ML060580544
ML060580544 | |
Person / Time | |
---|---|
Site: | Salem, Hope Creek |
Issue date: | 03/16/2004 |
From: | Meyer G NRC Region 1 |
To: | Lisamarie Jarriel, Miller H, Wiggins J NRC Region 1 |
References | |
FOIA/PA-2005-0194 | |
Download: ML060580544 (4) | |
Similar Documents at Salem, Hope Creek | |
---|---|
Category:E-Mail
MONTHYEARML24277A0812024-10-0303 October 2024
[Table view]NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form - Atlantic Sturgeon Collected on 10/02/2024 ML24269A0362024-09-24024 September 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Kemps Ridley Sea Turtle Collected on 9/24/2024 ML24253A1942024-09-0909 September 2024 NRR E-mail Capture - Final Eeeb RAI - Hope Creek Amendment to Revise TS to Change Surveillance Interval to Accommodate 24-Month Fuel Cycle ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 ML24248A0452024-09-0303 September 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Kemps Ridley Sea Turtle Collected on 9/3/2024 ML24240A2092024-08-27027 August 2024 NRR E-mail Capture - Acceptance Review - Hope Creek - Relief Request VR-04, SSW Rupture Disc Replacement ML24229A0422024-08-16016 August 2024 NRR E-mail Capture - Acceptance Review - Salem 1 and 2 - Implement Optimized ZIRLO Fuel Rod Cladding ML24229A0432024-08-16016 August 2024 NRR E-mail Capture - Acceptance Review - Salem 1 and 2 - Exemption from 10 CFR 50.46 and 10 CFR 50 Appendix K to Allow the Use of Optimized ZIRLO Fuel Rod Cladding ML24227A5092024-08-14014 August 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Kemps Ridley Sea Turtle Collected on 8/13/2024 ML24228A1942024-08-14014 August 2024 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form for a Live - Atlantic Sturgeon 8/14/2024 ML24197A1022024-07-15015 July 2024 NRR E-mail Capture - Acceptance Review - Hope Creek - Revise TS Lift Settings for Reactor Coolant System Safety Relief Valves ML24250A0562024-07-11011 July 2024 PSEG to NMFS, Regarding Processing of Fin Clips ML24219A2472024-07-0909 July 2024 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form - Shortnose Sturgeon 7/9/2024 ML24163A1632024-06-11011 June 2024 NRR E-mail Capture - Acceptance Review - Hope Creek - Revise TS to Change Surveillance Interval to Accommodate 24-Month Fuel Cycle ML24123A0522024-05-0101 May 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - One Deceased Sturgeon 4/30/2024 ML24106A0542024-04-12012 April 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Form - One Alive Atlantic Sturgeon 4/12/2024 ML24101A2192024-04-0909 April 2024 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form - Atlantic Sturgeon 4/8/24 ML24093A1222024-04-0101 April 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Form - One Atlantic Sturgeon 4/1/2024 ML24075A1862024-03-14014 March 2024 NRR E-mail Capture - (External_Sender) Biological Opinion Gar 2020-02842 - PSEG Salem and Hope Creek Generating Station Annual Incidental Take Report - 2023 ML24060A0492024-02-28028 February 2024 NRR E-mail Capture - Final Exhb RAI for Hope Creek, Salem 1 and 2 Amendment to Modify Exclusion Area Boundary ML24030A8432024-01-30030 January 2024 NRR E-mail Capture - (External_Sender) 2023 PSEG Sturgeon Pit Tag Data ML24016A1612024-01-10010 January 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Forms - Two Atlantic Sturgeon 1/9/2024 ML24002A7222023-12-29029 December 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - 2023 Annual Report - Inspection of the Circulating Water Intake Structure (Cwis) Trash Rack Bars ML24002A7242023-12-28028 December 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Form - Sturgeon 12/28/2023 ML23355A2732023-12-21021 December 2023 NRR E-mail Capture - (External_Sender) PSEG Response to Questions Associated with Supplement to Salem-Hope Creek Eab Reduction LAR ML24002A7252023-12-21021 December 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Shortnose Sturgeon 12/21/23 ML23346A0962023-12-0606 December 2023 NRR E-mail Capture - Reminder - Final Report - Completion of Required Additional Protocol (AP) Information in Accordance with the U.S. - IAEA Treaty Obligations ML23311A0792023-11-0101 November 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Atlantic Sturgeon Collected on 10/31/2023 ML23277A0482023-10-0404 October 2023 NRR E-mail Capture - 10/4/2023 Email: Acceptance Review - Hope Creek and Salem 1 and 2 - LAR to Modify Exclusion Area Boundary ML23277A0732023-09-29029 September 2023 NRR E-mail Capture - (External_Sender) 9/29/2023 Email from PSEG: Supplement to Proposed Amendment to PSEG Master Decommissioning Trust Amendment ML23226A0702023-08-11011 August 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Form for Sturgeon Collected on 8/10/2023 ML23226A0732023-08-10010 August 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Submittal of Necropsy Reports Regarding Sea Turtles Collected on 06/12/2022 ML23201A0132023-07-20020 July 2023 NRR E-mail Capture - Acceptance Review - Salem 1 and 2 - Permanent Extension of Type a and Type C Containment Leak Rate Test Frequencies ML23172A0982023-06-21021 June 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Kemps Ridley Sea Turtle Collected on 06/20/2022 ML23164A2062023-06-13013 June 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Kemps Ridley Sea Turtle Collected on 06/12/2023 ML24250A0572023-06-0606 June 2023 PSEG to NMFS, Request for Sturgeon Fin Clip Analysis Facilities ML23163A0442023-06-0606 June 2023 NRR E-mail Capture - (External_Sender) Biological Opinion GAR-2020-02842; FIN Clip Analysis Facilities ML23153A1552023-06-0202 June 2023 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form - Atlantic Sturgeon 6/1/2023 ML23151A6582023-05-31031 May 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Forms Sturgeon 5/30/2023 ML23137A2632023-05-17017 May 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Forms Sturgeon 5/16/2023 ML23135A0102023-05-11011 May 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report Sturgeon 5/11/2023 ML23129A7892023-05-0909 May 2023 NRR E-mail Capture - Acceptance Review - Hope Creek - Revise Trip and Standby Auto-Start Logic Associated with Safety Related HVAC Trains ML23136B2832023-05-0404 May 2023 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form - Atlantic Sturgeon 5/3/2023 ML23122A1982023-05-0202 May 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Forms for Atlantic Sturgeon 5/1/2023 ML23122A1672023-05-0202 May 2023 NRR E-mail Capture - Acceptance Review - Hope Creek and Salem 1 and 2 - Revise TS to Delete TS Section 5.5 - Meteorological Tower Location ML23117A2722023-04-17017 April 2023 NRR E-mail Capture - (External_Sender) Salem Generating STATION-INCIDENTAL Take of Atlantic Sturgeon Collected on 04/14/2023 ML23079A0032023-03-17017 March 2023 NRR E-mail Capture - Hope Creek, Salem 1 and 2 - Evacuation Time Estimate Review ML23065A0452023-02-23023 February 2023 NRR E-mail Capture - (External_Sender) Salem & Hope Creek Generating STATIONS-ANNUAL Incidental Take REPORT-STATION & REMP ML23033A0302023-02-0808 February 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report Sturgeon 1/24/2023 ML23010A2882023-01-10010 January 2023 NRR E-mail Capture - (External_Sender) Salem Generating STATION-INCIDENTAL Take of Atlantic Sturgeon Collected on 01/09/2023 2024-09-09 Category:Meeting Agenda MONTHYEARML24220A1002024-08-20020 August 2024
[Table view]August 20, 2024, PSEG Pre-Planning Meeting Slides for Salem Stretch Power Uprate Project PMNS20240996, Pre-planning Meeting to Discuss the Various Future License Amendment Requests for the Salem Power Uprate2024-08-0202 August 2024 Pre-planning Meeting to Discuss the Various Future License Amendment Requests for the Salem Power Uprate PMNS20240187, Meeting with PSEG Nuclear LLC to Discuss a Proposed Hope Creek Generating Station License Amendment Request to Change Surveillance Frequency from 18 Months to 24 Months2024-02-13013 February 2024 Meeting with PSEG Nuclear LLC to Discuss a