Vermont Yankee - Letter from Jason C. Zorn to Administrative Judges Responding to the Licensing Board'S Memorandum and Order (Ruling on Deliberative Process Privilege Claims), Dated December 21, 2005
ML060250472
Person / Time
Site: Vermont Yankee Entergy icon.png
Issue date: 01/19/2006
From: Zorn J
NRC/OGC
To: Anthony Baratta, Karlin A, Rubenstein L
Atomic Safety and Licensing Board Panel
Byrdsong A T
References
50-271-OLA, ASLBP 04-832-02-OLA, RAS 11083
Download: ML060250472 (54)


Text

vJ--

UNITED STATES 7D,--

NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 January 19, 2006 OFFICE OF THE GENERAL COUNSEL Administrative Judge Alex S. Karlin, Chair Administrative Judge Lester S. Rubenstein Atomic Safety and Licensing Board Panel Atomic Safety and Licensing Board Panel U.S. Nuclear Regulatory Commission 4760 East Country Villa Drive Mail Stop: T-3F23 Tucson, AZ 85718 Washington, DC 20555-0001 Administrative Judge Anthony J. Baratta Atomic Safety and Licensing Board Panel U.S. Nuclear Regulatory Commission Mail Stop: T-3F23 Washington, DC 20555-0001 In the Matter of ENTERGY NUCLEAR VERMONT YANKEE LLC and ENTERGY NUCLEAR OPERATIONS, INC.

(Vermont Yankee Nuclear Power Station)

Docket No. 50-271 -OLA

Dear Administrative Judges:

On December 21, 2005, the Atomic Safety and Licensing Board issued its "Memorandum and Order (Ruling on Deliberative Process Privilege Claims)" ("Order"),

concerning the State of Vermont Department of Public Service's ("DPS") two Motions to Compel Production of Certain NRC Staff ("Staff") Documents, filed on August 31, 2005, and September 29, 2005, respectively. In the Order, the Board directed the Staff to resubmit its deliberative process privilege logs filed between September 6, 2005, and December 21, 2005, under procedures outlined by the Board, including "the name and job title of the most senior person who made the decision to withhold the document and assert the [deliberative process]

privilege." In accordance with the Board's Order, the Staff submits the enclosed documents concerning its claim of the deliberative process privilege for the documents at issue.

Jason C. Zorn Counsel for NRC Staff

Enclosures:

Affidavit of Catherine Haney Deliberative Process Privilege Logs (Supplements 13 - 18) cc: Service List

I _W -

January 18, 2006 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of )

)

ENTERGY NUCLEAR VERMONT YANKEE ) Docket No. 50-271-OLA LLC and ENTERGY NUCLEAR )

OPERATIONS, INC. ) ASLBP No. 04-832-02-OLA (Vermont Yankee Nuclear Power Station) )

AFFIDAVIT OF CATHERINE HANEY I, Catherine Haney, being first duly sworn, do hereby state as follows:

1. I am employed as the Director of the Division of Operating Reactor Licensing

("DORL") in the Nuclear Regulatory Commission's ("NRC") Office of Nuclear Reactor Regulation ("NRR"). My supervisory responsibilities include oversight of the NRC Staff's review and evaluation of the Vermont Yankee Nuclear Power Station Extended Power Uprate ("EPU")

license amendment application.

2. During the course of its review and evaluation of the EPU license amendment application, the NRC Staff has generated or used documents that Staff members under my supervision have identified as privileged because the documents contained predecisional information related to the Staff's deliberative process. Although the identity of those documents has been disclosed during a document review process conducted as part of this proceeding, the documents themselves have been withheld in accordance with 10 C.F.R. § 2.390(a)(5) and NRC Management Directive 3.4.
3. I am aware that the Atomic Safety and Licensing Board ("Board") ordered the Staff to resubmit privilege logs that it had filed between September 6, 2005, and December 21,

2 2005, including the name and job title of a senior individual who has decided to withhold documents identified in those logs.

4. The total number of privileged documents identified in the privilege logs filed from September 6, 2005, to December 21, 2005, is 141. Of those, 40 have previously been reviewed and withheld by myself or my predecessor, Ledyard B. Marsh. Further, those 101 documents had previously been reviewed by another person within NRR with less senior responsibilities. Thus, the Board's December 21, 2005, Order applies to a total of 101 documents.
5. I have personally reviewed each of the 101 documents in question, and have determined, in accordance with the guidance contained in Management Directive 3.4, that they contain predecisional information concerning the Staff's review of the EPU application. All of the documents contain the Staff's analyses, recommendations, opinions, or evaluations, and may not necessarily reflect the final agency position with respect to the matters discussed therein. Each of the documents comprises part of the deliberative process necessary to the Staff's review of the pending EPU application.
6. Further, I have determined that disclosure of the 101 documents could result in harm to the agency, in that it would (a) prematurely disclose the preliminary views of individual Staff members and/or the Staff prior to reaching a final agency decision, and could thus create confusion as to the actual policy or views of the NRC Staff; (b) hinder the efficiency of the Staff, in that forced disclose of their internal discussions on an unresolved issue would serve to chill all future deliberations and would interfere with our ability to engage in a free exchange of opinions and analyses prior to publishing our final review documents; and (c) imply or suggest incorrectly that the opinions of the Staff members involved in these communications are actually the final decisions of the agency, while no such final decision has yet been made.
7. Accordingly, I formally invoke the deliberative process privilege with respect to

Tr~ F, 3

each of the 101 documents affected by the Board's December 21, 2005, Order.

8. I hereby certify that the foregoing is true and complete to the best of my knowledge, information and belief.

Cn /

Catherine Haneyv Subscribed and sworn to before me this 18t day of January, 2006.

(_ \9(t

  • 7 *LI

) t~

Mntn Mt Plihinu:

My commission expires: VC 1h X 9 7 CIRCE E. MARTIN NOTARY PUBLIC STATE OF MARYLAND My Commission Expires March 1, 2007

VERMONT YANKEE EPU HEARING FILE AND MANDATORY DISCLOSURES PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 13 - September 6, 2005 Reissued January 19, 2006' Certain documents otherwise subject to inclusion in the hearing file and mandatory disclosures for this proceeding have been determined by the NRC Staff to contain information subject to withholding from public disclosure as predecisional, deliberative information. Pursuant to 10 C.F.R.

§ 2.336(b)(5), the Staff is providing this log to identify the following documents, withheld under the "deliberative process" privilege.

Accession Author Title/Description: Document Document Addressee / Comment Page Number Name/Affiliation: Date Type Addressee Count Affiliation ML052230210 Razzaque M M, E-mail Razzaque, 8/10/2005 E-Mail Ennis R B, Contains draft 3 NRC/NRR NRR, to Ennis, NRR NRC/NRR requests for Re: VY EPU RAls. information regarUin lthe the effect of the EPU on new and spent fuel storage 1 The Director of the Division of Operating Reactor Licensing, Catherine Haney, has decided on behalf of the NRC that the thirteen documents in this privilege log that have been shaded in grey should be withheld from public disclosure under the deliberative process privilege. For those twenty-five documents not shaded in grey, Ledyard B. Marsh, the previous Director of the Division of Licensing and Project Management, had made the decision to withhold those documents under the deliberative process privilege. See NRC Staff's Answer to Vermont Department of Public Service's Second Motion to Compel at 10-1 1.

PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 13 09/06/05 (Reissued 01/19/06)

Accession Author Title/Description: Document Document Addressee / Comment Page Number Name/Affiliation: Date Type Addressee Count Affiliation ML052230209 Razzaque M M, E-mail Razzaque, 8/10/2005 E-Mail Ennis R B, Contains draft 3 NRC/NRR NRR, to Ennis, NRR, NRC/NRR requests for Re: VY EPU RAls. information regarding single loop operation of shutdown cooling and clarification of terms in previous responses to RAls ML052230204 Reddy D K- F-mai! RPddy, NRR, 8!10200o5 F-Mai! Ennis R R- Contains staff 2 NRC/NRR to Ennis, NRR, Re: NRC/NRR discussion of VY EPU RAls. responses to RAls regarding stability and reliability of condensate and feedwater system ML052310065 Ennis R' B, E-mail Ennis, NRR, 8/15/2005 E-Mail i Pal A N, Contains staff 2 iNRC/NRR .: toPal,

6 NRR, Re: VY: NRC/NRR recommendations EPU SBO Response. to draft safety evaluation regarding station

_ _ __ __ _ _ _ _ _ _ _ _ _ __ __ -__ ___ ___ __ __ __ _ __ _ _  : ___ ___ ___ __ blacko ut an alysis VI PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 13 09/06/05 (Reissued 01/19/06)

Accession Author Title/Description: Document Document Addressee / Comment Page Number Name/Affiliation: Date Type Addressee Count Affiliation ML052310072 Jacobson J,  : E-mail Jacobson, 8/15/2005 E-Mail Ennis R, Pal A, Contains staff 2 NRC/NRR NRR, To Ennis, NRC/NRR recommendations NRR,:Re: VY EPU to draft safety SBQ Response. evaluation regarding station

______________blackout analysis _ _ _ _

ML052340120 Ennis R 1B, E-mail Ennis,. NRR, 8/17/2005 :E-Mail- .:Pal:A N, I Contains: 9 uNRC/NRR' l00 l to:Pal and:1 :. :. 'Razzaque M M, information Razzaque,'NRR, Re; NRC/NRR-. . regarding NRC's VY EPU RAls--. staff's internal scheduling practices and several pages of previously disclosed requests for additional information ML052340040 Pal A N, E-mail.Pal, NRR, to 8/17/2005 E-Mail : Ennis R B3, Contains NRC/NRR/ADPT Ennis, NRR,, Re: VY NRC/NRR information EPU. RlAs. regarding NRC's staff's internal scheduling

___ ______ ______ ______ _ _:.: i:.d

-_. p ra c t i c e s PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 13 09/06/05 (Reissued 01/19/06)

Accession Author Title/Description: Document Document Addressee / Comment Page Number Name/Affiliation: Date Type Addressee Count Affiliation ML052340037 Ennis R B, E-mail Ennis, NRR, 8/18/2005 E-Mail Pal-A N, Contains 2 NRC/NRR/ADPT to Razzaque and Razzaque M M, information Pal, NRR, Re: VY NRC/NRR/ADP regarding NRC's EPU Conference: T staff's internal Call. scheduling

_________-___ practices ML052340101 Ennis R B, E-mail Ennis, NRR, 8/18/2005 E-Mail Reddy D K, Contains draft 5 NRC/NRR to Reddy, NRR, Re: NRC/NRR requests for VY EPU RAls. additional information reaardina condensate and feedwater system ML052340038 Razzaque M M, E-mail Razzaque, 8/18/2005 E-Mail Ennis R B, Contains 2 NRC/NRR NRR,^to Ennis, NRR NRC/NRR information Re:VY EPU regarding NRC's Conference CAll. staff's internal scheduling

_______________ _ S _ _ p ra ctices PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 13 09/06/05 (Reissued 01/19/06) ,1' Accession Author Title/Description: Document Document Addressee / Comment Page Number Name/Affiliation: Date Type Addressee Count Affiliation ML052310075 Reddy D K, E-mail Reddy, NRR, 8/18/2005 E-Mail Ennis R B, Contains staff 5 NRC/NRR to Ennis, NRR, Re: NRC/NRR discussion of VY EPU RAls. response to request for additional information regarding condensate and feedwater system ML052340089 Reddy D K, E-mail Reddy, NRR, 8/18/2005 E-Mail Ennis R B, Contains staff 5 NRr/NRR to Ennis, NRR, Re: discussion of VY EPU RAls. response to request for additional information regarding condensate and feedwater system ML052340108 Thomas G, E-mail Thomas, 8/18/2005 E-Mail Ennis R B, Contains draft 2 NRC/NRR NRR, to Ennis, NRR, NRC/NRR request for Re: VY EPU Review. additional information regarding accident and transient analyses PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 13 09/06/05 (Reissued 01/19/06)

Accession Author Title/Description: Document Document Addressee / Comment Page Number Name/Affiliation: Date Type Addressee Count Affiliation ML052340239 Ennis R B, E-mail Ennis, NRR, 8/19/2005 E-Mail Jones S R, Contains staff 2 NRC/NRR to Jones, NRR, Re: NRC/NRR discussion of VY EPU RAls. response to request for additional information regarding condensate and feedwater system ML052340258 Ennis R B, E-mail Ennis, NRR, 8/19/2005 E-Mail Thomas G, Contains draft NRC/NRR to Thomas, NRR, NRC/NRR request for Re: VY EPU RAls. additional information regarding accident and transient analyses ML052340262 Jones S R, E-mail Jones, NRR, 8/19/2005 E-Mail Ennis R B, Contains staff 2 NRC/NRR to Ennis, NRR, Re: NRC/NRR discussion of VY EPU RAls. response to request for additional information regarding condensate and J J.

feedwater system I PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 13 09/06/05 (Reissued 01/19/06)

Accession Author Title/Description: Document Document Addressee / Comment Page Number Name/Affiliation: Date Type Addressee Count Affiliation ML052340251 Jones S R, E-mail Jones, NRR, 8/19/2005 E-Mail Ennis R B, Contains staff 2 NRC/NRR to Ennis, NRR, Re: NRC/NRR discussion of VY EPU RAls. response to request for additional information regarding condensate and feedwater system ML052360313 Ennis R B, E-mail Ennis, NRR, 8/22/2005 E-Mail, PaIA N, Contains 9 NRG/NRR to RazzaqueNP, Requst Ifnr Razzaque M M, informton  :

Et. Al., ReL gVY EPU Additional Thomas G, regarding NRC RAls, Information NRC/NRR staff's internal (RAI) scheduling

._____________ n__  ::__:__  ::practices  :

ML052360320 Thomas G, E-Mail Thomas, 8/22/2005 E-Mail Ennis R B, Contains staff 2 NRC/NRR NRR, to Ennis, NRR, NRC/NRR recommendations Re: VY EPU RAI. to changes to request for additional information PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 13 09/06/05 (Reissued 01/19/06)

Accession Author Title/Description: Document Document Addressee / Comment Page Number Name/Affiliation: Date Type Addressee Count Affiliation ML052410318 Abdullahi Z, E-mail Abdullahi, 8/25/2005 E-Mail Ennis R B, Contains staff 9 NRC/NRR NRR, to Ennis, NRR, NRC/NRR recommendations Re: VY EPU RAls. to changes to request for additional information regarding linear heat generation rate ML052410385 Abdullahi Z, E-mail Abdullahi, 8/25/2005 E-Mail Ennis R B, Contains staff 18 NRC/NRR NRR, to Ennis. NRR, NRrG/NRR rrcnmmrendations Re: VY EPU RAls. to changes to request for additional information regarding linear heat generation rate PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 13 09/06/05 (Reissued 01/19/06)

Accession Author Title/Description: Document Document Addressee I Comment Page Number Name/Affiliation: Date Type Addressee Count Affiliation ML052410296 Ennis R B, E-mail Ennis, NRR, 8/25/2005 E-Mail Holden C F, Contains staff 4 NRC/NRR to Holden, NRR, Re: NRC/NRR recommendations VY EPU & regarding internal Conference Call. procedures for following up responses to requests for additional information ML052410379 Ennis R B, E-mail Ennis, NRR, 8/25/2005 E-Mail Jones S R, Contains staff 6 NRC/NRR to Jones. NRR. Re: NRC/NRR recommendations VY EPU RAIs. to changes to request for additional information regarding condensate and feedwater system PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 13 09/06/05 (Reissued 01/19/06) 'V Accession Author Title/Description: Document Document Addressee I Comment Page Number Name/Affiliation: Date Type Addressee Count Affiliation ML052410310 Marsh L B, E-mail Marsh, NRR, 8/25/2005 E-Mail Ennis R B, Contains staff 3 NRC/NRR to Ennis, NRR, Re: NRC/NRR recommendations VY EPU Conference regarding internal Call. procedures for following up responses to requests for additional information ML052410383 Razzaque M M, E-mail Razzaque, 8/25/2005 E-Mail Ennis R B, Contains staff 2 NRC/NRR NRR, to Ennis, NRR, NRG/NRR recommendations Re: VY EPU RAls. to changes to request for additional information regarding maximum and average power densities PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 13 09/06/05 (Reissued 01/19/06)

Accession Author Title/Description: Document Document Addressee / Comment Number Name/Affiliation: Date Type Addressee Affiliation ML052410391 Reddy D K, E-mail Reddy, NRR, 8/25/2005 E-Mail Ennis R B, Contains staff 3 NRC/NRR to Ennis, NRR Re: NRC/NRR recommendations VY EPU RAis. to changes to request for additional information regarding performance of safety relief valves ML052410316 Reddy D K, E-mail Reddy, NRR, 8/25/2005 E-Mail Ennis R B, Contains staffi 5 KNRC!NRR to Ennis, NRR, Re: NRr/NRR recommendations VY EPU RAls. to changes to request for additional information regarding condensate and feedwater system PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 13 09/06/05 (Reissued 01/19/06)

