Page 1 of 2 Watts Bar 03/02/2006 11:45:03 Inspection / Activity Plan Report 22 03/01/2006 - 09/30/2007 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type PSB1-RP - RP PUBLIC PRE-INSPECTION VISIT 1 1 IP 7112101 Access Control to Radiologically Significant Areas 04/11/2006 04/13/2006 Baseline Inspections PSB1-RP - RP PUBLIC BASELINE 4 1 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 05/08/2006 05/12/2006 Baseline Inspections 1 IP 7112201 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 05/08/2006 05/12/2006 Baseline Inspections 1 IP 7112203 Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control P 05/08/2006 05/12/2006 Baseline Inspections 1 IP 71151 Performance Indicator Verification 05/08/2006 05/12/2006 Baseline Inspections PS2 EP - EP EXERCISE 3 1 IP 7111401 Exercise Evaluation 06/05/2006 06/09/2006 Baseline Inspections OL PREP - INITIAL EXAM PREP 3 1 V23241 WATTS BAR/SEPTEMBER 2006 EXAM AT POWER FACILITIES 08/07/2006 08/11/2006 Not Applicable OL RQ - REQUAL INSPECTION 2 1 IP 7111111B Licensed Operator Requalification Program 08/14/2006 08/18/2006 Baseline Inspections PS2-EP - EP INSP 1 1 IP 7111402 Alert and Notification System Testing 09/04/2006 09/08/2006 Baseline Inspections 1 IP 7111403 Emergency Response Organization Augmentation Testing 09/04/2006 09/08/2006 Baseline Inspections 1 IP 7111404 Emergency Action Level and Emergency Plan Changes 09/04/2006 09/08/2006 Baseline Inspections 1 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 09/04/2006 09/09/2006 Baseline Inspections 1 IP 71151 Performance Indicator Verification 09/04/2006 09/09/2006 Baseline Inspections OL EXAM - INITIAL EXAM 3 1 V23241 WATTS BAR/SEPTEMBER 2006 EXAM AT POWER FACILITIES 09/05/2006 09/15/2006 Not Applicable EB3-ISI - U1 INSERVICE INSPECTION 1 1 IP 7111108P Inservice Inspection Activities - PWR 09/18/2006 09/22/2006 Baseline Inspections RP BR6 - UNIT 2 SYSTEMS LAY-UP INSPECTION 1 1 IP 92050 Review Of Quality Assurance For Extended Construction Delays 09/25/2006 09/29/2006 Other Routine EB1-SUMP - PWR CONTAINMENT SUMP BLOCKAGE TI (U-1) 2 1 IP 71111 Reactor Safety-Initiating Events, Mitigating Systems, Barrier Integrity 10/01/2006 10/06/2006 Baseline Inspections PSB1-RP - RP BASELINE OCCUPATIONAL & S/G REPL-WK1 2 1 IP 50001 Steam Generator Replacement Inspection 10/02/2006 10/06/2006 Other Routine 1 IP 7112101 Access Control to Radiologically Significant Areas 10/02/2006 10/06/2006 Baseline Inspections 1 IP 7112102 ALARA Planning and Controls 10/02/2006 10/06/2006 Baseline Inspections 1 IP 71151 Performance Indicator Verification 10/02/2006 10/06/2006 Baseline Inspections EB3SGRP - SG REPLACEMENT 3 1 IP 50001 Steam Generator Replacement Inspection 10/02/2006 10/06/2006 Other Routine 1 IP 50001 Steam Generator Replacement Inspection 10/23/2006 10/27/2006 Other Routine This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Enclosure

Page 2 of 2 Watts Bar 03/02/2006 11:45:03 Inspection / Activity Plan Report 22 03/01/2006 - 09/30/2007 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type EB3SGRP - SG REPLACEMENT 3 1 IP 50001 Steam Generator Replacement Inspection 10/30/2006 11/03/2006 Other Routine 1 IP 50001 Steam Generator Replacement Inspection 11/13/2006 11/17/2006 Other Routine PSB1-RP - RP BASELINE OCCUPATIONAL & S/G REPL WK2 1 1 IP 50001 Steam Generator Replacement Inspection 10/16/2006 10/20/2006 Other Routine 1 IP 7112101 Access Control to Radiologically Significant Areas 10/16/2006 10/20/2006 Baseline Inspections EB1-CDB - COMPONENT DESIGN BASES INSPECTION 6 1 IP 7111121 Component Design Bases Inspection 01/29/2007 02/02/2007 Baseline Inspections 1 IP 7111121 Component Design Bases Inspection 02/12/2007 02/16/2007 Baseline Inspections 1 IP 7111121 Component Design Bases Inspection 02/26/2007 03/02/2007 Baseline Inspections 1 IP 7111121 Component Design Bases Inspection 03/12/2007 03/16/2007 Baseline Inspections TFP - TFP INFO TRIP 5 1 IP 7111105T Fire Protection [Triennial] 05/08/2007 05/10/2007 Baseline Inspections PSB1-RP - RP OCCUPATIONAL BASELINE INSPECTION 3 1 IP 7112101 Access Control to Radiologically Significant Areas 05/21/2007 05/25/2007 Baseline Inspections 1 IP 7112102 ALARA Planning and Controls 05/21/2007 05/25/2007 Baseline Inspections 1 IP 7112202 Radioactive Material Processing and Transportation 05/21/2007 05/25/2007 Baseline Inspections 1 IP 71151 Performance Indicator Verification 05/21/2007 05/25/2007 Baseline Inspections TFP - TRIENNIAL FIRE PROTECTION INSPECTION 5 1 IP 7111105T Fire Protection [Triennial] 05/28/2007 06/01/2007 Baseline Inspections 1 IP 7111105T Fire Protection [Triennial] 06/11/2007 06/15/2007 Baseline Inspections PS2-EP - EP INSP 1 1 IP 7111402 Alert and Notification System Testing 06/04/2007 06/08/2007 Baseline Inspections 1 IP 7111403 Emergency Response Organization Augmentation Testing 06/04/2007 06/08/2007 Baseline Inspections 1 IP 7111404 Emergency Action Level and Emergency Plan Changes 06/04/2007 06/08/2007 Baseline Inspections 1 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 06/04/2007 06/08/2007 Baseline Inspections 1 IP 71151 Performance Indicator Verification 06/04/2007 06/08/2007 Baseline Inspections EB3-HS - HEAT SINK 1 1 IP 7111107B Heat Sink Performance 06/25/2007 06/29/2007 Baseline Inspections RPB6-PIR - BIENNIAL PI&R INSPECTION WEEK 1 4 1 IP 71152B Identification and Resolution of Problems 08/27/2007 08/31/2007 Baseline Inspections RPB6-PIR - BIENNIAL PI&R INSPECTION WEEK 2 4 1 IP 71152B Identification and Resolution of Problems 09/10/2007 09/14/2007 Baseline Inspections This report does not include INPO and OUTAGE activities.