North Anna Inspection / Activity Plan 03/01/2006 - 09/30/2007 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 03/02/2006 10:37:37 Report 22 3
PSB1-RP
- RP BASELINE OCCUPATIONAL WK1 Baseline Inspections 03/13/2006 03/17/2006 1, 2 7112101 IP Access Control to Radiologically Significant Areas Baseline Inspections 03/13/2006 03/17/2006 1, 2 7112102 IP ALARA Planning and Controls Baseline Inspections 03/13/2006 03/17/2006 1, 2 7112202 IP Radioactive Material Processing and Transportation Baseline Inspections 03/13/2006 03/17/2006 1, 2 71151 IP Performance Indicator Verification 2
EB3-ISI
- U1 INSERVICE INSPECTION Baseline Inspections 03/20/2006 03/24/2006 1
7111108P IP Inservice Inspection Activities - PWR 1
EB3SGISI
- U1 SG ISI Baseline Inspections 03/20/2006 03/24/2006 1
7111108P IP Inservice Inspection Activities - PWR 3
PSB1-RP
- RP BASELINE OCCUPATIONAL WK2 Baseline Inspections 03/27/2006 03/31/2006 1, 2 7112101 IP Access Control to Radiologically Significant Areas Baseline Inspections 03/27/2006 03/31/2006 1, 2 7112102 IP ALARA Planning and Controls Baseline Inspections 03/27/2006 03/31/2006 1, 2 7112202 IP Radioactive Material Processing and Transportation Baseline Inspections 03/27/2006 03/31/2006 1, 2 71151 IP Performance Indicator Verification 1
EB3-HS
- HEAT SINK Baseline Inspections 05/01/2006 05/05/2006 1, 2 7111107B IP Heat Sink Performance 3
OL PREP
- INITIAL EXAM PREP Not Applicable 05/01/2006 05/05/2006 1
V23257 NORTH ANNA/MAY 2006 EXAM AT POWER FACILITIES 3
OL EXAM
- INITIAL EXAM WEEK 1 Not Applicable 05/22/2006 05/26/2006 1
V23257 NORTH ANNA/MAY 2006 EXAM AT POWER FACILITIES 3
OL EXAM
- INITIAL EXAM WEEK 2 Not Applicable 06/05/2006 06/09/2006 1
V23257 NORTH ANNA/MAY 2006 EXAM AT POWER FACILITIES 4
EB1-MODS
- MODIFICATIONS/10CFR50.59 Baseline Inspections 06/12/2006 06/16/2006 1, 2 7111102 IP Evaluation of Changes, Tests, or Experiments Baseline Inspections 06/12/2006 06/16/2006 1, 2 7111117B IP Permanent Plant Modifications 1
ISFSI-O
- 60855.1 - OPERATION OF AN ISFSI Other Routine 07/03/2006 07/07/2006 1
60855.1 IP Operation of an Independent Spent Fuel Storage Installation at Operating Plants 3
PS2-EP
- EP EXERCISE Baseline Inspections 12/04/2006 12/08/2006 1, 2 7111401 IP Exercise Evaluation Baseline Inspections 12/04/2006 12/08/2006 1, 2 7111404 IP Emergency Action Level and Emergency Plan Changes Baseline Inspections 12/04/2006 12/08/2006 1, 2 71151 IP Performance Indicator Verification 4
EB1-CDB
- COMPONENT DESIGN BASES INSPECTION Baseline Inspections 12/11/2006 12/15/2006 1, 2 7111121 IP Component Design Bases Inspection 6
EB1-CDB
- COMPONENT DESIGN BASES INSPECTION Baseline Inspections 01/08/2007 01/12/2007 1, 2 7111121 IP Component Design Bases Inspection This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Enclosure
North Anna Inspection / Activity Plan 03/01/2006 - 09/30/2007 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 03/02/2006 10:37:37 Report 22 6
EB1-CDB
- COMPONENT DESIGN BASES INSPECTION Baseline Inspections 01/22/2007 01/26/2007 1, 2 7111121 IP Component Design Bases Inspection Baseline Inspections 02/05/2007 02/09/2007 1, 2 7111121 IP Component Design Bases Inspection 1
EB3-ISI
- U2 INSERVICE INSPECTION Baseline Inspections 03/26/2007 03/30/2007 2
7111108P IP Inservice Inspection Activities - PWR 1
EB3SGISI
- U2 STEAM GENERATOR ISI Baseline Inspections 04/02/2007 04/06/2007 2
7111108P IP Inservice Inspection Activities - PWR 4
- PROBLEM IDENTIFICATION AND RESOLUTION Baseline Inspections 04/02/2007 04/06/2007 1, 2 71152B IP Identification and Resolution of Problems Baseline Inspections 04/16/2007 04/20/2007 1, 2 71152B IP Identification and Resolution of Problems 1
EB1-SUMP
- PWR CONTAINMENT SUMP BLOCKAGE TI (U-2)
Baseline Inspections 04/08/2007 04/13/2007 2
71111 IP Reactor Safety-Initiating Events, Mitigating Systems, Barrier Integrity 1
PSB1-RP
- RP PUBLIC PRE-INSP VISIT/ISFSI Baseline Inspections 05/14/2007 05/16/2007 1, 2 7112101 IP Access Control to Radiologically Significant Areas 4
PSB1-RP
- RP PUBLIC BASELINE INSPECTION Baseline Inspections 06/11/2007 06/15/2007 1, 2 7112101 IP Access Control to Radiologically Significant Areas Baseline Inspections 06/11/2007 06/15/2007 1, 2 7112103 IP Radiation Monitoring Instrumentation and Protective Equipment Baseline Inspections 06/11/2007 06/15/2007 1, 2 7112201 IP Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems Baseline Inspections 06/11/2007 06/15/2007 1, 2 7112203 IP Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control P Baseline Inspections 06/11/2007 06/15/2007 1, 2 71151 IP Performance Indicator Verification 1
PS2-EP
- EP INSP Baseline Inspections 08/06/2007 08/10/2007 1, 2 7111402 IP Alert and Notification System Testing Baseline Inspections 08/06/2007 08/10/2007 1, 2 7111403 IP Emergency Response Organization Augmentation Testing Baseline Inspections 08/06/2007 08/10/2007 1, 2 7111404 IP Emergency Action Level and Emergency Plan Changes Baseline Inspections 08/06/2007 08/10/2007 1, 2 7111405 IP Correction of Emergency Preparedness Weaknesses and Deficiencies Baseline Inspections 08/06/2007 08/10/2007 1, 2 71151 IP Performance Indicator Verification 1
EB3-ISI
- U1 INSERVICE INSPECTION Baseline Inspections 09/17/2007 09/21/2007 1
7111108P IP Inservice Inspection Activities - PWR 1
EB3SGISI
- U1 STEAM GENERATOR ISI Baseline Inspections 09/24/2007 09/28/2007 1
7111108P IP Inservice Inspection Activities - PWR 1
EB1-SUMP
- PWR CONTAINMENT SUMP BLOCKAGE TI (U-1)
Baseline Inspections 09/30/2007 10/05/2007 1
71111 IP Reactor Safety-Initiating Events, Mitigating Systems, Barrier Integrity This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.