Accession Author Title/Description: Document Document Addressee I Comment Page Number Name/Affiliation: Date Type Addressee Count Affiliation ML052410395 Tatum J E, E-mail Tatum, NRR, 8/25/2005 E-Mail Ennis R B, Contains staff 2 NRC/NRR to Ennis, NRR, Re: NRC/NRR recommendations VY EPU RAls. to changes to request for additional information regarding condensate and feedwater system ML052420358 Jones S R, E-Mail Jones, NRR, 8/26/2005 E-Mail Ennis R B. Contains staff 2 NRCKNRR to Ennis NIPP m ENRC/NRR recomnmendations VY EPU RA's. to changes to request for additional information regarding condensate and feedwater system PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 13 09/06/05 (Reissued 01/19/06)

Accession Author Title/Description: Document Document Addressee / Comment Page Number Name/Affiliation: Date Type Addressee Count Affiliation ML052420371 Jones S R, E-mail Jones, NRR, 8/26/2005 E-Mail Ennis R B, Contains staff 2 NRC/NRR to Ennis, NRR, Re: NRC/NRR recommendations VY EPU RAI. to changes to request for additional information regarding condensate and feedwater system ML052420376 Jones S R, E-mail Jones, NRR, 8/26/2005 E-Mail Ennis R B, Contains staff 3 NRC/NRR to Fnnis, NRR, Re: NPrC!NRP rerommendations VY EPU RAI. to changes to request for additional information regarding performance of safety relief valves ML052420401 Razzaque MM, E-mail Pazzaque, 8/26/2005 E-Mail Ennis R B, Contains staff 3 NRC/NRR NRR, to PAL, NRR, NRC/NRR recommendations Re: VY EPUSBO to draft safety Input.: evaluation regarding station

_____ _____ _________ _____ ____ _____ ____ blackout analysis _ _ _ _

PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 13 09/06/05 (Reissued 01/19/06)

Accession Author Title/Description: Document Document Addressee / Comment Page Number Name/Affiliation: Date Type Addressee Count Affiliation ML052420384 Tatum J E, E-mail Tatum, NRR, 8/26/2005 E-Mail Ennis R B, Contains staff 2 NRC/NRR to Ennis, NRR, Re: NRC/NRR recommendations VY EPU RAis. to changes to request for additional information regarding condensate and feedwater system ML052420409 Ennis R'B,

4. 1NRC/NRRE-Mail[

E-rmailEnnis, NRR, to Holden, NRR, Et-1 8/29/2005'l: Holden C F, Contains info^rmatio,,

Al., Re:,VYEPU' regarding NRC Conference Cal. ' staff internal scheduling

____ __ __ __ _ practices ML052420408 Ennis R B, E-mail, Ennis, NRR, 8/29/2005 E-Mail Holden C F, Contains NRC/NRR to Holden, NRR, Et. NRC/NRR information Al., Re: VY EPU regarding NRC Conference Call. staff internal scheduling

-'_________'- __ '____________ _ __ __ __ __' p ra ctices PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 13 09/06/05 (Reissued 01/19/06)

Accession Author Title/Description: Document Document Addressee / Comment Page Number Name/Affiliation: Date Type Addressee Count Affiliation ML052440380 Ennis R B, E-mail Ennis, NRR, 8/30/2005 E-Mail Abdullahi Z, Contains 3 NRC/NRR to Wermiel, NRR, Et. Akstulewicz F information AL., Re:VY:EPUGE M, Wermiel-J regarding NRC Audit. S. NRC/NRR staff internal scheduling

__ _ _ f _ : _ _: ________:_0

practiceses

ML052440378 Ennis R B, E-mail Ennis, NRR, 8/31/2005 E-Mail' Thomas G, Contains 2 NRC/NRR to Thormias,'Re:R VY NRC/NRR; information EPU Question. ' :z regarding NRC staff internal~

sheduling,

__ __ _ _ _ _ _ __ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ p ra c tic e s_ _ _ _ _

ML052440373 Ennis R B, E-mail Ennis, NRR, 8/31/2005: :l E-Mail We rmiel J S, Contains 3 NRC/NRR to Wermiel, NRR, NRC/NPRR: information Re: VY EPU Audit. regarding NRC Staff internal scheduling

__ __ __ _ __ _ __ _ _ _ _ _ _ _ __ _ _ __ _ _ _ _ _ _ _ __ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ p rac tice s_ _ _ _ _

VERMONT YANKEE EPU HEARING FILE AND MANDATORY DISCLOSURES PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 14 - September 29,2005 Reissued January 19, 20061 Certain documents otherwise subject to inclusion in the hearing file and mandatory disclosures for this proceeding have been determined by the NRC Staff to contain information subject to withholding from public disclosure as predecisional, deliberative information. Pursuant to 10 C.F.R.

§ 2.336(b)(5), the Staff is providing this log to identify the following documents, withheld under the "deliberative process" privilege.

PDP Accession Author Title/ Document Document Addressee / Comment Page No. Number Name/

Description:

Date Type Addressee Count Affiliation: Affiliation 14-01 ML052500332 Stutzke M A, E-mail, Stutzke, 9/2/2005 E-Mail Ennis R B, Contains NRC staff 2 NRC/NRR NRR, to Ennis, NRC/NRR discussion of NRR, Re: VY preliminary results of EPU risk evaluation of Containment containment Overpressure overpressure credit Credit.

14-02 ML052450441 Ward L W, E-mail, Ward, 9/2/2005 E-Mail Lobel R M, Contains NRC staff 2 NRC/NRR NRR, to Lobel, NRC/NRR analysis of LBLOCA NRR, Re: BY mass and energy EPU LBLOCA release calculations Calc.

' The Director of the Division of Operating Reactor Licensing, Catherine Haney, has decided on behalf of the NRC that all of the documents listed in this privilege log should be withheld from public disclosure under the deliberative process privilege.

1 of 14

PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 14 - 09/29/05 (Reissued 01/19/06)

PDP Accession Author Title/ Document Document Addressee I Comment Page No. Number Name/

Description:

Date Type Addressee Count Affiliation: Affiliation 14-03 ML052500337 Abdullahi Z, E-mail, Abdullahi, 9/8/2005 E-Mail Gehin J C, Oak Contains discussion 4 NRC/NRR NRR, to Gehin, Ridge National of internal NRC staff ORNL, Re: VY Lab (ORNL) auditing procedures EPU GE Audit.

14-04 ML052550202 Ennis, Email, Ennis, 9/8/2005 Email Abdullahi Z, Contains information 2 NRC/NRR NRR, Abdullahi, NRC/NRR regarding internal NRR, re: VY EPU NRC staff scheduling Conference Call practices 14-05 ML052560046 Wang A B. E-mail Wang, 9/9/2005 E-Mail Ennis R B, Contains discussion 2 NRC/NRR NRR, to Ennis, NRC/NRR of internal NRC staff NRR, Re: VY auditing procedures EPU Conference Call.

14-06 ML052560045 Abdullahi Z, E-mail Ennis, 9/12/2005 E-Mail Ennis R B, Contains information 2 Akstulewicz F NRR, to NRC/NRR regarding internal M, NRC/NRR Abdullahi and NRC staff scheduling Akstulewicz, practices NRR, Re: VY EPU Conference Call.

2 of 14

PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 14 - 09/29/05 (Reissued 01/19/06)

PDP Accession Author Title/ Document Document Addressee / Comment Page No. Number Name/

Description:

Date Type Addressee Count Affiliation: Affiliation 14-07 ML052570529 Jones S R, E-mail, Jones, 9/12/2005 E-Mail Ennis R B, Contains NRC staff 3 NRC/NRR NRR, to Ennis, NRC/NRR analysis of NRR, Re: VY responses to EPU Supplement requests for

32. additional information 14-08 ML052580571 Burns T F, Erosion- 9/12/2005 Memoranda Anderson C J, Contains NRC staff's 8 NRC/RGN- Corrosion/Flow- NRC/RGN- analysis and I/DRS/PSB2 Accelerated- I/DRP/PB5 preliminary Corrosion recommendations Monitorin resulting from Activities for inspection of Power Uprate Erosion-Inspection Corrosion/Flow-Feeder for Accelerated-Vermont Yankee, Corrosion Monitoring Inspection Report Activities 05000271/20050 04 14-09 ML052570534 Ennis R B, E-mail, Ennis, 9/13/2005 E-Mail Abdullahi Z, Contains information 4 NRC/NRR NRR, to NRC/NRR regarding internal Abdullahi, NRR, NRC staff scheduling Et. Al., Re: VY practices EPU Schedule _ _

3 of 14

PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 14- 09/29/05 (Reissued 01/19/06)

PDP Accession Author Title/ Document Document Addressee I Comment Page No. Number Name/

Description:

Date Type Addressee Count Affiliation: Affiliation 14-10 ML052570530 Ennis R B, E-mail, Ennis, 9/13/2005 E-Mail Jones S R, Contains information 4 NRC/NRR NRR, to Jones, NRC/NRR regarding internal NRR, Re: VY NRC staff scheduling EPU Supplement practices 32 14-11 ML052570507 Ennis R B, E-mail, Ennis, 9/13/2005 E-Mail Sienel B E, Contains NRC staff 2 NRC/NRR RGN-1, to Sienel, NRC/RGN-I discussion of NRR, Re: VY contents of draft EPU Review. safety evaluation 14-12 ML052570536 Jones S R, E-mail, Jones, 9/13/2005 E-Mail Ennis R B, Contains information 3 NRC/NRR NRR, to Ennis, NRC/NRR regarding internal NRR, Re: VY NRC staff scheduling EPU Supplement practices 32.

