2/24/06 Letter to John T. Conway from Daniel J. Merzke Revision of Schedule for the Conduct of Review of the Monticello Nuclear Generating Plant License Renewal Application
ML060550139
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 02/24/2006
From: Daniel Merzke
NRC/NRR/ADRO/DLR/RLRB
To: Conway J
Nuclear Management Co
Merzke, D., NRR/ADRO/DLR/RLRB, 415-3777
References
Download: ML060550139 (6)


Text

February 24, 2006 Mr. John T. Conway Site Vice President Nuclear Management Company, LLC 2807 West County Road 75 Monticello, MN 55362-9637

SUBJECT:

REVISION OF SCHEDULE FOR THE CONDUCT OF REVIEW OF THE MONTICELLO NUCLEAR GENERATING PLANT LICENSE RENEWAL APPLICATION

Dear Mr. Conway:

Enclosed is a revised schedule for review of the Monticello Nuclear Generating Plant license renewal application. This schedule has been revised to reflect the 22-month review plan. Because no hearing was granted, the milestone associated with time to conduct a hearing was removed from the schedule. If you have any questions on the revised schedule, please contact me by telephone at 301-415-3777 or via electronic mail at DXM2@nrc.gov.

Sincerely,

/RA/

Daniel J. Merzke, Project Manager License Renewal Branch B Division of License Renewal Office of Nuclear Reactor Regulation Docket No.: 50-263

Enclosure:

As stated cc w/encl: See next page

February 24, 2006 Mr. John T. Conway Site Vice President Nuclear Management Company, LLC 2807 West County Road 75 Monticello, MN 55362-9637

SUBJECT:

REVISION OF SCHEDULE FOR THE CONDUCT OF REVIEW OF THE MONTICELLO NUCLEAR GENERATING PLANT LICENSE RENEWAL APPLICATION

Dear Mr. Conway:

Enclosed is a revised schedule for review of the Monticello Nuclear Generating Plant license renewal application. This schedule has been revised to reflect the 22-month review plan. Because no hearing was granted, the milestone associated with time to conduct a hearing was removed from the schedule. If you have any questions on the revised schedule, please contact me by telephone at 301-415-3777 or via electronic mail at DXM2@nrc.gov.

Sincerely,

/RA/

Daniel J. Merzke, Project Manager License Renewal Branch B Division of License Renewal Office of Nuclear Reactor Regulation Docket No.: 50-263

Enclosure:

As stated cc w/encl: See next page DISTRIBUTION: See next page ADAMS Accession no.: ML060550139 Document Name: E:\\Filenet\\ML060550139.wpd OFFICE PM:RLRB LA:RLRB BC:RLRB NAME DMerzke YEdmonds JZimmerman DATE 2/24/06 2/22/06 2/24/06 OFFICIAL RECORD COPY

Monticello Nuclear Generating Plant cc:

Jonathan Rogoff, Esquire Vice President, Counsel & Secretary Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 U.S. Nuclear Regulatory Commission Resident Inspectors Office 2807 W. County Road 75 Monticello, MN 55362 Manager, Regulatory Affairs Monticello Nuclear Generating Plant Nuclear Management Company, LLC 2807 West County Road 75 Monticello, MN 55362-9637 Robert Nelson, President Minnesota Environmental Control Citizens Association (MECCA) 1051 South McKnight Road St. Paul, MN 55119 Commissioner Minnesota Pollution Control Agency 520 Lafayette Road St. Paul, MN 55155-4194 Regional Administrator, Region III U.S. Nuclear Regulatory Commission 801 Warrenville Road Lisle, IL 60532-4351 Commissioner Minnesota Department of Health 717 Delaware Street, S.E.

Minneapolis, MN 55440 Douglas M. Gruber, Auditor/Treasurer Wright County Government Center 10 NW Second Street Buffalo, MN 55313 Commissioner Minnesota Department of Commerce 85 7th Place East, Suite 500 St. Paul, MN 55101-2198 Manager - Environmental Protection Division Minnesota Attorney Generals Office 445 Minnesota St., Suite 900 St. Paul, MN 55101-2127 John Paul Cowan Executive Vice President & Chief Nuclear Officer Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 Nuclear Asset Manager Xcel Energy, Inc.

