDURE (OFFICE OF INVESTIGATIONS CASE NUMBER 2-2005-019)

Dear:

Mr. Stall:

Enclosed for your information is the synopsis of the Nuclear Regulatory Commission (NRC)

Office of Investigations (OI) completed report regarding a field engineer planner who willfully failed to follow a modification package revision procedure at the St. Lucie Nuclear Plant.

OI determined that there was insufficient evidence to substantiate the allegation. We plan no further action with regard to this matter. Should you have any questions concerning this letter, please contact us.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Joel T. Munday, Chief Reactor Projects Branch 3 Division of Reactor Projects Docket Nos. 50-335, 50-389 License Nos. DPR-67, NPF-16

Enclosure:

Investigative Synopsis, OI Case No. 2-2005-019

SYNOPSIS This investigation was initiated by the Nuclear Regulatory Commission (NRC), Office of Investigations (OI), Region II (RII), on April 25, 2005, to determine whether a Field Engineer Planner with Day & Zimmermann NPS (DZ NPS) at Florida Power and Lights (FPL) St. Lucie Nuclear Plant willfully failed to follow a modification package revision procedure.

Based on the evidence developed during this investigation, OI:RIV did not substantiate that a Field Engineer Planner with DZ NPS at FPLs St. Lucie Nuclear Plant willfully failed to follow a modification package revision procedure.

OFFICE RII:EICS RII:DRP SIGNATURE CFE for SON NAME ODeMiranda SNinh DATE 03/28/2006 03/28/2006 3/ /2006 3/ /2006 3/ /2006 3/ /2006 3/ /2006 E-MAIL COPY?

YES NO YES NO YES NO YES NO YES NO YES NO YES NO