14-13 ML052570547 Lobel R M, E-mail, Lobel, 9/13/2005 E-Mail Ennis R B, Contains information 3 NRC/NRR NRR, to Ennis, NRC/NRR regarding internal NRR, Re: VY NRC staff scheduling EPU Schedule. practices 14-14 ML052570544 Pal A N, E-mail, Pal, NRR, 9/13/2005 E-Mail Ennis R B, Contains information 2 NRC/NRR to Ennis, NRR, NRC/NRR regarding internal Re: VY EPU NRC staff scheduling Schedule. practices 4 of 14

PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 14 - 09/29105 (Reissued 01/19/06)

PDP Accession Author Title/ Document Document Addressee I Comment Page No. Number Name/

Description:

Date Type Addressee Count Affiliation: Affiliation 14-15 ML052570518 Sienel B E, E-mail, Sienel, 9/13/2005 E-Mail Ennis R B, Contains NRC staff 2 NRC/RGN-I RGN-1, to Ennis, NRC/NRR discussion of NRR, Re: VY contents of draft EPU Review. safety evaluation 14-16 ML052590139 Ennis R B, E-mail, Ennis, 9/14/2005 E-Mail Jones S R, Contains information 2 NRC/NRR NRR, to Ready, Reddy D K, regarding internal NRR, Et. AL., Re: Tatum J E, NRC staff scheduling VY EPU NRC/NRR practices Conference Call.

14-17 ML052570537 Ennis R B, E-mail, Ennis, 9/14/2005 E-Mail Reddy D K, Contains NRC staff 2 NRC/NRR NRR, to Reddy, NRC/NRR discussion of NRR, Re: VY contents of draft EPU SBO RAI safety evaluation 14-18 ML052590099 Razzaque M E-mail, 9/14/2005 E-Mail Ennis R B, Contains NRC staff 3 M, NRC/NRR Razzaque, NRR, NRC/NRR discussion regarding to Ennis, NRR, internal review Re: VY EPU practices and Supplement 32 contents of draft safety evaluation 5 of 14

PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 14- 09/29/05 (Reissued 01/19/06)

PDP Accession Author Title/ Document Document Addressee / Comment Page No. Number Name/

Description:

Date Type Addressee Count Affiliation: Affiliation 14-19 ML052570525 Devender R E-mail, Reddy, 9/14/2005 E-Mail Ennis R B, Contains NRC staff 2 K, NRC/NRR NRR, to Ennis, NRC/NRR discussion regarding NRR, Re: VY internal review EPU SBO RAls practices and contents of draft safety evaluation 14-20 ML052570517 Reddy D K, E-mail, Reddy, 9/14/2005 E-Mail Jones S R, Contains NRC staff 4 NRC/NRR NRR, to Jones, NRC/NRR discussion of NPR R: VY contet ofd EPU SBO RAls. safety evaluation 14-21 ML052590136 Tatum J E, E-mail, Tatum, 9/14/2005 E-Mail Ennis R B, Contains information 2 NRC/NRR NRR, to Ennis, NRC/NRR regarding internal NRR, Re: VY NRC staff scheduling EPU Conference practices Call.

14-22 ML052620316 Ennis R B, E-mail, Ennis, 9/15/2005 E-Mail Razzaque M M, Contains NRC staff 5 NRC/NRR NRR, to NRC/NRR discussion of Razzaque, NRR, contents of draft

- Re: VY EPU safety evaluation and Supplement 32. draft requests for additional information 6 of 14

PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 14 - 09/29/05 (Reissued 01/19/06)

PDP Accession Author Title/ Document Document Addressee / Comment Page No. Number Name/

Description:

Date Type Addressee Count Affiliation: Affiliation 14-23 ML052620313 Jones S R, E-mail, Jones, 9/15/2005 E-Mail Lyons J E, Contains NRC staff 4 NRC/NRR NRR, to Lyons, NRC/NRR analysis of NRR, Re: VY responses to EPU Issues. requests for additional information regarding condensate and feedwater system . -

14-24 ML052620321 Razzaque M E-mail; 9/15/2005 E-Mail Enniq R R. Contains NRC staff 9 M, NRC/NRR Razzaque, NRR, NRC/NRR discussion of to Ennis, Re: VY contents of draft EPU Supplement safety evaluation and

32. draft requests for additional information 14-25 ML052590108 Reddy D K, E-mail, Reddy, 9/15/2005 E-Mail Ennis R B, Contains NRC staff 2 NRC/NRR NRR, to Ennis, NRC/NRR discussion of NRR, Re: VY contents of draft EPU SBO Input. safety evaluation 14-26 ML052590060 Reddy D K, E-mail, Reddy, 9/15/2005 E-Mail Pal A N, Contains NRC staff 3 NRC/NRR NRR, to Pal, NRC/NRR discussion of NRR, Re: VY contents of draft EPU SBO Input. safety evaluation 7 of 14

PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 14- 09/29/05 (Reissued 01/19/06)

PDP Accession Author Title/ Document Document Addressee / Comment Page No. Number Name/

Description:

Date Type Addressee Count Affiliation: Affiliation 14-27 ML052590121 Scarbrough T E-mail, 9/15/2005 E-Mail Ennis R B, Contains NRC staff 2 G, NRC/NRR Scarbrough, NRC/NRR discussion regarding NRR, to Ennis, internal review NRR, Re: VY practices EPU Supplement 33.

14-28 ML052590132 Scarbrough T E-mail, 9/15/2005 E-Mail Ennis R B, Contains NRC staff 2 G, NRC/NRR Scarbrough, NRC/NRR discussion regarding KIPP to Pnnia interna2l reiew NRR, Re: V practices EPU Supplement 33.

14-29 ML052660070 Ennis R B, E-mail, Ennis, 9/15/2005 E-Mail Scarbrough T G, Contains NRC staff 2 NRC/NRR NRR, to NRC/NRR discussion regarding Scarbrough, internal review NRR, Et. Al., Re: practices VY EPU Supplement 33.

8 of 14

PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 14 - 09/29/05 (Reissued 01/19/06)

PDP Accession Author Title/ Document Document Addressee I Comment Page No. Number Name/

Description:

Date Type Addressee Count Affiliation: Affiliation 14-30 ML052640132 Ennis R B, E-mail, Ennis, 9/16/2005 E-Mail Imbro E V, Contains NRC staff 4 NRC/NRR NRR, to Imbro, NRC/NRR discussion of NRR, Re: VY contents of draft EPU GE Review. safety evaluation and draft requests for additional information 14-31 ML052640165 Grimes C I, E-mail, Grimes, 9/16/2005 E-Mail Marsh L B, Contains NRC staff 4 NRC/NRR NRR, to Mayfield Mayfield M E, analysis of and Marsh, MNOR NIO!NIO responses to Re: VY EPU requests for Steam Dryer. information regarding steam dryer review 14-32 ML052640148 Imbro E V, E-mail, Imbro, 9/16/2005 E-Mail Ennis R B, Contains NRC staff 4 NRC/NRR NRR, to Ennis, NRC/NRR discussion of internal NRR, Re: VY NRC staff scheduling EPU Review. practices and contents of draft safety evaluation 9 of 14

PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 14 - 09129/05 (Reissued 01/19/06)

PDP Accession Author Title/ Document Document Addressee / Comment Page No. Number Name/

Description:

Date Type Addressee Count Affiliation: Affiliation 14-33 ML052640150 Imbro E V, E-mail, Imbro, 9/16/2005 E-Mail Ennis R B, Contains NRC staff 4 NRC/NRR NRR, to Ennis, NRC/NRR discussion of internal NRR, Re: VY NRC staff scheduling EPU Review. practices and contents of draft safety evaluation 14-34 ML052620274 Ennis R B, E-mail, Ennis, 9/16/2005 E-Mail Jones S, Reddy Contains information 2 NRC/NRR NRR, to Reddy, D, Tatum J, regarding internal IR' rn, Re1. V I'dI 1l, 1II'I l , Iva La.II actI IVUI11 IV EPU Conference practices Call.