Proposed Hope Creek Generating Station License Amendment Request to Change Surveillance Frequency from 18 Months to 24 Months PMNS20240186, Meeting with PSEG Nuclear LLC to Discuss a Proposed Hope Creek Generating Station License Amendment Request for Improved Technical Specification Conversion2024-02-13013 February 2024 Meeting with PSEG Nuclear LLC to Discuss a Proposed Hope Creek Generating Station License Amendment Request for Improved Technical Specification Conversion PMNS20231157, Pre-planning Meeting with PSEG Nuclear LLC to Discuss Future Amendments Regarding Integrated Technical Specification Conversion, 24-Month Fuel Cycle and Revise Safety Release Valve Setpoint to 1130 Psig2023-10-10010 October 2023 Pre-planning Meeting with PSEG Nuclear LLC to Discuss Future Amendments Regarding Integrated Technical Specification Conversion, 24-Month Fuel Cycle and Revise Safety Release Valve Setpoint to 1130 Psig PMNS20231042, Closed Meeting with PSEG Nuclear, LLC (PSEG) and Westinghouse Electric Company (Westinghouse) to Discuss Cobalt-60 Production at Salem Nuclear Generating Station (Salem)2023-09-14014 September 2023 Closed Meeting with PSEG Nuclear, LLC (PSEG) and Westinghouse Electric Company (Westinghouse) to Discuss Cobalt-60 Production at Salem Nuclear Generating Station (Salem) PMNS20230612, Pre-submittal Meeting with PSEG to Discuss the Amendment to Reduce Sites Exclusion Area Boundary2023-05-10010 May 2023 Pre-submittal Meeting with PSEG to Discuss the Amendment to Reduce Sites Exclusion Area Boundary ML22319A2432022-11-17017 November 2022 Stations - Nuclear Regulatory Commission: Threshold Determination Pre-submittal Meeting on November 17, 2022 (EPID L-2022-LRM-0090) (Slides) PMNS20221135, Public Meeting to Discuss Transfer of Ownership of Portions of the PSEG Nuclear Site2022-11-0303 November 2022 Public Meeting to Discuss Transfer of Ownership of Portions of the PSEG Nuclear Site PMNS20220509, Pre-Submittal Meeting with PSEG Nuclear, LLC to Discuss a License Amendment Request Regarding Emergency Diesel Generator Allowed Outage Time for Salem Nuclear Generating Station, Units 1 and 22022-05-10010 May 2022 Pre-Submittal Meeting with PSEG Nuclear, LLC to Discuss a License Amendment Request Regarding Emergency Diesel Generator Allowed Outage Time for Salem Nuclear Generating Station, Units 1 and 2 PMNS20211231, Pre-Application Meeting with Exelon Generation Company, LLC (Exelon) Regarding Extending Inservice Inspection Intervals2021-10-0505 October 2021 Pre-Application Meeting with Exelon Generation Company, LLC (Exelon) Regarding Extending Inservice Inspection Intervals PMNS20210302, Pre-Submittal Meeting with PSEG Nuclear LLC to Discuss Plans and Details of Upcoming License Amendment Request Regarding Changes to the Ultimate Heat Sink Technical Specifications for Hope Creek2021-03-17017 March 2021 Pre-Submittal Meeting with PSEG Nuclear LLC to Discuss Plans and Details of Upcoming License Amendment Request Regarding Changes to the Ultimate Heat Sink Technical Specifications for Hope Creek PMNS20210173, Pre-Submittal Meeting with PSEG Nuclear, LLC to Discuss Relief Requests to Adopt Code Cases N-878, N-879, and N-880 for Hope Creek Generating Station and Salem Nuclear Generating Station, Units 1 and 22021-02-18018 February 2021 Pre-Submittal Meeting with PSEG Nuclear, LLC to Discuss Relief Requests to Adopt Code Cases N-878, N-879, and N-880 for Hope Creek Generating Station and Salem Nuclear Generating Station, Units 1 and 2 ML20287A2472020-10-13013 October 2020 Pre-submittal Teleconference Regarding Proposed Licensing Approach to Install the General Electric Numac Wide Range Neutron Monitoring System for Hope Creek Generating Station ML20195A3962020-07-13013 July 2020 Pseg/Nrc Pre-Submittal Meeting - Salem Pressurizer Weld Interval Extension Request for Alternative (Presentation Slides) - July 20, 2020 ML15015A6772015-01-16016 January 2015 Forthcoming Closed Meeting with PSEG Nuclear, LLC, Regarding a Planned