1 New England Coalitions Brief on the Legal Scope of [NEC] Contention 4," dated March 17, 2006 [sic].
March 27, 2006 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of
)
)
ENTERGY NUCLEAR VERMONT YANKEE,
)
Docket No. 50-271-OLA LLC and ENTERGY NUCLEAR
)
OPERATIONS, INC.
)
ASLBP No. 04-832-02-OLA
)
(Vermont Yankee Nuclear Power Station)
)
NRC STAFFS UNOPPOSED MOTION FOR A TWO-DAY EXTENSION OF TIME TO FILE ITS ANSWER TO NECS BRIEF ON NEC CONTENTION 4 Pursuant to 10 C.F.R. § 2.323(a), the NRC Staff (Staff) hereby requests a two-day extension of time in which to file its Answer to New England Coalitions [NECs] Brief on the Legal Scope of [NEC] Contention 4 (NECs Brief), filed by NEC on March 21, 2006. In support of this request, the Staff states as follows:
1.
NEC filed its Brief on March 21, 2006, setting forth its views on the legal standard at issue in NEC Contention 4,1 as required by the Licensing Board in its Order (Supplemental Schedule) dated March 14, 2006, as modified by the Boards Order (Granting Motion for Enlargement of Time Related to NEC Contention 4... ), dated March 23, 2006.
2.
In accordance with the Licensing Boards Orders, the Staffs Answer to NECs Brief is due to be filed by March 28, 2006. The Staff is currently preparing its Answer to NECs Brief, but due to the press of other matters, has found that it will require a limited extension of time of two days, until March 30, 2006, in which to complete and file its Answer.
3.
Counsel for the Staff has spoken with Counsel for the Licensee and NECs representative (Mr. Shadis) concerning this request. Counsel for the Licensee does not oppose the Staffs request; NECs representative does not oppose this request, with the understanding that the date for NECs filing of its reply to the Staffs Answer is also extended by two days, i.e.,
until April 6, 2006.
4.
The Staff submits that a grant of the instant request will not result in adverse impact to any party and will not unduly delay the conclusion of this proceeding.
Accordingly, the Staff respectfully requests a two-day extension of time, until March 30, 2006, in which to file its Answer to NECs Brief on the legal standard at issue in NEC Contention 4.
Respectfully submitted,
/RA/
Sherwin E. Turk Counsel for NRC Staff Dated at Rockville, Maryland this 27th day of March, 2006
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of
)
)
ENTERGY NUCLEAR VERMONT YANKEE
)
Docket No. 50-271-OLA LLC and ENTERGY NUCLEAR
)
OPERATIONS, INC.
)
ASLBP No. 04-832-02-OLA
)
(Vermont Yankee Nuclear Power Station)
)
CERTIFICATE OF SERVICE I hereby certify that copies of NRC STAFFS UNOPPOSED MOTION FOR A TWO-DAY EXTENSION OF TIME TO FILE ITS ANSWER TO NECS BRIEF ON NEC CONTENTION 4,"
in the above-captioned proceeding have been served on the following by deposit in the United States mail, first class; or as indicated by an asterisk (*), by deposit in the Nuclear Regulatory Commissions internal mail system; and by e-mail as indicated by a double asterisk (**), this 27th day of March, 2006.
Alex S. Karlin, Chair**
Administrative Judge Atomic Safety and Licensing Board Panel Mail Stop T-3F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 E-mail: ask2@nrc.gov Dr. Anthony J. Baratta**
Administrative Judge Atomic Safety and Licensing Board Panel Mail Stop T-3F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 E-mail: ajb5@nrc.gov Lester S. Rubenstein**
Administrative Judge Atomic Safety and Licensing Board Panel 4760 East Country Villa Drive Tucson, AZ 85718 E-mail: lesrrr@comcast.net Office of the Secretary**
ATTN: Rulemaking and Adjudications Staff Mail Stop: O-16C1 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 E-mail: HEARINGDOCKET@nrc.gov Office of Commission Appellate Adjudication*
Mail Stop: O-16C1 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Jonathan M. Rund, Esq.**
Law Clerk Atomic Safety and Licensing Board Panel Mail Stop: T-3F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 (E-mail: jmr3@nrc.gov)
Jered J. Lindsay, Esq.**
Law Clerk Atomic Safety and Licensing Board Panel Mail Stop: T-3F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 (E-mail: JJL5@nrc.gov)
Sarah Hofmann, Esq.**
Special Counsel Department of Public Service 112 State Street - Drawer 20 Montpelier, VT 05620-2601 E-mail: sarah.hofmann@state.vt.us Jay E. Silberg, Esq.**
Matias Travieso-Diaz, Esq.**
Pillsbury Winthrop Shaw Pittman, LLP 2300 N St., NW Washington, DC 20037-1128 E-mail: jay.silberg@pillsburylaw.com, and matias.travieso-diaz@pillsburylaw.com Anthony Z. Roisman, Esq.**
National Legal Scholars Law Firm 84 East Thetford Rd.
Lyme, NH 03768 E-mail: aroisman@nationallegalscholars.com John M. Fulton, Esq.
Assistant General Counsel Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Raymond Shadis**
Staff Technical Advisor New England Coalition P.O. Box 98 Edgecomb, ME 04556 E-mail: shadis@prexar.com, shadis@ime.net
/RA/
Sherwin E. Turk Counsel for NRC Staff