14-35 ML052620295 Ennis R B, E-mail, Ennis, 9/16/2005 E-Mail Roberts D J, Contains NRC staff 4 NRC/NRR NRR, to Roberts, NRC/NRR discussion of draft NRR, Et. Al., Re: safety evaluation and VY EPU Review. internal NRC staff scheduling practices 14-36 ML052640135 Abdullahi Z, E-mail, Abdullahi, 9/18/2005 E-Mail Ennis R B, Contains NRC staff 2 NRC/NRR NRR, to Ennis, NRC/NRR discussion of draft NRR, Re: VY safety evaluation and EPU GE internal NRC staff Conference call. scheduling practices 10 of 14

PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 14 - 09/29/05 (Reissued 01/19/06)

PDP Accession Author Title/ Document Document Addressee / Comment Page No. Number Name/

Description:

Date Type Addressee Count Affiliation: Affiliation 14-37 ML052640141 Alexion T W, E-mail, Alexion, 9/19/2005 E-Mail Ennis R B, Contains NRC staff 2 NRC/NRR NRR, to Ennis, NRC/NRR discussion regarding NRR, Re: VY internal review EPU Testing. practices 14-38 ML052640122 Ennis R B, E-mail, Ennis, 9/19/2005 E-Mail Marsh T B, Contains information 2 NRC/NRR NRR, to Marsh, NRC/NRR regarding internal NRR, Re: VY NRC staff scheduling EPU Steam practices Conference Calls.

14-39 ML052640155 Marsh L B, E-mail, Marsh, 9/19/2005 E-Mail Alexion T W, Contains NRC staff 2 NRC/NRR NRR, to Alexion, NRC/NRR discussion regarding NRR, Re: VY internal review EPU Testing. practices 14-40 ML052640143 Marsh L B, E-mail, Marsh, 9/19/2005 E-Mail Ennis R B, Contains information 2 NRC/NRR NRR, to Ennis, NRC/NRR regarding internal NRR, Re: VY NRC staff scheduling EPU Conference practices Calls.

11 of 14

PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 14 - 09/29/05 (Reissued 01/19/06)

PDP Accession Author Title/ Document Document Addressee / Comment Page No. Number Name/

Description:

Date Type Addressee Count Affiliation: Affiliation 14-41 ML052640138 Marsh L B, E-mail, Marsh, 9/19/2005 E-Mail Ennis R B, Contains NRC staff 2 NRC/NRR NRR, to Ennis, NRC/NRR discussion of NRR, Re: VY responses to EPU Supplement requests for

34. additional information regarding steam dryer load 14-42 ML052640160 Thatcher D F, E-mail, Thatcher, 9/19/2005 E-Mail Alexion T W, Contains NRC staff 2 NRC/NRR NRR to Alexion, NRC/NRR discussion regarding NRR, Re: VY internal review EPU Testing. practices 14-43 ML052640415 Akstulewicz F E-mail 9/20/2005 E-Mail Holden C F, Contains NRC staff 3 M, NRC/NRR Akstulewicz, NRC/NRR analysis of NRR, to Holden, responses to NRR, Et. Al., Re: requests for VY EPU SRXB additional information Status.

14-44 ML052640419 Jones S R, E-mail Jones, 9/20/2005 E-Mail Ennis R B, Contains information 2 NRC/NRR NRR, to Ennis, NRC/NRR regarding internal NRR, Et. Al., Re: NRC staff scheduling VY EPU practices Conference Call.

12 of 14

PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 14 - 09/29/05 (Reissued 01/19/06)

PDP Accession Author Title/ Document Document Addressee / Comment Page No. Number Name/

Description:

Date Type Addressee Count Affiliation: Affiliation 14-45 ML052640424 Reddy D K, E-mail Reddy, 9/20/2005 E-Mail Ennis R B, Contains information 3 NRC/NRR NRR, to Ennis, NRC/NRR regarding internal NRR, Et. Al., Re: NRC staff scheduling VY EPU practices Conference Call.

14-46 ML052640417 Tatum J E, E-mail Tatum, 9/20/2005 E-Mail Ennis R B, Contains information 2 NRC/NRR NRR, to Ennis, NRC/NRR regarding internal NRR, Et. Al., Re: NRC staff scheduling V EPI I nrac-tiacs Conference Call.

14-47 ML052640432 Ennis R B, E-mail, Ennis, 9/20/2005 E-Mail Reddy D K, Contains information 3 NRC/NRR NRR, to Reddy, NRC/NRR regarding internal NRR, Et. Al., Re: NRC staff scheduling VY EPU practices Conference Call.

14-48 ML052640412 Marsh L B, E-mail Marsh, 9/21/2005 E-Mail Boger B A, Contains information 3 NRC/NRR NRR, to Boger, NRC/NRR regarding internal NRR, Et. Al., Re: NRC staff scheduling VY EPU SE practices Inputs. _ _

13 of 14

PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 14 - 09/29/05 (Reissued 01/19/06)

PDP Accession Author Title/ Document Document Addressee / Comment Page No. Number Name/

Description:

Date Type Addressee Count Affiliation: Affiliation 14-49 ML052650195 Ennis R B, E-mail, Ennis, 9/21/2005 E-Mail Grimes C I, Contains information 3 NRC/NRR NRR, to Grimes, NRC/NRR regarding internal NRR, Re: VY NRC staff scheduling EPU practices Communications.

14-50 ML052650197 Grimes C 1, E-mail, Grimes, 9/21/2005 E-Mail Scarbrough T G, Contains NRC staff 2 NRC/NRR NRR, to NRC/NRR discussion regarding Scarbrough, internal review NRR, Et A!,Re: practices VY EPU Communications.

14-51 ML052650086 Jones S R, E-mail, Jones, 9/21/2005 E-Mail Ennis R B, Contains NRC staff 2 NRC/NRR NRR, to Ennis, NRC/NRR recommendations NRR, Re: VY regarding content of EPU License draft safety Condition. evaluation 14 of 14

VERMONT YANKEE EPU HEARING FILE AND MANDATORY DISCLOSURES PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 15 - October 31, 2005 Reissued January 19, 20061 Certain documents otherwise subject to inclusion in the hearing file and mandatory disclosures for this proceeding have been determined by the NRC Staff to contain information subject to withholding from public disclosure as predecisional, deliberative information. Pursuant to 10 C.F.R.

§ 2.336(b)(5), the Staff is providing this log to identify the following documents, withheld under the "deliberative process" privilege.

PDP Accession Author Title/ Document Document Addressee / Comment Page No. Number Name/

Description:

Date Type Addressee Count Affiliation: Affiliation 15-01 ML052710076 Ennis R B, E-mail, Ennis, 9/22/2005 E-Mail Akstulewicz F Contains information 2 NRC/NRR NRR to M, NRC/NRR concerning NRC Akstulewicz, Staff scheduling NRR, Re: VY practices EPU Conference Call.

15-02 ML052650199 Grimes C I, E-mail, Grimes, 9/22/2005 E-Mail Ennis R B, Contains information 2 NRC/NRR NRR, to Ennis, NRC/NRR concerning NRC NRR Re: VY Staff review practices EPU (Redacted version Communications. will be made available in Supplement 16) 1The Director of the Division of Operating Reactor Licensing, Catherine Haney, has decided on behalf of the NRC that all of the documents listed in this privilege log should be withheld from public disclosure under the deliberative process privilege.