Digital Instrumentation and Controls License Amendment Request Associated with Hope Creek Generating Station, Unit 1 ML13246A1232013-08-29029 August 2013 8/29/13 Ltr to Mr. Denight Participation in Commission Meeting on Flooding and Other Extreme Weather Events ML13233A1132013-08-22022 August 2013 Notice of Forthcoming Meeting with PSEG Nuclear, LLC Regarding a Planned Digital Instrumentation and Controls License Amendment Request Associated with Hope Creek Generating Station, Unit 1 ML12314A1572012-11-14014 November 2012 Notice of Forthcoming Meeting with PSEG Nuclear, LLC, Regarding Final Supplemental Reponse to Generic Letter 2004-02 for Salem Generating Station, Units 1 and 2 ML12229A2402012-08-15015 August 2012 Closed Notice of Meeting for Salem and Hope Creek Nuclear Generating Station Scheduled for August 31, 2012 ML12013A1002012-01-13013 January 2012 Notice of Closed Meeting with PSEG Nuclear, LLC, Salem and Hope Creek, to Discuss a Potentially Greater than Green Security Related Finding ML11250A1712011-09-14014 September 2011 Notice of Forthcoming Meeting with Petitioner Requesting Action Under 10 CFR 2.206 Regarding Immediate Suspension of the Operating Licenses of General Electric (GE) Mark 1 Boiling Water Reactors (Bwrs) ML1123511452011-08-24024 August 2011 Forthcoming Meeting with PSEG Nuclear LLC (PSEG) to Discuss Proposed License Amendment Regarding Reactor Coolant System Activity for Salem Nuclear Generating Station, Unit Nos. 1 and 2 ML11126A0962011-05-12012 May 2011 Notice of Meeting with Petitioner Requesting Action Under 10CFR2.206 Regarding Immediate Suspension of Operating Licenses of General Electric Mark 1 Boiling Water Reactors ML1111703172011-04-27027 April 2011 Notice of Public Meeting - Salem Nuclear Generating Station and Hope Creek Generating Station ML1029500062010-10-28028 October 2010 11/17/10 Forthcoming Meeting to Discuss the Draft Supplemental Environmental Impact Statement for the License Renewal of Hope Creek Generating Station and Salem Nuclear Generating Station Units 1 and 2 ML1022305122010-08-18018 August 2010 08/04/10 Summary of Telephone Conference Call Held on Between NRC and PSEG Nuclear, LLC, Concerning Drais Pertaining to the Salem Nuclear Generating Station, Units 1 and 2, License Renewal Application ML1015405252010-06-0808 June 2010 Notice of Meeting with PSEG Nuclear LLC, Regarding Response to Generic Letter 2004-02 for Salem Nuclear Generating Station, Units 1 and 2 ML1012412182010-05-0606 May 2010 Public Meeting with Salem-Hope Creek to Discuss PSEG Nuclear, Llc'S Plans for Movement of Spent Fuel from Salem Nuclear Generating Station to the Independent Spent Fuel Storage Installation That It Shares with Hope Creek Generating Station ML1008103452010-03-22022 March 2010 Notice of Public Meeting: Annual Assessment Meeting with PSEG ML1003411882010-02-17017 February 2010 Notice of Forthcoming Meeting with PSEG Nuclear LLC (PSEG) Regarding Response to Generic Letter 2004-02 for Salem Nuclear Generating Station, Unit Nos. 1 and 2 ML0934405582009-12-10010 December 2009 Notice of Closed Meeting with PSEG Nuclear LLC (PSEG) to Discuss Exemption from Schedular Requirements of 10 CFR 73.55 for Hope Creek Generating Station and Salem Nuclear Generating Station, Unit Nos. 1 and 2 ML0928706352009-10-23023 October 2009 11/05/2009 Notice of Meeting to Discuss License Renewal Process and Environmental Scoping for Salem Nuclear Generating Station, Units 1 and 2, and Hope Creek Generating Station, License Renewal Application Review ML0910703162009-04-16016 April 2009 NRC Meeting with PSEG Nuclear (Salem & Hope Creek) on May 5, 2009 ML0812605262008-04-30030 April 2008 Slides from NRC Annual Assessment Meeting 2007 Reactor Oversight Process for Salem Units 1 and 2, and Hope Creek ML0726402342007-10-0101 October 2007 Notice of Closed Meeting with PSEG Nuclear LLC (Licensee) Regarding an Application for Extended Power Uprate for Hope Creek Generating Station ML0724203702007-09-24024 