414 Nicollet Mall, R.S. 8 Minneapolis, MN 55401 Mr. James Ross Nuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, DC 20006-3708 Joseph Pairitz License Renewal Project Manager Monticello Nuclear Generating Plant Nuclear Management Company, LLC 2807 West County Road 75 Monticello, MN 55362-9637 Mr. Douglas F. Johnson Director, Plant Life Cycle Issues Nuclear Management Company, LLC 700 First Street Hudson, WI 54016

Monticello Nuclear Generating Plant cc:

David R. Lewis Pillsbury Winthrop Shaw Pittman, LLP 2300 N Street, NW Washington, DC 20037-1122 Mr. George Crocker North American Water Office P.O. Box 174 Lake Elmo, MN 55042 Mr. John T. Conway Site Vice President Monticello Nuclear Generating Plant Nuclear Management Company, LLC 2807 West County Road 75 Monticello, MN 55362-9637

Letter to J. Conway from D. Merzke dated February 24, 2006

SUBJECT:

REVISION OF SCHEDULE FOR THE CONDUCT OF REVIEW OF THE MONTICELLO NUCLEAR GENERATING PLANT LICENSE RENEWAL APPLICATION DISTRIBUTION:

HARD COPY DMerzke E-MAIL JFair RWeisman AMurphy RPettis GGalletti CLi GBagchi SSmith (srs3)

SDuraiswamy YL (Renee) Li RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDe RidsNrrDci RidsNrreEemb RidsNrrDeEeeb RidsNrrDeEqva RidsNrrDss RidsNrrDnrl RidsOgcMailCenter RidsNrrDipm DLR Staff LRaghavan PTam AStone, RIII BBurgess, RIII PLougheed, RIII SRay, RIII AHodgdon MWoods RidsOpaMail

Enclosure Monticello Nuclear Generating Plant LICENSE RENEWAL APPLICATION REVIEW MILESTONES Milestone Schedule Actual Receive License Renewal (LR) Application 03/24/05 03/24/05 Federal Register Notice (FRN) published - Receipt & Availability review 04/06/05 04/06/05 Public Information Meeting - LR Process & Safety Review Overview 04/20/05 04/20/05 FRN published - Acceptability/Opportunity for Hearing 05/10/05 05/12/05 FRN published - Intent/Environmental Scoping Meeting 06/03/05 06/02/05 Public Exit Meeting - Scoping & Screening Methodology Audit 06/24/05 06/24/05 Public Meeting - Environmental Scoping 06/30/05 06/30/05 Deadline for filing hearing requests and petitions for intervention 07/11/05 07/11/05 Environmental Scoping Periods Ends 08/02/05 08/02/05 Public Exit Meeting - AMP/AMR Audit 08/18/05 08/18/05 Environmental Requests for Additional Information (RAIs) - issued 08/26/05 08/26/05 Environmental RAIs - responses received 10/07/05 10/07/05 Safety RAIs - issued 11/01/05 11/07/05 Safety RAI - responses received 12/01/05 12/07/05 Draft Supplemental Environmental Impact Statement (SEIS) Issued 02/10/06 01/23/06 FRN Published - Availability/Comment on draft SEIS 02/17/06 02/02/06 Public Exit Meeting - Scoping & Screening/AMP Inspections 02/22/06 02/22/06 Public Meeting - draft SEIS 03/22/06 Safety Evaluation Report (SER) with Open Item(s) - Issued 04/28/06 End of draft SEIS comment period 05/04/06 ACRS Subcommittee Meeting on SER with Open Item(s) 06/06 SER Open Item(s) - Response(s) Received 06/23/06 Final SEIS - issued 09/22/06 FRN published - Availability of Final SEIS 09/29/06 SER - issued 10/04/06 ACRS Full Committee Meeting on SER 11/06 Decision - Director, NRR (license issued, if approved) 01/24/07