1 of 13

PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 15 - 10/31/05 (Reissued 01/19/06)

PDP Accession Author Title/ Document Document Addressee / Comment Page No. Number Name/

Description:

Date Type Addressee Count Affiliation: Affiliation 15-03 ML052710080 Kotzalas M A, E-mail, Kolzalas, 9/22/2005 E-Mail Ennis R B, Contains NRC Staff 5 NRC/NRR NRR, to Ennis, NRC/NRR recommended input NRR, Re: VY to draft SER EPU SBO Input. regarding effect of EPU on station blackout 15-04 ML052710041 Sekerak S P, E-mail, Sekerak, 9/23/2005 E-Mail Wu C, Contains NRC Staff 11 NRC/NRR NRR, to Wu, NRC/NRR recommended input NRR, Re: VY to draft SER EPU Draft SER regarding effect of Inp. o+

.II 1JtL. =DI I ,- 0DI supports, RPV internals and core support structures, and CRDM pressure boundary housing 15-05 ML052710044 Razzaque M E-mail, 9/26/2005 E-Mail Ennis R B, Contains NRC Staff M, NRC/NRR Razzaque, NRR, NRC/NRR discussion of draft to Ennis, NRR, RAls concerning Re: VY EPU LBLOCAs, fuel SRXB RAIs storage, and RHR 15-06 ML052710043 Ennis R B, E-mail, Ennis, 9/27/2005 E-Mail Razzaque M M, Contains NRC Staff NRC/NRR NRR, to NRC/NRR discussion of draft Razzaque, NRR, RAls concerning Re: VY EPU LBLOCAs, fuel SRXB RAls storage, and RHR 2 of 13

PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 15 - 10/31/05 (Reissued 01/1 9/06)

PDP Accession Author Title/ Document Document Addressee / Comment Page No. Number Name/

Description:

Date Type Addressee Count Affiliation: Affiliation 15-07 ML052710045 Huang T L, E-mail, Huang, 9/27/2005 E-Mail Ennis R B, Contains NRC Staff 2 NRC/NRR NRR, to Ennis, NRC/NRR discussion of draft NRR, Re: VY RAls concerning EPU SRXB RAls. LBLOCAs, fuel storage, and RHR 15-08 ML052720436 Ennis R B, E-mail, Ennis, 9/28/2005 E-Mail Akstulewicz F Contains information 4 NRC/NRR NRR, to M, NRC/NRR concerning NRC Akstulewicz, Staff reviewing and NRR, Et. Al., Re: scheduling practices VY EPU SE 15-09 ML052720447 Jones S R, E-mail, Jones, 9/28/2005 E-Mail Ennis R B, Contains information 2 NRC/NRR NRR, to Ennis, NRC/NRR concerning NRC NRR, Re: VY Staff reviewing and EPU SE Status. scheduling practices 15-10 ML052720444 Kotzalas M A, E-mail, Kotzalas, 9/28/2005 E-Mail Ennis R B, Contains information 2 NRC/NRR NRR, to Ennis, NRC/NRR concerning NRC NRR, Re: VY Staff reviewing and EPU SE Status. scheduling practices 3 of 13

PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 15 - 10/31/05 (Reissued 01/19/06)

PDP Accession Author Title/ Document Document Addressee I Comment Page No. Number Name/

Description:

Date Type Addressee Count Affiliation: Affiliation 15-11 ML052790699 Thatcher D F, Draft Safety 9/29/2005 Memoranda Roberts D J, Contains NRC Staff 18 NRC/NRR/DI Evaluation Power Safety NRC/NRR/DLP recommended input PM/IPSB Ascension Evaluation M/LPD2 to draft SER Testing for regarding power Vermont Yankee, ascension testing Dated September 10, 2003.

15-12 ML052720443 Fischer D C, E-mail, Fischer, 9/29/2005 E-Mail Ennis R B, Contains information 2 NRC/NRR NRR, to Ennis, NRC/NRR concerning NRC NRR, Re: VY Staff reviewing and EPU SE Status scheduling practices 15-13 ML052790091 Pal A N, E-mail, Pal, NRR, 9/29/2005 E-Mail Ennis R B, Contains information 2 NRC/NRR to Ennis, NRR, NRC/NRR concerning NRC Re: VY EPU SE Staff reviewing and Status. scheduling practices 15-14 ML052790087 Pettis R L, E-mail, Pettis, 9/29/2005 E-Mail Ennis R B, Contains information 2 NRC/NRR NRR, to Ennis, NRC/NRR concerning NRC NRR, Re: VY Staff reviewing and EPU SE Status scheduling practices 15-15 ML052730071 Jenkins R V, Vermont Yankee: 9/29/2005 Memoranda Roberts D J, Contains NRC Staff 15 NRC/NRR/DE Thermal Power Safety NRC/NRR/DLP recommended input

/EEIB Uprate - Station Evaluation M/LPD2 to draft SER Blackout. regarding station blackout 4 of 13

PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 15 - 10/31/05 (Reissued 01/19/06)

PDP Accession Author Title/ Document Document Addressee I Comment Page No. Number Name/

Description:

Date Type Addressee Count Affiliation: Affiliation 15-16 ML052790059 Jones S R, E-mail, Jones, 9/30/2005 E-Mail Tatum J E, Contains NRC Staff 2 NRC/NRR NRR, to Tatum, NRC/NRR discussion of draft NRR, Re: VY license condition EPU License regarding transient Condition. testing 15-17 ML052790061 Jones S R, E-mail, Jones, 9/30/2005 E-Mail Tatum J E, Contains NRC Staff 2 NRC/NRR NRR, to Tatum, NRC/NRR discussion of draft NRR, Re: VY license condition EPU License regarding transient onnditio.nn testing 15-18 ML052790063 Jones S R, E-mail, Jones, 9/30/2005 E-Mail Tatum J E, Contains NRC Staff 2 NRC/NRR NRR, to Tatum, NRC/NRR discussion of draft NRR, Re: VY license condition EPU License regarding transient Condition. testing 15-19 ML052790064 Tatum J E, E-mail, Tatum, 9/30/2005 E-Mail Jones S R, Contains NRC Staff 2 NRC/NRR NRR, to Jones, NRC/NRR discussion of draft NRR, Re: VY license condition EPU License regarding transient Condition. testing 5 of 13

PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 15 - 10/31/05 (Reissued 01/19/06)

PDP Accession Author Title/ Document Document Addressee / Comment Page No. Number Name/

Description:

Date Type Addressee Count Affiliation: Affiliation 15-20 ML052790068 Tatum J E, E-mail, Tatum, 9/30/2005 E-Mail Jones J R, Contains NRC Staff 2 NRC/NRR NRR, to Jones, NRC/NRR discussion of draft NRR, Re: VY license condition EPU License regarding transient Condition. testing 15-21 ML052790066 Tatum J E, E-mail, Tatum, 9/30/2005 E-Mail Jones S R, Contains NRC Staff 2 NRC/NRR NRR, to Jones, NRC/NRR discussion of draft NRR, Re: WY license condition EPU License regarding transient 15-22 ML052730335 Manoly K A, Safety Evaluation 9/30/2005 Memoranda Roberts D J, Contains NRC Staff 40 NRC/NRR/DE of Vermont Safety NRC/NRR/DLP recommended input

/EMEB Yankee Nuclear Evaluation M/LPD1 to draft SER Power Station, regarding structural License No. and pressure DPR-28 (Docket boundary integrity of No. 50-271), various systems, Technical effect of EPU on Specification condensate and Proposed feedwater system, Change No. 263, and performance of Extended Power safety-related valves Uprate.

6 of 13

PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 15 - 10/31/05 (Reissued 01/19/06)

PDP Accession Author Title/ Document Document Addressee / Comment Page No. Number Name/

Description:

Date Type Addressee Count Affiliation: Affiliation 15-23 ML052730219 Dennig R L, Safety Evaluation 9/30/2005 Memoranda Roberts D J, Contains NRC Staff 38 NRC/NRR/DS Report Input - NRC/NRR/DLP recommended input SA/SPSB Review of M/LPD1 to draft SER Containment regarding Systems and containment system Analysis for the safety Vermont Yankee Nuclear Power Station Extended Power Uprate (TAC IVIC76i) 15-24 ML052710446 Jones S R, Vermont Yankee 9/30/2005 Memoranda Roberts D J, Contains NRC Staff 28 NRC/NRR/DS EPU SPLB-A NRC/NRR/DLP recommended input SANSPLB BOP Input. M/LPD1 to draft SER regarding balance of plant systems 15-25 ML052790105 Ennis R B, E-mail, Ennis, 10/1/2005 E-Mail Scarbrough T G, Contains NRC Staff 11 NRC/NRR NRR, to NRC/NRR discussion of draft Scarbrough, license condition NRR, Re: VY regarding potential EPU Steam adverse flow effects Dryer License Conditions.