September 2007 Summary of Meeting with PSEG Nuclear LLC Regarding an Application for an Extended Power Uprate for the Hope Creek Generating Station Regarding Steam Dryer Analysis ML0719905282007-08-13013 August 2007 Summary of the June 28, 2007, Meeting with PSEG Nuclear, LLC, Regarding an Application for an Extended Power Uprate for the Hope Creek Generating Station Regarding Dryer Analysis Acceptance Criteria ML0721803862007-08-0606 August 2007 Notice of Forthcoming Meeting with PSEG Nuclear LLC (Licensee) Regarding an Application for Extended Power Uprate for Hope Creek Generating Station ML0717804562007-06-27027 June 2007 Notice of Meeting with PSEG Nuclear LLC (Licensee) Regarding an Application for Extended Power Uprate for Hope Creek Generating Station, to Discuss Acceptance Criteria for Boiling-Water Reactor Steam Dryer Predictive Load Under Power Uprate ML0712405052007-05-15015 May 2007 Summary of Meeting with PSEG Nuclear LLC, Regarding Technical Aspects of the Licensee'S Application for an Extended Power Uprate (EPU) at the Hope Creek Generating Station (Hope Creek) ML0710105422007-04-13013 April 2007 Notice of Forthcoming Meeting with PSEG Nuclear LLC to Discuss Technical Aspects of the Licensee'S Application for an Extended Power Uprate (EPU) at Hope Creek ML0709505272007-04-0505 April 2007 Notice of Annual Assessment Meeting with PSEG Nuclear LLC Management to Discuss the Nrc'S Assessment of the Safety Performance at the Salem and Hope Creek Generating Stations for Calendar Year 2006 ML0704602562007-02-15015 February 2007 3/02/07, Notice of Meeting with PSEG Nuclear, LLC, to Discuss Technical Aspects of the Licensee'S Application for an Extended Power Uprate (EPU) at the Hope Creek ML0631001592006-11-0808 November 2006 11/13-14/2006 Revised Notice of Forthcoming Meeting with PSEG Nuclear LLC (Licensee) Regarding an Application for Extended Power Uprate for Hope Creek ML0630301362006-10-30030 October 2006 11/13-14/2006 Notice of Meeting with PSEG Nuclear LLC Regarding Application for Extended Power Uprate for Hope Creek Generating Station ML0617900252006-07-0505 July 2006 Forthcoming Meeting with PSEG Nuclear LLC Regarding Planned Application for Extended Power Uprate for Hope Creek Generating Station ML0613904192006-05-22022 May 2006 Notice of Meeting with PSEG Nuclear LLC, Regarding Salem Nuclear Generating Station Service Water System ML0613901092006-05-11011 May 2006 Cancellation of Public Meeting with PSEG Nuclear LLC, Regarding Salem Nuclear Generating Station Service Water System and Compliance with Generic Letter 2004-02 ML0612904982006-05-11011 May 2006 Notice of Forthcoming Meeting with PSEG Nuclear LLC, Regarding Salem Nuclear Generating Station Service Water System and Compliance with Generic Letter 2004-02 2024-08-20 |
Text
I ,fDavid'Vito
"- 4.- - . - . . .
- Additional meeting materials Page
[DavidVito Additional meeting materials Paqe 1 11 From: Glenn Meyer To: Jarriel, Lisamarie; Miller, Hubert J.; Salem HC Group; Wiggins, James Date: 3/16/04 4:16PM
Subject:
- Additional meeting materials Q&As and NRC meeting slides for your use and comment CC: Matakas, Gina 0c/\
' [a~i~fIg NRC sode Wodecw ...111.1 I.., Page 1 NRC logo Management Meeting between NRC and PSEG Assessment Plans for Salem & Hope Creek March 18, 2004
FDayidVio-NRC sfideordPerfect.w d
_~~ _.. ,..y _Page 2 Agenda
- 1. Discussion of work environment issue by NRC
- 2. Presentation by PSEG on assessment plan and initial results
- 3. Detailed discussion on assessment plan between NRC & PSEG
- 4. Closing remarks
- 5. Public questions and comments
- 6. Adjournment by 5 pm
J7_VDavdfVito,-
'Z~~R Uide (WordPerfecttwp __g Pagep NIRC Letter dated January 28, 2004 -
- Interim results of ongoing special review of work environment
- Concerns on work environment
- Emergent equipment issues and operational decision-making
- Request for PSEG in-depth assessment
- PSEG Plan of action within 30 days (Feb. 27, 2004)
- Meeting to discuss plan in detail