7 of 13

PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 15 - 10/31/05 (Reissued 01/19/06)

PDP Accession Author Title/ Document Document Addressee / Comment Page No. Number Name/

Description:

Date Type Addressee Count Affiliation: Affiliation 15-26 ML052790121 Akstulewicz F E-mail, 10/3/2005 E-Mail Ennis R B, Contains NRC Staff 2 M, NRC/NRR Akstulewicz, NRC/NRR discussion of draft NRR, to Ennis, license condition NRR, Re: VY regarding potential EPU SLMCPR. adverse flow effects 15-27 ML052790130 Ennis R B, E-mail, Ennis, 10/3/2005 E-Mail Akstulewicz F Contains NRC Staff 2 NRC/NRR NRR, to M, NRC/NRR discussion of draft Akstulewicz, license condition NRR, Re: VY regarding potential EPU SLMCPR. adverse flow effects 15-28 ML052790084 Scarbrough T E-mail, 10/3/2005 E-Mail Ennis R B, Contains NRC Staff 2 G, NRC/NRR Scarbrough, NRC/NRR discussion of draft NRR, to Ennis, license condition NRR, Re: VY regarding potential EPU License adverse flow effects Conditions.

15-29 ML052790050 Scarbrough T E-mail, 10/3/2005 E-Mail Ennis R B, Contains NRC Staff 3 G, NRC/NRR Scarbrough, NRC/NRR discussion of draft NRR, to Ennis, license condition NRR, Re: VY regarding potential EPU License adverse flow effects Conditions.

8 of 13

PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 15 - 10/31/05 (Reissued 01/19/06)

PDP Accession Author Title/ Document Document Addressee I Comment Page No. Number Name/

Description:

Date Type Addressee Count Affiliation: Affiliation 15-30 ML052770442 Rubin M P, Safety Evaluation 10/3/2005 Memoranda Roberts D J, Contains NRC Staff 20 NRC/NRR/DS Report Input Safety NRC/NRR/DLP recommended input SA/SPSB Concerning the Evaluation M/LPD1 to draft SER Risk Evaluation Report regarding risk of the Vermont evaluation Yankee Nuclear Power Station Extended Power Uprate Application (TAC No. MC0761).

15-31 ML052790065 Roberts D J, E-mail, Roberts, 10/4/2005 E-Mail Marsh L B, Contains information 2 NRC/NRR NRR, to Marsh, NRC/NRR concerning NRC NRR, Et. Al., Re: Staff reviewing and VY EPU License scheduling practices Condition.

15-32 ML052790043 Sheron B W, E-mail, Sheron, 10/4/2005 E-Mail Ennis R B, Contains NRC Staff 2 NRC/NRR NRR, to Ennis, NRC/NRR discussion of draft NRR, Et. Al., Re: license condition VY EPU License regarding risk-Conditions. informed evaluation of requested containment overpressure credit 9 of 13

PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 15 - 10/31/05 (Reissued 01/19/06)

PDP Accession Author Title/ Document Document Addressee I Comment Page No. Number Name/

Description:

Date Type Addressee Count Affiliation: Affiliation 15-33 ML052790132 Ennis R B, E-mail, Ennis, 10/5/2005 E-Mail Stutzke M A, Contains NRC Staff 6 NRC/NRR NRR, to Stutzke, NRC/NRR discussion of draft NRR, Re: VY license condition EPU License regarding risk-Condition. informed evaluation of requested containment overpressure credit 15-34 ML052790048 Marsh L B, E-mail, Marsh, 10/5/2005 E-Mail Ennis R B, Contains NRC Staff 3 NRr/NRR NRR, Ennis NRCNRR evaluations and NRR, Et. AL., Re: recommendations VY EPU License concerning press Conditions. release concerning issuing of license conditions 15-35 ML052790038 Stutzke M A, E-mail, Stutzke, 10/5/2005 E-Mail Ennis R B, Contains NRC Staff 4 NRC/NRR NRR, to Ennis, NRC/NRR discussion of draft NRR, Re: VY license condition EPU License regarding risk-Conditions. informed evaluation of requested containment overpressure credit 10 of 13

PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 15 - 10/31/05 (Reissued 01/19/06)

PDP Accession Author Title/ Document Document Addressee / Comment Page No. Number Name/

Description:

Date Type Addressee Count Affiliation: Affiliation 15-36 ML052790039 Stutzke M A, E-mail, Stutzke, 10/5/2005 E-Mail Ennis R B, Contains NRC Staff 3 NRC/NRR NRR, to Ennis, NRC/NRR discussion of draft NRR, Re: VY license condition EPU License regarding risk-Conditions. informed evaluation of requested containment overpressure credit 15-37 ML052850136 Scarbrough T E-mail, 10/7/2005 E-Mail Ennis R B, Contains NRC Staff 3 GJI ' 41.uI I'dI II a I Ug NI IIICIrIIIo.AeU IInIJUL NRR, to Ennis, to draft SER NRR, Re: VY regarding inspection EPU Inspections. follow-up items 15-38 ML052850151 Ennis R B, E-mail, Ennis, 10/8/2005 E-Mail Knutson E C, Contains NRC Staff 8 NRC/NRR NRR, to Sienel Sienel B E, recommended input and Knutson, NRC/RGN-I to draft SER RGN-1, Re: VY regarding inspection

_ EPU Inspections. follow-up items 11 of 13

PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 15 - 10/31/05 (Reissued 01/19/06)

PDP Accession Author Title/ Document Document Addressee / Comment Page No. Number Name/

Description:

Date Type Addressee Count Affiliation: Affiliation 15-39 ML052850051 Akstulewicz F Safety Evaluation 10/11/2005 Memoranda Roberts D J, Contains NRC Staff 64 M, Input for Safety NRC/NRR/DLP recommended input NRC/NRR/DS Extended Power Evaluation M/LPD1 to draft SER SA/SRXB Uprate Vermont regarding ECCS Yankee Nuclear LOCA and Methods Power Station Evaluation (TAC No.

MC0761) Section 2.8.7 and Revised Section 15-40 ML052900197 Ennis R B, E-mail, Ennis, 10/14/2005 E-Mail Reddy D K, Contains NRC Staff 4 NRC/NRR NRR, to Reddy, NRC/NRR analysis of licensee's NRR, Et. Al., Re: proposed VY EPU modification of draft Conference Call. license condition regarding transient testing 12 of 13

PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 15 - 10/31/05 (Reissued 01/19/06)

PDP Accession Author Title/ Document Document Addressee / Comment Page No. Number Name/

Description:

Date Type Addressee Count Affiliation: Affiliation 15-41 ML052900188 Jones S R, E-mail, Jones, 10/14/2005 E-Mail Reddy D K, Contains NRC Staff 3 NRC/NRR NRR, to Reddy, NRC/NRR analysis of licensee's NRR, Et. Al., Re: proposed VY EPU License modification of draft Condition. license condition regarding transient testing 15-42 ML052900185 Stutzke M A, E-mail, Stutzke, 10/14/2005 E-Mail Rubin M P, Contains NRC Staff 3 NRC/NRR NRR, to Rubin, NRC/NRR analysis of licensee's EPU containment Containment overpressure credit Overpressure. (Redacted version will be made available in Supplement 16) 15-43 ML052900195 Tatum J E, E-mail,Tatum, 10/14/2005 E-Mail Reddy D K, Contains NRC Staff 4 NRC/NRR NRR, to Reddy, NRC/NRR analysis of licensee's NRR, Et. Al., Re: proposed VY EPU modification of draft Conference Call. license condition regarding transient testing 13 of 13

VERMONT YANKEE EPU HEARING FILE AND MANDATORY DISCLOSURES PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 16 - November 14,2005 Reissued January 19, 2006' Certain documents otherwise subject to inclusion in the hearing file and mandatory disclosures for this proceeding have been determined by the NRC Staff to contain information subject to withholding from public disclosure as predecisional, deliberative information. Pursuant to 10 C.F.R.

§ 2.336(b)(5), the Staff is providing this log to identify the following documents, withheld under the "deliberative process" privilege.

PDP Accession Author Title/ Document Document Addressee I Comment Page No. Number Name/

Description:

Date Type Addressee Count Affiliation: Affiliation 16-01 ML053080208 Ennis R B, E-mail, Ennis, 10/27/2005 E-Mail, Richards S A, Contains NRC Staff 38 NRC/NRR NRR, to Slides and NRC/NRR recommendations Richards, NRR, Viewgraphs and discussion of Et. Al., Re: VY Staff presentation to EPU ACRS the ACRS Presentation.

16-02 ML053080206 Anderson C E-mail, 11/2/2005 E-Mail Ennis R B, Contains NRC Staff 3 J, NRC/RGN- Anderson, RGN- NRC/NRR discussion of I I, to Ennis, NRR, regional inspector's Re: VY EPU comments on Steam Dryer. preliminary results of VY steam dryer inspection

' The Director of the Division of Operating Reactor Licensing, Catherine Haney, has decided on behalf of the NRC that all of the documents listed in this privilege log should be withheld from public disclosure under the deliberative process privilege.

1 of 2

PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 16 - NOVEMBER 14,2005 (Reissued January 19, 2006)

PDP Accession Author Title/ Document Document Addressee I Comment Page No. Number Name/

Description:

Date Type Addressee Count Affiliation: Affiliation 16-03 ML053080203 Ennis R B, E-mail, Ennis, 11/2/2005 E-Mail Scarbrough T G, Contains NRC 3 NRC/NRR NRR, to NRC/NRR regional inspector's Scarbrough, comments on NRR, Et. AL., Re: preliminary results of VY EPU Steam VY steam dryer Dryer. inspection 16-04 ML053080204 Ennis R B, E-mail, Ennis, 11/2/2005 E-Mail Scarbrough T G, Contains regional 5 NRC/NRR NRR, to NRC/NRR inspector's Scarbrough, comments on NRR, Re: VY preliminary results of FPU Steam \Y steam dryer Dryer. inspection 16-05 ML053120102 Ennis R B, E-mail, Ennis, 11/3/2005 E-Mail, Jones S R, Contains NRC Staff 19 NRC/NRR NRR, to Jones, Letter NRC/NRR recommendations NRR, Et. Al., Re: and discussion of VY EPU Staff presentation to Supplement 41. the ACRS (Non-privileged material (Entergy's Supplement 41) available at ML053120378) 2 of 2

VERMONT YANKEE EPU HEARING FILE AND MANDATORY DISCLOSURES PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 17 - November 28, 2005 Reissued January 19, 20061 Certain documents otherwise subject to inclusion in the hearing file and mandatory disclosures for this proceeding have been determined by the NRC Staff to contain information subject to withholding from public disclosure as predecisional, deliberative information. Pursuant to 10 C.F.R.

§ 2.336(b)(5), the Staff is providing this log to identify the following documents, withheld under the "deliberative process" privilege.

PDP Accession Author Title/ Document Document Addressee / Comment Page No. Number Name/

Description:

Date Type Addressee Count Affiliation: Affiliation 17-01 ML053180027 Ennis R B, E-mail, Ennis, 11/3/2005 E-Mail Scarbrough T G, Contains NRC Staff 32 NRC/NRR NRR, to NRC/NRR discussion Scarbrough, concerning results of NRR, Et. Al., Re: VY steam dryer VY EPU Steam inspection.

Dryer Redacted version (factual information) will be made available for Supplement 18

' The Director of the Division of Operating Reactor Licensing, Catherine Haney, has decided on behalf of the NRC that all of the documents listed in this privilege log should be withheld from public disclosure under the deliberative process privilege.

1 of 2

PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 17 11/28/05 (Reissued 01/1 9106) 1W PDP Accession Author Title/ Document Document Addressee I Comment Page No. Number Name/

Description:

Date Type Addressee Count Affiliation: Affiliation 17-02 ML053180029 White J R, E-mail, White, 11/3/2005 E-Mail Ennis R B, Contains NRC Staff 30 NRC/RGN-1 RGN-1, to Ennis, NRC/NRR discussion NRR, Re: VY concerning results of EPU Steam VY steam dryer Dryer. inspection.

Redacted version (factual information) will be made available for Supplement 18 2 of 2

VERMONT YANKEE EPU HEARING FILE AND MANDATORY DISCLOSURES PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 18 - December 12,2005 Reissued January 19, 2006' Certain documents otherwise subject to inclusion in the hearing file and mandatory disclosures for this proceeding have been determined by the NRC Staff to contain information subject to withholding from public disclosure as predecisional, deliberative information. Pursuant to 10 C.F.R.

§ 2.336(b)(5), the Staff is providing this log to identify the following documents, withheld under the "deliberative process" privilege.

PDP Accession Author Title/ Document Document Addressee / Comment Page No. Number Name/

Description:

Date Type Addressee Count Affiliation: Affiliation 18-01 ML053320396 Stutzke M A, E-mail, Stutzke, 11/21/2005 E-Mail Ennis R B, Contains NRC Staff 4 NRC/NRR NRR, to Ennis, NRC/NRR member's proposed NRR, Re: VY RAls regarding EPU Entergy's probabilistic Supplements 38 risk analysis of and 39. containment overpressure (Note:

final version of RAls available at ML053260427)

' The Director of the Division of Operating Reactor Licensing, Catherine Haney, has decided on behalf of the NRC that all of the documents listed in this privilege log should be withheld from public disclosure under the deliberative process privilege.

1 of 2

u PRIVILEGE LOG - DELIBERATIVE PROCESS SUPPLEMENT 18 - 12/12/05 (Reissued 01/19/06) It PDP Accession Author Title/ Document Document Addressee / Comment Page No. Number Name/

Description:

Date Type Addressee Count Affiliation: Affiliation 18-02 ML053320402 Reddy D K, E-mail, Reddy, 11/22/2005 E-Mail Ennis R B, Contains NRC Staff 9 NRC/NRR NRR, to Ennis, NRC/NRR member's proposed NRR, Re: VY revisions to Sections EPU SE 2.5.4.4 (Condensate Revision. and Feedwater System) and 2.12 (Power Ascension Testing: BOP Systems Testing Review) of the Draft Safety Evaluation 2 of 2

I 0V UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of

)

ENTERGY NUCLEAR VERMONT YANKEE Docket No. 50-271 -OLA LLC and ENTERGY NUCLEAR OPERATIONS, INC. ASLBP No. 04-832-02-OLA (Vermont Yankee Nuclear Power Station)

CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing letter from Jason C. Zorn, Counsel for NRC Staff, to the Atomic Safety and Licensing Board, dated January 19, 2006, responding to the Licensing Board's December 21, 2005, Order, together with attachments, in the captioned proceeding have been served on the following. Service has been performed by deposit in the U.S. Mail, First Class; through electronic mail, with copies to follow by deposit in the NRC's internal mail system (as indicated by a single asterisk); or through electronic mail, with copies to follow by deposit in the U.S. Mail, First Class (as indicated by two asterisks), this 19t day of January, 2006.

Alex S. Karlin, Chair* Dr. Anthony J. Baratta*

Administrative Judge Administrative Judge Atomic Safety and Licensing Board Panel Atomic Safety and Licensing Board Panel Mail Stop T-3F23 Mail Stop T-3F23 U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Washington, DC 20555-0001 (E-mail: ask2@nrc.gov) (E-mail: ajb5@nrc.gov)

Lester S. Rubenstein** Office of the Secretary*

Administrative Judge ATTN: Rulemaking and Adjudications Staff Atomic Safety and Licensing Board Panel Mail Stop: 0-1 6C1 4760 East Country Villa Drive U.S. Nuclear Regulatory Commission Tucson, AZ 85718 Washington, DC 20555-0001 (E-mail: lesrrr@comcast.net) (E-mail: HEARINGDOCKET@nrc.gov)

Office of Commission Appellate John M. Fulton, Esq.

Adjudication* Assistant General Counsel Mail Stop: O-16C1 Entergy Nuclear Operations, Inc.

U.S. Nuclear Regulatory Commission 440 Hamilton Avenue Washington, DC 20555-0001 White Plains, NY 10601

I 1...

Jay E. Silberg, Esq.** Raymond Shadis**

Matias Travieso-Diaz, Esq.** Staff Technical Advisor Pillsbury Winthrop Shaw Pittman, LLP New England Coalition 2300 N St., NW P.O. Box 98 Washington, DC 20037-1128 Edgecomb, ME 04556 (E-mail: jay.silberg @pillsburylaw.com (E-mail: shadisQprexar.com matias.travieso-diaz ©pillsburylaw.com) shadis ©ime.net)

Sarah Hofmann, Esq.** Anthony Z. Roisman, Esq.**

Special Counsel National Legal Scholars Law Firm Department of Public Service 84 East Thetford Rd.

112 State Street - Drawer 20 Lyme, NH 03768 Montpelier, VT 05620-2601 (E-mail:

(E-mail: sarah.hofmann@state.vt.us) aroisman @nationallegalscholars.com)

Jonathan M. Rund, Esq.* Jared Lindsay, Esq.*

Law Clerk Law Clerk Atomic Safety and Licensing Board Panel Atomic Safety and Licensing Board Panel Mail Stop: T-3F23 Mail Stop: T-3F23 U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Washington, DC 20555-0001 (E-mail: imr3@nrc.pov) (E-mail: iilSnrc.aov)

Jasoh C. Zorn Counsel for NRC Staff